Award recordCONTRACT

J. W. FULLER CONSTRUCTION, L.L.C.

PIID VA255C1007· VHA· 255-NETWORK CONTRACT OFFICE 15· Z222 · MAINT-REP-ALT/HWYS-RDS-STS-BRDGS-RA· FY2010· $624,563 net obligations· UEI C6JJDQTNLSK5· MO

Description

NON-ARRA FUNDED WITHIN-SCOPE MODIFICATION TO ADD ADDITIONAL PARKING LOTS TO THE SOUTH PERIPHERY ROAD RECOVERY PROJECT.

Base award description: TAS::36 0158::TAS RECOVERY PROJECT 657A5-09-101, RELOCATE SOUTH PERIPHERY ROAD, WHICH IS LOCATED AT THE MARION, IL, VA MEDICAL CENTER.

First action · last action
2010-03-12 · 2011-05-13
Transactions
5
First transaction's obligation
$336,156
Base + all options value (sum of deltas)
$624,563
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
6
SDVOSB flag on record
Yes (self-representation)
NAICS
237310 · HIGHWAY, STREET, AND BRIDGE CONSTRUCTION

Modification chain · 5 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$624,563$0Base award · 2010-03-12 · this action $336,156 · running total $336,156Modification 1 · 2010-06-11 · this action $203,254 · running total $539,410Modification 2 · 2010-11-30 · this action $0 · running total $539,410Modification 3 · 2011-01-14 · this action $0 · running total $539,410Modification 4 · 2011-05-13 · this action $85,153 · running total $624,563
  • Base2010-03-12+$336,156= $336,156
  • Mod 12010-06-11+$203,254= $539,410
  • Mod 22010-11-30+$0= $539,410
  • Mod 32011-01-14+$0= $539,410
  • Mod 42011-05-13+$85,153= $624,563
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2010-03-12+$336,156$336,156TAS::36 0158::TAS RECOVERY PROJECT 657A5-09-101, RELOCATE SOUTH PERIPHERY ROAD, WHICH IS LOCATED AT THE MARIO…
Mod 1· CHANGE ORDER2010-06-11+$203,254$539,410TAS::36 0158::TAS WITHIN-SCOPE MODIFICATION TO ADD ADDITIONAL STREET LIGHTS TO THE SOUTH PERIPHERY ROAD RECOV…
Mod 2· CHANGE ORDER2010-11-30+$0$539,410TAS::36 0158::TAS WITHIN-SCOPE MODIFICATION TO ADD ADDITIONAL STREET LIGHTS TO THE SOUTH PERIPHERY ROAD RECOV…
Mod 3· CHANGE ORDER2011-01-14+$0$539,410WITHIN-SCOPE NO-COST MODIFICATION EXTEND THE COMPLETION DATE OF THE SOUTH PERIPHERY ROAD RECOVERY PROJECT.
Mod 4· CHANGE ORDER2011-05-13+$85,153$624,563NON-ARRA FUNDED WITHIN-SCOPE MODIFICATION TO ADD ADDITIONAL PARKING LOTS TO THE SOUTH PERIPHERY ROAD RECOVERY…

Related awards · 6

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI C6JJDQTNLSK5)

AwardOffice · PSC / listingNet obligationsFY
36C25519C0035255-NETWORK CONTRACT OFFICE 15 (36C255) · J063 · MAINT/REPAIR/REBUILD OF EQUIPMENT- ALARM, SIGNAL, AND SECURITY DETECTION SYSTEMS$218,400FY2019
36C78618C0219NATIONAL CEMETERY ADMIN (36C786) · N099 · INSTALLATION OF EQUIPMENT- MISCELLANEOUS$31,000FY2018
36C78618C0215NATIONAL CEMETERY ADMIN (36C786) · J042 · MAINT/REPAIR/REBUILD OF EQUIP- FIRE FIGHTING/RESCUE/SAFETY EQUIP; ENVIRON PROTECT EQUIP/MATLS$18,365FY2018
36C78618C0130NATIONAL CEMETERY ADMIN (36C786) · 5430 · STORAGE TANKS$128,500FY2018
VA25517J4311255-NETWORK CONTRACT OFFICE 15 (36C255) · Z2DZ · REPAIR OR ALTERATION OF OTHER HOSPITAL BUILDINGS$1,000FY2017