Description
IGF::OT::IGF CONSTRUCTION CONTRACT FOR IT INFRASTRUCTURE PHASE II (PROJECT NO. 506-12-101), AT ANN ARBOR VAMC. MOD P00002
Base award description: IGF::OT::IGF OTHER FUNCTIONS - CONSTRUCTION CONTRACT FOR IT INFRASTRUCTURE PHASE II (PROJECT NO. 506-12-101), AT ANN ARBOR VAMC.
Modification chain · 3 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2012-06-28+$2,200,000= $2,200,000
- Mod P000012013-04-18+$0= $2,200,000
- Mod P000022013-09-12+$67,998= $2,267,998
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2012-06-28 | +$2,200,000 | $2,200,000 | IGF::OT::IGF OTHER FUNCTIONS - CONSTRUCTION CONTRACT FOR IT INFRASTRUCTURE PHASE II (PROJECT NO. 506-12-101),… |
| Mod P00001· CHANGE ORDER | 2013-04-18 | +$0 | $2,200,000 | IGF::OT::IGF CONSTRUCTION CONTRACT FOR IT INFRASTRUCTURE PHASE II (PROJECT NO. 506-12-101), AT ANN ARBOR VAMC… |
| Mod P00002· CHANGE ORDER | 2013-09-12 | +$67,998 | $2,267,998 | IGF::OT::IGF CONSTRUCTION CONTRACT FOR IT INFRASTRUCTURE PHASE II (PROJECT NO. 506-12-101), AT ANN ARBOR VAMC… |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA25112C0084_3600_-NONE-_-NONE- · retrieved 2026-09-27.