Description
PROJECT NO. 550-09-102, UPGRADE CHILLER&AHU, BUILDING 58.
Base award description: TAS::36 0158::TAS PROJECT NO. 550-09-102, UPGRADE CHILLER&AHU, BUILDING 58
Modification chain · 10 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2010-06-11+$2,244,545= $2,244,545
- Mod P000012011-10-19+$3,355= $2,247,900
- Mod P000022011-12-16+$19,737= $2,267,637
- Mod P000032012-01-13+$0= $2,267,637
- Mod P000042012-03-29+$293,072= $2,560,710
- Mod P000052012-04-12+$0= $2,560,710
- Mod P000062013-02-25+$671,106= $3,231,816
- Mod P000072013-07-26+$0= $3,231,816
- Mod P000082013-09-03+$32,845= $3,264,661
- Mod P000092014-02-24+$49,854= $3,314,516
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2010-06-11 | +$2,244,545 | $2,244,545 | TAS::36 0158::TAS PROJECT NO. 550-09-102, UPGRADE CHILLER&AHU, BUILDING 58 |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-19 | +$3,355 | $2,247,900 | PROJECT NO. 550-09-102, UPGRADE CHILLER&AHU, BUILDING 58 |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-12-16 | +$19,737 | $2,267,637 | PROJECT NO. 550-09-102, UPGRADE CHILLER&AHU, BUILDING 58 |
| Mod P00003· OTHER ADMINISTRATIVE ACTION | 2012-01-13 | +$0 | $2,267,637 | PROJECT NO. 550-09-102, UPGRADE CHILLER&AHU, BUILDING 58 |
| Mod P00004· OTHER ADMINISTRATIVE ACTION | 2012-03-29 | +$293,072 | $2,560,710 | OTHER FUNCTIONS. PROJECT NO. 550-09-102, UPGRADE CHILLER&AHU, BUILDING 58 |
| Mod P00005· OTHER ADMINISTRATIVE ACTION | 2012-04-12 | +$0 | $2,560,710 | OTHER FUNCTIONS. PROJECT NO. 550-09-102, UPGRADE CHILLER&AHU, BUILDING 58 |
| Mod P00006· UNIQUE ENTITY ID OR LEGAL BUSINESS NAME CHANGE - NON-NOVATION | 2013-02-25 | +$671,106 | $3,231,816 | PROJECT NO. 550-09-102, UPGRADE CHILLER&AHU, BUILDING 58. NEW CONTRACTOR SURETY TAKEOVER |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-07-26 | +$0 | $3,231,816 | PROJECT NO. 550-09-102, UPGRADE CHILLER&AHU, BUILDING 58. |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-09-03 | +$32,845 | $3,264,661 | PROJECT NO. 550-09-102, UPGRADE CHILLER&AHU, BUILDING 58. |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-02-24 | +$49,854 | $3,314,516 | PROJECT NO. 550-09-102, UPGRADE CHILLER&AHU, BUILDING 58. |
Related awards · 6
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI MFB4BVRLYMB1)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA25114C0028 | 550-DANVILLE · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $148,909 | FY2014 |
Other recipients under Z149 from 550-DANVILLE (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA251C1037 | LEE & RYAN ENVIRONMENTAL CONSULTING, INCORPORATED | 550-DANVILLE | $5,140,594 | FY2011 |
| VA550C03020 | ANDROS CONTRACTING INC. | 550-DANVILLE | $16,645 | FY2010 |
| VA251C0802 | LEE & RYAN ENVIRONMENTAL CONSULTING, INCORPORATED | 550-DANVILLE | $270,683 | FY2010 |
| VA251C0749 | ANDROS CONTRACTING INC. | 550-DANVILLE | $1,700,000 | FY2010 |
| VA251C0652 | FRANK J STRAHL & SONS, INC | 550-DANVILLE | $3,377 | FY2010 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA251C0837_3600_-NONE-_-NONE- · retrieved 2026-09-26.