Description
RADIATION ONCOLOGY INTERIOR RENOVATION CONSTRUCTION PROJECT
Modification chain · 9 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-08-19+$896,875= $896,875
- Mod COA2010-01-19+$0= $896,875
- Mod SA12010-01-22+$5,578= $902,453
- Mod SA22010-05-05+$115,886= $1,018,338
- Mod SA32010-06-04+$0= $1,018,338
- Mod SA42010-07-22+$10,788= $1,029,127
- Mod SA52010-10-18+$29,937= $1,059,064
- Mod SA62010-11-15+$5,639= $1,064,703
- Mod SA72011-06-10+$9,360= $1,074,063
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-08-19 | +$896,875 | $896,875 | RADIATION ONCOLOGY INTERIOR RENOVATION CONSTRUCTION PROJECT |
| Mod COA· CHANGE ORDER | 2010-01-19 | +$0 | $896,875 | RADIATION ONCOLOGY INTERIOR RENOVATION CONSTRUCTION PROJECT |
| Mod SA1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-01-22 | +$5,578 | $902,453 | RADIATION ONCOLOGY INTERIOR RENOVATION CONSTRUCTION PROJECT |
| Mod SA2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-05-05 | +$115,886 | $1,018,338 | RADIATION ONCOLOGY INTERIOR RENOVATION CONSTRUCTION PROJECT |
| Mod SA3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-06-04 | +$0 | $1,018,338 | RADIATION ONCOLOGY INTERIOR RENOVATION CONSTRUCTION PROJECT |
| Mod SA4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-07-22 | +$10,788 | $1,029,127 | RADIATION ONCOLOGY INTERIOR RENOVATION CONSTRUCTION PROJECT |
| Mod SA5· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-10-18 | +$29,937 | $1,059,064 | RADIATION ONCOLOGY INTERIOR RENOVATION CONSTRUCTION PROJECT |
| Mod SA6· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-11-15 | +$5,639 | $1,064,703 | RADIATION ONCOLOGY INTERIOR RENOVATION CONSTRUCTION PROJECT |
| Mod SA7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-10 | +$9,360 | $1,074,063 | RADIATION ONCOLOGY INTERIOR RENOVATION CONSTRUCTION PROJECT |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI RSUZTCPDU9B3)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA24614J1602 | 246-NETWORK CONTRACTING OFFICE 6 · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $499,842 | FY2014 |
| VA24614J1607 | 246-NETWORK CONTRACTING OFFICE 6 · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $499,258 | FY2014 |
| VA24614J5417 | 246-NETWORK CONTRACTING OFFICE 6 · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $13,500 | FY2014 |
| VA24614P5336 | 246-NETWORK CONTRACTING OFFICE 6 · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $3,670 | FY2014 |
| VA24614J0163 | 246-NETWORK CONTRACTING OFFICE 6 · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $320,656 | FY2014 |
| VA24614J0162 | 246-NETWORK CONTRACTING OFFICE 6 · Z1LZ · MAINTENANCE OF PARKING FACILITIES | $449,728 | FY2014 |
Other recipients under Z141 from 506-ANN ARBOR (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA506C11504 | SILVER STAR CONTRACTING, LLC | 506-ANN ARBOR | $6,071 | FY2011 |
| VA506C11502 | SILVER STAR CONTRACTING, LLC | 506-ANN ARBOR | $3,670 | FY2011 |
| VA506C11501 | SILVER STAR CONTRACTING, LLC | 506-ANN ARBOR | $1,865 | FY2011 |
| VA506C11503 | SILVER STAR CONTRACTING, LLC | 506-ANN ARBOR | $14,730 | FY2011 |
| VA506C11505 | SILVER STAR CONTRACTING, LLC | 506-ANN ARBOR | $12,530 | FY2011 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA251C0593_3600_-NONE-_-NONE- · retrieved 2026-09-26.