Award recordCONTRACT

CA SERVICES, LLC

PIID VA251C0852· VHA· 506-ANN ARBOR· Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY· FY2010· $4,087,373 net obligations· UEI FLNJUCT58UN1· MI

Description

CONSTRUCT 2ND LINEAR ACCELERATOR

First action · last action
2010-06-25 · 2014-10-02
Transactions
20
First transaction's obligation
$2,645,000
Base + all options value (sum of deltas)
$4,087,373
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
6
SDVOSB flag on record
Yes (self-representation)
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION

Modification chain · 20 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$4,087,373$0Base award · 2010-06-25 · this action $2,645,000 · running total $2,645,000Modification 1 · 2011-02-25 · this action $191,744 · running total $2,836,744Modification COA · 2011-03-25 · this action $62,194 · running total $2,898,938Modification COB · 2011-03-25 · this action $27,000 · running total $2,925,938Modification 2 · 2011-06-08 · this action $87,245 · running total $3,013,183Modification 3 · 2011-07-01 · this action -$2,065 · running total $3,011,118Modification 4 · 2011-07-01 · this action -$2,108 · running total $3,009,010Modification 5 · 2011-07-01 · this action $144,221 · running total $3,153,230Modification 6 · 2011-08-27 · this action $237,298 · running total $3,390,528Modification P00007 · 2011-12-21 · this action $0 · running total $3,390,528Modification P00008 · 2012-01-24 · this action $0 · running total $3,390,528Modification P00009 · 2012-02-07 · this action $0 · running total $3,390,528Modification 11 · 2012-07-30 · this action $48,021 · running total $3,438,550Modification 12 · 2012-07-30 · this action $12,102 · running total $3,450,652Modification 13 · 2012-07-30 · this action $23,782 · running total $3,474,434Modification P00010 · 2012-07-30 · this action $0 · running total $3,474,434Modification P00014 · 2013-05-28 · this action $6,247 · running total $3,480,681Modification P00015 · 2014-08-04 · this action $192,611 · running total $3,673,292Modification P00016 · 2014-08-04 · this action $403,486 · running total $4,076,778Modification P00017 · 2014-10-02 · this action $10,595 · running total $4,087,373
  • Base2010-06-25+$2,645,000= $2,645,000
  • Mod 12011-02-25+$191,744= $2,836,744
  • Mod COA2011-03-25+$62,194= $2,898,938
  • Mod COB2011-03-25+$27,000= $2,925,938
  • Mod 22011-06-08+$87,245= $3,013,183
  • Mod 32011-07-01-$2,065= $3,011,118
  • Mod 42011-07-01-$2,108= $3,009,010
  • Mod 52011-07-01+$144,221= $3,153,230
  • Mod 62011-08-27+$237,298= $3,390,528
  • Mod P000072011-12-21+$0= $3,390,528
  • Mod P000082012-01-24+$0= $3,390,528
  • Mod P000092012-02-07+$0= $3,390,528
  • Mod 112012-07-30+$48,021= $3,438,550
  • Mod 122012-07-30+$12,102= $3,450,652
  • Mod 132012-07-30+$23,782= $3,474,434
  • Mod P000102012-07-30+$0= $3,474,434
  • Mod P000142013-05-28+$6,247= $3,480,681
  • Mod P000152014-08-04+$192,611= $3,673,292
  • Mod P000162014-08-04+$403,486= $4,076,778
  • Mod P000172014-10-02+$10,595= $4,087,373
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2010-06-25+$2,645,000$2,645,000CONSTRUCT 2ND LINEAR ACCELERATOR
Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-02-25+$191,744$2,836,744CONSTRUCT 2ND LINEAR ACCELERATOR
Mod COA· CHANGE ORDER2011-03-25+$62,194$2,898,938CONSTRUCT 2ND LINEAR ACCELERATOR
Mod COB· CHANGE ORDER2011-03-25+$27,000$2,925,938CONSTRUCT 2ND LINEAR ACCELERATOR
Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-06-08+$87,245$3,013,183CONSTRUCT 2ND LINEAR ACCELERATOR
Mod 3· CHANGE ORDER2011-07-01−$2,065$3,011,118CONSTRUCT 2ND LINEAR ACCELERATOR
Mod 4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-07-01−$2,108$3,009,010CONSTRUCT 2ND LINEAR ACCELERATOR
Mod 5· CHANGE ORDER2011-07-01+$144,221$3,153,230CONSTRUCT 2ND LINEAR ACCELERATOR
Mod 6· CHANGE ORDER2011-08-27+$237,298$3,390,528CONSTRUCT 2ND LINEAR ACCELERATOR
Mod P00007· CHANGE ORDER2011-12-21+$0$3,390,528CONSTRUCT 2ND LINEAR ACCELERATOR
Mod P00008· CHANGE ORDER2012-01-24+$0$3,390,528CONSTRUCT 2ND LINEAR ACCELERATOR
Mod P00009· CHANGE ORDER2012-02-07+$0$3,390,528CONSTRUCT 2ND LINEAR ACCELERATOR
Mod 11· CHANGE ORDER2012-07-30+$48,021$3,438,550CONSTRUCT 2ND LINEAR ACCELERATOR
Mod 12· CHANGE ORDER2012-07-30+$12,102$3,450,652CONSTRUCT 2ND LINEAR ACCELERATOR
Mod 13· CHANGE ORDER2012-07-30+$23,782$3,474,434CONSTRUCT 2ND LINEAR ACCELERATOR
Mod P00010· CHANGE ORDER2012-07-30+$0$3,474,434CONSTRUCT 2ND LINEAR ACCELERATOR
Mod P00014· CHANGE ORDER2013-05-28+$6,247$3,480,681CONSTRUCT 2ND LINEAR ACCELERATOR
Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-08-04+$192,611$3,673,292CONSTRUCT 2ND LINEAR ACCELERATOR
Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-08-04+$403,486$4,076,778CONSTRUCT 2ND LINEAR ACCELERATOR
Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-10-02+$10,595$4,087,373CONSTRUCT 2ND LINEAR ACCELERATOR

Related awards · 9

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI FLNJUCT58UN1)

AwardOffice · PSC / listingNet obligationsFY
VA250C0542541-BRECKSVILLE · Y149 · CONSTRUCT/OTHER HOSPITAL BLDGS$1,975,255FY2010
VA251C0823506-ANN ARBOR · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY$161,486FY2010
VA250C0454541-BRECKSVILLE · Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES$4,897,566FY2009
VA251C0570506-ANN ARBOR · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY$494,065FY2009

Other recipients under Z141 from 506-ANN ARBOR (most recent first)

AwardRecipientOfficeNet obligationsFY
VA506C11503SILVER STAR CONTRACTING, LLC506-ANN ARBOR$14,730FY2011
VA506C11504SILVER STAR CONTRACTING, LLC506-ANN ARBOR$6,071FY2011
VA506C11501SILVER STAR CONTRACTING, LLC506-ANN ARBOR$1,865FY2011
VA506C11502SILVER STAR CONTRACTING, LLC506-ANN ARBOR$3,670FY2011
VA506C11505SILVER STAR CONTRACTING, LLC506-ANN ARBOR$12,530FY2011

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA251C0852_3600_-NONE-_-NONE- · retrieved 2026-09-26.