Description
SUPPLEMENTAL AGREEMENT #4 CONSTRUCTION CONTRACT - BUILDING 30 CD SA #5 DOORS AND FINAL PHASE
Base award description: CONSTRUCTION CONTRACT - BUILDING 30 CD
Modification chain · 6 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2011-04-28+$1,109,200= $1,109,200
- Mod 22012-06-27+$64,998= $1,174,198
- Mod 12012-07-10+$8,240= $1,182,438
- Mod 32012-09-19+$17,929= $1,200,367
- Mod P000042013-04-02+$43,616= $1,243,983
- Mod P000052013-09-11+$96,610= $1,340,593
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2011-04-28 | +$1,109,200 | $1,109,200 | CONSTRUCTION CONTRACT - BUILDING 30 CD |
| Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-06-27 | +$64,998 | $1,174,198 | CONSTRUCTION CONTRACT - BUILDING 30 CD |
| Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-10 | +$8,240 | $1,182,438 | CONSTRUCTION CONTRACT - BUILDING 30 CD |
| Mod 3· CHANGE ORDER | 2012-09-19 | +$17,929 | $1,200,367 | CONSTRUCTION CONTRACT - BUILDING 30 CD |
| Mod P00004· CHANGE ORDER | 2013-04-02 | +$43,616 | $1,243,983 | SUPPLEMENTAL AGREEMENT #4 CONSTRUCTION CONTRACT - BUILDING 30 CD |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-09-11 | +$96,610 | $1,340,593 | SUPPLEMENTAL AGREEMENT #4 CONSTRUCTION CONTRACT - BUILDING 30 CD SA #5 DOORS AND FINAL PHASE |
Related awards · 10
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI PFKFJR4UWJE8)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA250C0682 | 541-BRECKSVILLE (00541) · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $2,414,924 | FY2011 |
| VA250C0666 | 552-DAYTON · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $2,056,365 | FY2011 |
| VA786AC0408 | NATIONAL CEMETERY ADMINISTRATION · Y299 · CONTRUCT/ALL OTHER NON-BLDG FACS | $1,563,073 | FY2011 |
| VA250C0590 | 552-DAYTON · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $631,521 | FY2010 |
| VA250C0551 | 552-DAYTON · Z149 · MAINT-REP-ALT/OTHER HOSPITAL BLDGS | $277,720 | FY2010 |
| VA250C0550 | 538-CHILLICOTHE · Z149 · MAINT-REP-ALT/OTHER HOSPITAL BLDGS | $950,414 | FY2010 |
Other recipients under Y141 from 538-CHILLICOTHE (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA250C0659 | CENTURION SOLUTIONS GROUP LLC | 538-CHILLICOTHE | $741,588 | FY2011 |
| VA250C0652 | ROBERT F. HYLAND & SONS, LLC | 538-CHILLICOTHE | $211,904 | FY2011 |
| VA250C0321 | MESSER CONSTRUCTION CO | 538-CHILLICOTHE | $7,319,473 | FY2009 |
| VA250C0306 | SETTERLIN BUILDING COMPANY | 538-CHILLICOTHE | $9,122,146 | FY2008 |