Description
PROJECT 589-754 CREATE A NEW STERILE PROCESSING SERVICE AREA FOR THE SURGERY DEPARTMENT AT THE WICHITA VA MEDICAL CENTER.
Base award description: IGF::OT::IGF PROJECT 589-754 CREATE A NEW STERILE PROCESSING SERVICE AREA FOR THE SURGERY DEPARTMENT AT THE WICHITA VA MEDICAL CENTER.
Modification chain · 19 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2017-08-18+$8,214,356= $8,214,356
- Mod P000022018-05-09+$91,429= $8,305,785
- Mod P000032018-08-27+$67,137= $8,372,922
- Mod P000012018-09-19+$19,343= $8,392,265
- Mod P000042019-02-11+$81,770= $8,474,035
- Mod P000062019-06-04+$28,218= $8,502,254
- Mod P000072019-06-06+$44,181= $8,546,435
- Mod P000052019-08-06+$38,738= $8,585,172
- Mod P000092019-08-08+$26,971= $8,612,143
- Mod P000082019-08-29+$184,093= $8,796,236
- Mod P000112019-08-29+$9,100= $8,805,336
- Mod P000122019-08-29+$38,090= $8,843,427
- Mod P000102019-09-03+$59,835= $8,903,262
- Mod P000132019-09-20+$46,156= $8,949,418
- Mod P000142019-09-20+$14,937= $8,964,355
- Mod P000152019-09-20+$1,083= $8,965,438
- Mod P000162020-03-04+$23,808= $8,989,246
- Mod P000172020-04-23+$85,364= $9,074,610
- Mod P000182020-05-05+$61,354= $9,135,964
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2017-08-18 | +$8,214,356 | $8,214,356 | IGF::OT::IGF PROJECT 589-754 CREATE A NEW STERILE PROCESSING SERVICE AREA FOR THE SURGERY DEPARTMENT AT THE W… |
| Mod P00002· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2018-05-09 | +$91,429 | $8,305,785 | IGF::OT::IGF PROJECT 589-754 MODIFICATION TO MOVE THE ELECTRICAL DUCT BANK. |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-08-27 | +$67,137 | $8,372,922 | IGF::OT::IGF PROJECT 589-754 MODIFICATION TO MOVE THE ELECTRICAL DUCT BANK AND CORRECT FOOTINGS. |
| Mod P00001· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2018-09-19 | +$19,343 | $8,392,265 | IGF::OT::IGF PROJECT 589-754 CREATE A NEW STERILE PROCESSING SERVICE AREA FOR THE SURGERY DEPARTMENT AT THE W… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-02-11 | +$81,770 | $8,474,035 | IGF::OT::IGF PROJECT 589-754 CREATE A NEW STERILE PROCESSING SERVICE AREA FOR THE SURGERY DEPARTMENT AT THE W… |
| Mod P00006· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2019-06-04 | +$28,218 | $8,502,254 | IGF::OT::IGF PROJECT 589-754 CREATE A NEW STERILE PROCESSING SERVICE AREA FOR THE SURGERY DEPARTMENT AT THE W… |
| Mod P00007· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2019-06-06 | +$44,181 | $8,546,435 | IGF::OT::IGF PROJECT 589-754 CREATE A NEW STERILE PROCESSING SERVICE AREA FOR THE SURGERY DEPARTMENT AT THE W… |
| Mod P00005· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2019-08-06 | +$38,738 | $8,585,172 | PROJECT 589-754 CREATE A NEW STERILE PROCESSING SERVICE AREA FOR THE SURGERY DEPARTMENT AT THE WICHITA VA MEDI… |
| Mod P00009· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2019-08-08 | +$26,971 | $8,612,143 | PROJECT 589-754 CREATE A NEW STERILE PROCESSING SERVICE AREA FOR THE SURGERY DEPARTMENT AT THE WICHITA VA MEDI… |
| Mod P00008· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2019-08-29 | +$184,093 | $8,796,236 | MODIFICATION P00008 REA PROJECT 589-754 CREATE A NEW STERILE PROCESSING SERVICE AREA FOR THE SURGERY DEPARTMEN… |
| Mod P00011· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2019-08-29 | +$9,100 | $8,805,336 | MOD P00011 PROJECT 589-754 CREATE A NEW STERILE PROCESSING SERVICE AREA FOR THE SURGERY DEPARTMENT AT THE WICH… |
| Mod P00012· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2019-08-29 | +$38,090 | $8,843,427 | PROJECT 589-754 CREATE A NEW STERILE PROCESSING SERVICE AREA FOR THE SURGERY DEPARTMENT AT THE WICHITA VA MEDI… |
| Mod P00010· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2019-09-03 | +$59,835 | $8,903,262 | PROJECT 589-754 CREATE A NEW STERILE PROCESSING SERVICE AREA FOR THE SURGERY DEPARTMENT AT THE WICHITA VA MEDI… |
| Mod P00013· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2019-09-20 | +$46,156 | $8,949,418 | PROJECT 589-754 CREATE A NEW STERILE PROCESSING SERVICE AREA FOR THE SURGERY DEPARTMENT AT THE WICHITA VA MEDI… |
| Mod P00014· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2019-09-20 | +$14,937 | $8,964,355 | PROJECT 589-754 CREATE A NEW STERILE PROCESSING SERVICE AREA FOR THE SURGERY DEPARTMENT AT THE WICHITA VA MEDI… |
| Mod P00015· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2019-09-20 | +$1,083 | $8,965,438 | PROJECT 589-754 CREATE A NEW STERILE PROCESSING SERVICE AREA FOR THE SURGERY DEPARTMENT AT THE WICHITA VA MEDI… |
| Mod P00016· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2020-03-04 | +$23,808 | $8,989,246 | PROJECT 589-754 CREATE A NEW STERILE PROCESSING SERVICE AREA FOR THE SURGERY DEPARTMENT AT THE WICHITA VA MEDI… |
| Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-04-23 | +$85,364 | $9,074,610 | PROJECT 589-754 CREATE A NEW STERILE PROCESSING SERVICE AREA FOR THE SURGERY DEPARTMENT AT THE WICHITA VA MEDI… |
| Mod P00018· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2020-05-05 | +$61,354 | $9,135,964 | PROJECT 589-754 CREATE A NEW STERILE PROCESSING SERVICE AREA FOR THE SURGERY DEPARTMENT AT THE WICHITA VA MEDI… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI ZHRKJX5UGJY7)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C25526N0400 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $497,781 | FY2026 |
| 36C25526N0357 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $39,658 | FY2026 |
| 36C25526N0326 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $406,387 | FY2026 |
| 36C25526N0346 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $188,393 | FY2026 |
| 36C25526N0324 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $497,136 | FY2026 |
| 36C25526N0325 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $486,203 | FY2026 |
Other recipients under Z2DA from 255-NETWORK CONTRACT OFFICE 15 (36C255) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C25526C0062 | RECON CONSTRUCTION SPECIALTIES LLC | 255-NETWORK CONTRACT OFFICE 15 (36C255) | $3,077,750 | FY2026 |
| 36C25526C0057 | ONSITE CONSTRUCTION GROUP LLC | 255-NETWORK CONTRACT OFFICE 15 (36C255) | $2,779,646 | FY2026 |
| 36C25526C0034 | RECON CONSTRUCTION SPECIALTIES LLC | 255-NETWORK CONTRACT OFFICE 15 (36C255) | $8,985,750 | FY2026 |
| 36C25526N0332 | FLOYD CONSTRUCTION CORP | 255-NETWORK CONTRACT OFFICE 15 (36C255) | $24,615 | FY2026 |
| 36C25526C0041 | PERSONS SERVICES CORP. | 255-NETWORK CONTRACT OFFICE 15 (36C255) | $3,367,000 | FY2026 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA25517C0172_3600_-NONE-_-NONE- · retrieved 2026-09-26.