Description
OTHER FUNCTIONS; 550-Z90003 PROJECT 550-09-305 BLDG 58;
Base award description: 550-Z90002 PROJECT 550-09-305 BLDG 58
Modification chain · 36 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-09-16+$4,896,000= $4,896,000
- Mod 12010-01-21+$0= $4,896,000
- Mod 32010-02-23-$98= $4,895,902
- Mod 22010-03-23+$7,775= $4,903,678
- Mod 42010-03-23+$11,193= $4,914,871
- Mod 52010-06-15+$1,703= $4,916,574
- Mod 62010-06-15+$1,895= $4,918,469
- Mod 72010-06-15+$30,924= $4,949,393
- Mod 82010-06-15+$6,305= $4,955,697
- Mod 102010-07-08+$27,619= $4,983,316
- Mod 112010-07-08+$1,444= $4,984,760
- Mod 92010-07-08+$11,634= $4,996,393
- Mod 122010-08-28+$19,730= $5,016,123
- Mod 162010-09-22-$1,811= $5,014,313
- Mod 142010-10-04+$29,871= $5,044,184
- Mod 172010-10-04+$4,065= $5,048,249
- Mod 192010-10-04+$45,092= $5,093,341
- Mod PO12010-11-17+$1,034= $5,094,375
- Mod COB2010-11-29+$74,321= $5,168,696
- Mod COC2010-12-15+$207,720= $5,376,416
- Mod 202011-01-07+$407= $5,376,823
- Mod 212011-01-07+$1,129= $5,377,952
- Mod 222011-01-07+$8,253= $5,386,205
- Mod 232011-02-01+$436= $5,386,641
- Mod 132011-02-07+$0= $5,386,641
- Mod 152011-02-07+$0= $5,386,641
- Mod 182011-02-07+$0= $5,386,641
- Mod 242011-02-16+$200,000= $5,586,641
- Mod 252011-03-29+$11,043= $5,597,684
- Mod 262011-03-29+$503= $5,598,187
- Mod 272011-04-13+$51,004= $5,649,191
- Mod 282011-07-05+$15,914= $5,665,105
- Mod 292012-02-23-$348= $5,664,757
- Mod 302012-02-23-$4,747= $5,660,010
- Mod P00312012-03-30+$0= $5,660,010
- Mod P000322013-02-22+$248,417= $5,908,427
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-09-16 | +$4,896,000 | $4,896,000 | 550-Z90002 PROJECT 550-09-305 BLDG 58 |
| Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-01-21 | +$0 | $4,896,000 | 550-Z90002 PROJECT 550-09-305 BLDG 58 |
| Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-02-23 | −$98 | $4,895,902 | 550-Z90002 PROJECT 550-09-305 BLDG 58 |
| Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-03-23 | +$7,775 | $4,903,678 | 550-Z90002 PROJECT 550-09-305 BLDG 58 |
| Mod 4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-03-23 | +$11,193 | $4,914,871 | 550-Z90002 PROJECT 550-09-305 BLDG 58 |
| Mod 5· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-06-15 | +$1,703 | $4,916,574 | 550-Z90002 CONSTRUCTION PROJECT 550-09-305 RENOVATE BLDG 58 |
| Mod 6· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-06-15 | +$1,895 | $4,918,469 | 550-Z90002 PROJECT 550-09-305 BLDG 58 |
| Mod 7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-06-15 | +$30,924 | $4,949,393 | 550-Z90002 PROJECT 550-09-305 BLDG 58 |
| Mod 8· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-06-15 | +$6,305 | $4,955,697 | 550-Z90002 PROJECT 550-09-305 BLDG 58 |
| Mod 10· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-07-08 | +$27,619 | $4,983,316 | 550-Z90002 PROJECT 550-09-305 BLDG 58 |
| Mod 11· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-07-08 | +$1,444 | $4,984,760 | 550-Z90002 PROJECT 550-09-305 BLDG 58 |
| Mod 9· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-07-08 | +$11,634 | $4,996,393 | 550-Z90002 PROJECT 550-09-305 BLDG 58 |
| Mod 12· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-08-28 | +$19,730 | $5,016,123 | 550-Z90002 PROJECT 550-09-305 BLDG 58 |
| Mod 16· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-22 | −$1,811 | $5,014,313 | 550-Z90003 PROJECT 550-09-305 BLDG 58 |
| Mod 14· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-10-04 | +$29,871 | $5,044,184 | 550-Z90003 PROJECT 550-09-305 BLDG 58 |
| Mod 17· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-10-04 | +$4,065 | $5,048,249 | 550-Z90002 PROJECT 550-09-305 BLDG 58 |
| Mod 19· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-10-04 | +$45,092 | $5,093,341 | 550-Z90003 PROJECT 550-09-305 BLDG 58 |
| Mod PO1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-11-17 | +$1,034 | $5,094,375 | 550-Z90003 PROJECT 550-09-305 BLDG 58; PROCEED ORDER FOR CO J |
| Mod COB· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-11-29 | +$74,321 | $5,168,696 | 550-Z90003 PROJECT 550-09-305 BLDG 58; PROCEED ORDER FOR CO J |
| Mod COC· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-15 | +$207,720 | $5,376,416 | 550-Z90003 PROJECT 550-09-305 BLDG 58; PROCEED ORDER FOR CO J |
| Mod 20· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-01-07 | +$407 | $5,376,823 | 550-Z90003 PROJECT 550-09-305 BLDG 58 |
| Mod 21· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-01-07 | +$1,129 | $5,377,952 | 550-Z90003 PROJECT 550-09-305 BLDG 58; PROCEED ORDER FOR CO J |
| Mod 22· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-01-07 | +$8,253 | $5,386,205 | 550-Z90003 PROJECT 550-09-305 BLDG 58; PROCEED ORDER FOR CO J |
| Mod 23· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-02-01 | +$436 | $5,386,641 | 550-Z90003 PROJECT 550-09-305 BLDG 58; PROCEED ORDER FOR CO J |
| Mod 13· OTHER ADMINISTRATIVE ACTION | 2011-02-07 | +$0 | $5,386,641 | 550-Z90002 PROJECT 550-09-305 BLDG 58; REPORT TO CLOSE OUT ACTION IN ECMS |
| Mod 15· OTHER ADMINISTRATIVE ACTION | 2011-02-07 | +$0 | $5,386,641 | 550-Z90002 PROJECT 550-09-305 BLDG 58; AWARDED FOR ECMS PURPOSES ONLY NO CHANGES IMPLEMENTED |
| Mod 18· OTHER ADMINISTRATIVE ACTION | 2011-02-07 | +$0 | $5,386,641 | 550-Z90003 PROJECT 550-09-305 BLDG 58; FPDS AWARDED FOR ECMS PURPOSES ONLY - NO CHANGE IN WORK |
| Mod 24· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-02-16 | +$200,000 | $5,586,641 | 550-Z90003 PROJECT 550-09-305 BLDG 58; PROCEED ORDER FOR CO J |
| Mod 25· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-03-29 | +$11,043 | $5,597,684 | 550-Z90003 PROJECT 550-09-305 BLDG 58; FPDS AWARDED FOR ECMS PURPOSES ONLY - NO CHANGE IN WORK |
| Mod 26· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-03-29 | +$503 | $5,598,187 | 550-Z90003 PROJECT 550-09-305 BLDG 58; PROCEED ORDER FOR CO J |
| Mod 27· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-13 | +$51,004 | $5,649,191 | 550-Z90003 PROJECT 550-09-305 BLDG 58; PROCEED ORDER FOR CO J |
| Mod 28· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-05 | +$15,914 | $5,665,105 | 550-Z90003 PROJECT 550-09-305 BLDG 58; PROCEED ORDER FOR CO J |
| Mod 29· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-02-23 | −$348 | $5,664,757 | 550-Z90003 PROJECT 550-09-305 BLDG 58; PROCEED ORDER FOR CO J |
| Mod 30· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-02-23 | −$4,747 | $5,660,010 | 550-Z90003 PROJECT 550-09-305 BLDG 58; PROCEED ORDER FOR CO J |
| Mod P0031· OTHER ADMINISTRATIVE ACTION | 2012-03-30 | +$0 | $5,660,010 | OTHER FUNCTIONS; 550-Z90003 PROJECT 550-09-305 BLDG 58; PROCEED ORDER FOR CO J |
| Mod P00032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-02-22 | +$248,417 | $5,908,427 | OTHER FUNCTIONS; 550-Z90003 PROJECT 550-09-305 BLDG 58; |
Related awards · 4
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other recipients under Z141 from 550-DANVILLE (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA251C1127 | CANNON MANAGEMENT GROUP, LLC | 550-DANVILLE | $566,000 | FY2011 |
| VA251C0846 | BW CONTRACTING SERVICES, INC. | 550-DANVILLE | $137,403 | FY2010 |
| VA251C0530 | VALOR FIELD SERVICES, INC. | 550-DANVILLE | $1,158,138 | FY2009 |
| VA251C0326 | FRANK J STRAHL & SONS, INC | 550-DANVILLE | $412,160 | FY2008 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA251C0597_3600_-NONE-_-NONE- · retrieved 2026-09-26.