Award recordCONTRACT

BOUTWELL & ASSOCIATES, INC.

PIID VA250C0662· VHA· 552-DAYTON· Y111 · CONSTRUCTION OF OFFICE BUILDINGS· FY2011· $1,171,326 net obligations· UEI QR4NEDG58R88· OH

Description

MOD #0004: BEAM SUPPORT - ROOM 105

Base award description: RENOVATE PROTESTANT CHAPEL (BLDG. 118)

First action · last action
2011-04-25 · 2012-04-13
Transactions
6
First transaction's obligation
$1,117,000
Base + all options value (sum of deltas)
$1,171,326
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
7
SDVOSB flag on record
Yes (self-representation)
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION

Modification chain · 6 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$1,171,326$0Base award · 2011-04-25 · this action $1,117,000 · running total $1,117,000Modification COA · 2011-07-26 · this action $0 · running total $1,117,000Modification 1 · 2011-08-29 · this action $23,823 · running total $1,140,823Modification 2 · 2011-09-24 · this action $18,429 · running total $1,159,252Modification 3 · 2011-11-04 · this action $6,171 · running total $1,165,423Modification P0004 · 2012-04-13 · this action $5,903 · running total $1,171,326
  • Base2011-04-25+$1,117,000= $1,117,000
  • Mod COA2011-07-26+$0= $1,117,000
  • Mod 12011-08-29+$23,823= $1,140,823
  • Mod 22011-09-24+$18,429= $1,159,252
  • Mod 32011-11-04+$6,171= $1,165,423
  • Mod P00042012-04-13+$5,903= $1,171,326
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2011-04-25+$1,117,000$1,117,000RENOVATE PROTESTANT CHAPEL (BLDG. 118)
Mod COA· CHANGE ORDER2011-07-26+$0$1,117,000CO A: INSTALL FOUR ELECTRICAL BOXES AND REMOVAL OF TRASH.
Mod 1· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2011-08-29+$23,823$1,140,823MOD #0001: INSTALL FOUR ELECTRICAL BOXES; REMOVAL OF TRASH; REPLACE BASE BOARD; AND REPLACE/REPAIR EXISTING MO…
Mod 2· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2011-09-24+$18,429$1,159,252MOD #0002: ADDITIONAL RESTORATION NEEDS AND INSTALL CARPETING.
Mod 3· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2011-11-04+$6,171$1,165,423MOD #0003: ADDITIONAL WATER SUPPLY LINES&DRAINS.
Mod P0004· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2012-04-13+$5,903$1,171,326MOD #0004: BEAM SUPPORT - ROOM 105

Related awards · 7

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI QR4NEDG58R88)

AwardOffice · PSC / listingNet obligationsFY
VA250C0662A552-DAYTON · Y111 · CONSTRUCTION OF OFFICE BUILDINGS$1,117,000FY2011
VA250C0593538-CHILLICOTHE · Z149 · MAINT-REP-ALT/OTHER HOSPITAL BLDGS$4,240,593FY2010
VA250RA0416552-DAYTON · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY$2,408,250FY2009

Other recipients under Y111 from 552-DAYTON (most recent first)

AwardRecipientOfficeNet obligationsFY
VA250C0720CALVARY CONTRACTING INC552-DAYTON$1,549,264FY2011
VA250C0700ASPIRE GROUP OF OHIO, LLC, THE552-DAYTON$3,331,446FY2011
VA250C0173GEILER COMPANY, THE552-DAYTON$272,368FY2008
VA250C0030DORSEY CONSTRUCTION COMPANY552-DAYTON$13,781FY2008