Description
IGF::OT::IGF CONSTRUCTION PROJECT 550-315 FOR 2 GREEN HOMES. MOD P00011 FOR DOOR MODIFICATIONS, CHANGE IN LOCK CORES,DRYWALL REPAIRS, AND TIME EXTENSION.
Base award description: IGF::OT::IGF CONSTRUCTION PROJECT 550-315 FOR 2 GREEN HOMES
Modification chain · 12 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2013-08-27+$7,711,444= $7,711,444
- Mod P000012014-07-11+$22,932= $7,734,376
- Mod P000022014-08-25+$118,801= $7,853,176
- Mod P000032014-10-02+$10,454= $7,863,631
- Mod P000042014-11-06+$34,239= $7,897,870
- Mod P000052014-12-18+$574,710= $8,472,580
- Mod P000062015-07-15+$246,656= $8,719,236
- Mod P000072015-09-10+$74,874= $8,794,110
- Mod P000082015-11-20+$0= $8,794,110
- Mod P000092016-01-07+$49,207= $8,843,317
- Mod P000102016-02-10+$0= $8,843,317
- Mod P000112016-06-01+$0= $8,843,317
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2013-08-27 | +$7,711,444 | $7,711,444 | IGF::OT::IGF CONSTRUCTION PROJECT 550-315 FOR 2 GREEN HOMES |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-07-11 | +$22,932 | $7,734,376 | IGF::OT::IGF CONSTRUCTION PROJECT 550-315 FOR 2 GREEN HOMES. MOD FOR PERMIT TIME EXTENSION, TRANSFORMER LOCATI… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-08-25 | +$118,801 | $7,853,176 | IGF::OT::IGF CONSTRUCTION PROJECT 550-315 FOR 2 GREEN HOMES. MOD FOR ADDITIONAL ROAD WORK, FOUNDATION WORK, ST… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-10-02 | +$10,454 | $7,863,631 | IGF::OT::IGF CONSTRUCTION PROJECT 550-315 FOR 2 GREEN HOMES. MOD FOR REMOVAL AND REPLACEMENT OF BASEMENT PIER… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-11-06 | +$34,239 | $7,897,870 | IGF::OT::IGF CONSTRUCTION PROJECT 550-315 FOR 2 GREEN HOMES. MOD FOR REMOVAL AND REDESIGN OF PLUMBING CONFLICT… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-12-18 | +$574,710 | $8,472,580 | IGF::OT::IGF CONSTRUCTION PROJECT 550-315 FOR 2 GREEN HOMES. MOD FOR DEWATERING ISSUE AND ASSOCIATED DELAY |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-07-15 | +$246,656 | $8,719,236 | IGF::OT::IGF CONSTRUCTION PROJECT 550-315 FOR 2 GREEN HOMES. MOD FOR MULTIPLE DIFFERING SITE CONDITIONS AND TI… |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-10 | +$74,874 | $8,794,110 | IGF::OT::IGF CONSTRUCTION PROJECT 550-315 FOR 2 GREEN HOMES. MOD P00007 FOR MULTIPLE DIFFERING SITE CONDITIONS… |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-11-20 | +$0 | $8,794,110 | IGF::OT::IGF CONSTRUCTION PROJECT 550-315 FOR 2 GREEN HOMES. MOD P00008 FOR MULTIPLE DIFFERING SITE CONDITIONS… |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-01-07 | +$49,207 | $8,843,317 | IGF::OT::IGF CONSTRUCTION PROJECT 550-315 FOR 2 GREEN HOMES. MOD P00008 FOR MULTIPLE DIFFERING SITE CONDITIONS… |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-02-10 | +$0 | $8,843,317 | IGF::OT::IGF CONSTRUCTION PROJECT 550-315 FOR 2 GREEN HOMES. MOD P00010 FOR CABINET MODS, DOOR HARDWARE, PERGO… |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-06-01 | +$0 | $8,843,317 | IGF::OT::IGF CONSTRUCTION PROJECT 550-315 FOR 2 GREEN HOMES. MOD P00011 FOR DOOR MODIFICATIONS, CHANGE IN LOCK… |