Award recordCONTRACT

2H&V CONSTRUCTION SERVICES, LLC

PIID VA251C0836· VHA· 550-DANVILLE· Z245 · MAINT-REP-ALT/WATER SUPPLY· FY2010· $698,203 net obligations· UEI JM6EATAHBEL6· FL

Description

PROJECT NO. 550-10-112, REPLACE EXTERIOR WATER MAINS PHASE III

First action · last action
2010-06-11 · 2011-05-27
Transactions
4
First transaction's obligation
$687,555
Base + all options value (sum of deltas)
$698,203
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
2
SDVOSB flag on record
Yes (self-representation)
NAICS
238220 · PLUMBING, HEATING, AND AIR-CONDITIONING CONTRACTORS

Modification chain · 4 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$698,203$0Base award · 2010-06-11 · this action $687,555 · running total $687,555Modification 1 · 2011-03-08 · this action $0 · running total $687,555Modification 2 · 2011-04-27 · this action -$1,275 · running total $686,280Modification 3 · 2011-05-27 · this action $11,923 · running total $698,203
  • Base2010-06-11+$687,555= $687,555
  • Mod 12011-03-08+$0= $687,555
  • Mod 22011-04-27-$1,275= $686,280
  • Mod 32011-05-27+$11,923= $698,203
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2010-06-11+$687,555$687,555PROJECT NO. 550-10-112, REPLACE EXTERIOR WATER MAINS PHASE III
Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-03-08+$0$687,555PROJECT NO. 550-10-112, REPLACE EXTERIOR WATER MAINS PHASE III
Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-04-27−$1,275$686,280PROJECT NO. 550-10-112, REPLACE EXTERIOR WATER MAINS PHASE III
Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-27+$11,923$698,203PROJECT NO. 550-10-112, REPLACE EXTERIOR WATER MAINS PHASE III

Related awards · 6

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI JM6EATAHBEL6)

AwardOffice · PSC / listingNet obligationsFY
36C24726C0051247-NETWORK CONTRACT OFFICE 7 (36C247) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$271,550FY2026
36C24826C0028248-NETWORK CONTRACT OFFICE 8 (36C248) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES$1,208,143FY2026
36C24826C0004248-NETWORK CONTRACT OFFICE 8 (36C248) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$1,295,008FY2026
36C25626N0344256-NETWORK CONTRACT OFFICE 16 (36C256) · Z2DZ · REPAIR OR ALTERATION OF OTHER HOSPITAL BUILDINGS$7,015,631FY2026
36C25624C0089256-NETWORK CONTRACT OFFICE 16 (36C256) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES$1,573,624FY2024
36C24924C0006249-NETWORK CONTRACT OFFICE 9 (36C249) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS$737,982FY2024

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA251C0836_3600_-NONE-_-NONE- · retrieved 2026-09-26.