Description
IGF::OT::IGF PROJECT NO. 589A7-15-100 REPLACE CHILLER AND AIR HANDLING UNITS BUILDINGS 19&60
Modification chain · 4 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2015-09-25+$620,322= $620,322
- Mod P000022016-01-25+$0= $620,322
- Mod P000012016-03-14+$34,878= $655,200
- Mod P000032016-06-06+$0= $655,200
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2015-09-25 | +$620,322 | $620,322 | IGF::OT::IGF PROJECT NO. 589A7-15-100 REPLACE CHILLER AND AIR HANDLING UNITS BUILDINGS 19&60 |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-01-25 | +$0 | $620,322 | IGF::OT::IGF PROJECT NO. 589A7-15-100 REPLACE CHILLER AND AIR HANDLING UNITS BUILDINGS 19&60 |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-03-14 | +$34,878 | $655,200 | IGF::OT::IGF PROJECT NO. 589A7-15-100 REPLACE CHILLER AND AIR HANDLING UNITS BUILDINGS 19&60 |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-06-06 | +$0 | $655,200 | IGF::OT::IGF PROJECT NO. 589A7-15-100 REPLACE CHILLER AND AIR HANDLING UNITS BUILDINGS 19&60 |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI XDNKT3LJCKL7)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C25520P0105 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · J041 · MAINT/REPAIR/REBUILD OF EQUIPMENT- REFRIGERATION, AIR CONDITIONING, AND AIR CIRCULATING EQUIPMENT | $219,983 | FY2020 |
| VA25516C0151 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $1,145,460 | FY2016 |
| VA25516P3540 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · J045 · MAINT/REPAIR/REBUILD OF EQUIPMENT- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT | $24,147 | FY2016 |
| VA25516P3063 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · N067 · INSTALLATION OF EQUIPMENT- PHOTOGRAPHIC EQUIPMENT | $14,322 | FY2016 |
| VA25516C0126 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $871,965 | FY2016 |
| VA25516C0118 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $753,878 | FY2016 |
Other recipients under Z1DA from 255-NETWORK CONTRACT OFFICE 15 (36C255) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C25526N0385 | ONSITE CONSTRUCTION GROUP LLC | 255-NETWORK CONTRACT OFFICE 15 (36C255) | $88,559 | FY2026 |
| 36C25526C0060 | BKM CONSTRUCTION LLC | 255-NETWORK CONTRACT OFFICE 15 (36C255) | $739,012 | FY2026 |
| 36C25526N0308 | GUARANTEE INTERIORS, INC. | 255-NETWORK CONTRACT OFFICE 15 (36C255) | $318,556 | FY2026 |
| 36C25526N0238 | GUARANTEE INTERIORS, INC. | 255-NETWORK CONTRACT OFFICE 15 (36C255) | $249,795 | FY2026 |
| 36C25526C0028 | RECON CONSTRUCTION SPECIALTIES LLC | 255-NETWORK CONTRACT OFFICE 15 (36C255) | $294,750 | FY2026 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA25515C0197_3600_-NONE-_-NONE- · retrieved 2026-09-26.