Description
P00029 IS TO ADD COST OF SETTLEMENT AGREEMENT FOR DISPUTED ACTION.
Base award description: ANIMAL RESEARCH RENOVATIONS IS A CONSTRUCTION CONTRACT THAT WILL RENOVATE THE ANIMAL RESEARACH LAB SECTION OF THE LOUIS STOKES VA MEDICAL CENTER, CLEVELAND OH.
Modification chain · 30 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2008-12-17+$3,653,000= $3,653,000
- Mod 12009-07-14+$25,619= $3,678,619
- Mod 22010-01-28+$57,564= $3,736,183
- Mod 32010-02-22+$55,135= $3,791,319
- Mod COA2010-06-02+$0= $3,791,319
- Mod 42010-06-29+$0= $3,791,319
- Mod 52010-10-06+$35,481= $3,826,800
- Mod 62010-10-08+$74,140= $3,900,940
- Mod 72011-02-14+$24,054= $3,924,994
- Mod 82011-03-10+$0= $3,924,994
- Mod P000092012-01-27+$33,645= $3,958,639
- Mod P000102012-08-30+$0= $3,958,639
- Mod P000112012-08-30+$0= $3,958,639
- Mod P000122012-08-30+$0= $3,958,639
- Mod P000132012-08-30+$0= $3,958,639
- Mod P000142012-08-30+$0= $3,958,639
- Mod P000152012-10-26+$48,977= $4,007,616
- Mod P000162012-10-26+$14,975= $4,022,591
- Mod P000172012-10-26+$46,962= $4,069,553
- Mod P000182012-10-26+$25,316= $4,094,869
- Mod P000192012-10-26+$44,258= $4,139,127
- Mod P000202012-11-30+$72,000= $4,211,127
- Mod P000212013-02-05+$12,419= $4,223,546
- Mod P000222013-08-15+$243,010= $4,466,556
- Mod P000232013-10-10+$11,812= $4,478,367
- Mod P000252014-04-14+$3,840= $4,482,207
- Mod P000262014-04-22+$50,072= $4,532,279
- Mod P000272014-08-08+$3,642= $4,535,921
- Mod P000282014-09-05-$6,000= $4,529,921
- Mod P000292017-03-02+$241,800= $4,771,721
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2008-12-17 | +$3,653,000 | $3,653,000 | ANIMAL RESEARCH RENOVATIONS IS A CONSTRUCTION CONTRACT THAT WILL RENOVATE THE ANIMAL RESEARACH LAB SECTION OF… |
| Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-07-14 | +$25,619 | $3,678,619 | NOT REQUIRED |
| Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-01-28 | +$57,564 | $3,736,183 | NOT REQUIRED |
| Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-02-22 | +$55,135 | $3,791,319 | SA #3 ANIMAL RESEARCH RENOVATIONS INCORPORATE BULLETINS 5, 8R, 11R,&12R PRICE INCREASE: 55,135.30 ADD 30 DAYS |
| Mod COA· CHANGE ORDER | 2010-06-02 | +$0 | $3,791,319 | SA #3 ANIMAL RESEARCH RENOVATIONS INCORPORATE BULLETINS 5, 8R, 11R,&12R PRICE INCREASE: 55,135.30 ADD 30 DAYS |
| Mod 4· DEFINITIZE CHANGE ORDER | 2010-06-29 | +$0 | $3,791,319 | SA #4 ANIMAL RESEARCH RENOVATIONS DEFINITIZES CO A, PROVIDES SPECIFICATION CLARIFICATION, ADDS 25 DAYS TO CONT… |
| Mod 5· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-10-06 | +$35,481 | $3,826,800 | SA#5 ANIMAL RESEARCH RENOVATIONS INCORPORATES 4 WITHIN SCOPE CHANGES, BULLETINS 13, 15, 16 19. ADDS 25 DAYS TO… |
| Mod 6· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-10-08 | +$74,140 | $3,900,940 | SA #6 ANIMAL RESEARCH RENOVATIONS SUPPLEMENTAL AGREEMENT TO ADD WITHIN SCOPE CHANGES REPRESENTED BY BULLETINS… |
| Mod 7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-02-14 | +$24,054 | $3,924,994 | SA #7 SUPPLEMENTAL AGREEMENT ADUSTS CONTRACT PRICE FOR DIFFERING SITE CONDITIONS NOT DISCOVERABALE AT TIME OF… |
| Mod 8· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-03-10 | +$0 | $3,924,994 | SA #8 THIS SUPPLEMENTAL AGREEMENT EXTENDS THE CONTRACT SCHEDULE BY 30 DAYS AT NO COST TO THE GOVERNMENT. |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-01-27 | +$33,645 | $3,958,639 | SA P00009 THIS SUPPLEMENTAL INCORPORATES SEVERAL MISCELLANEOUS WITHIN SCOPE CHANGES TO THE CONTRACT AND EXTEND… |
| Mod P00010· CHANGE ORDER | 2012-08-30 | +$0 | $3,958,639 | P00010 THIS UNILATERAL MODIFICATION DIRECTS THE CONTRACTOR TO PERFORM 8 ITEMS ARISING FROM DIFFERING SITE COND… |
| Mod P00011· CHANGE ORDER | 2012-08-30 | +$0 | $3,958,639 | P00011 IS A UNILATERAL MOD BEING ISSSUED TO AVOID A SUSPENSION IN WORK BY DIRECTING THE CONTRACTOR TO PERFORM… |
| Mod P00012· CHANGE ORDER | 2012-08-30 | +$0 | $3,958,639 | P00012 IS BEING ISSUED AS A UNILATERAL MOD TO AVERT A SUSPENSISON OF WORK ON THIS CONTRACT. THIS MOD STEMS FR… |
| Mod P00013· CHANGE ORDER | 2012-08-30 | +$0 | $3,958,639 | P00013 IS BEING ISSUED AS A UNILATERAL MODIFICATION TO AVERT A SUSPENSION IN WORK. IT ARISES DUE TO DIFFERING… |
| Mod P00014· CHANGE ORDER | 2012-08-30 | +$0 | $3,958,639 | P00014 IS BEING ISSUED AS A UNILATERAL MODIFICATION TO AVERT A SUSPENSION OF WORK ON THIS CONTRACT. IT AROSE… |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-26 | +$48,977 | $4,007,616 | P00015 IS A SUPPLEMENTAL AGREEMENT WHICH DEFINITIZES UNILATERAL MODIFICATION P00010 WHICH INCORPORATED A/E BU… |
| Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-26 | +$14,975 | $4,022,591 | P00016 IS A SUPPLEMENTAL AGREEMENT WHICH DEFINITIZES UNILATERAL MODIFICATION P00011 WHICH INCORPORATED A/E BU… |
| Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-26 | +$46,962 | $4,069,553 | P00017 IS A SUPPLEMENTAL AGREEMENT WHICH DEFINITIZES UNILATERAL MODIFICATION P00012 WHICH INCORPORATED A/E BU… |
| Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-26 | +$25,316 | $4,094,869 | P00018 IS A SUPPLEMENTAL AGREEMENT WHICH DEFINITIZES UNILATERAL MODIFICATION P00013 WHICH INCORPORATED A/E BU… |
| Mod P00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-26 | +$44,258 | $4,139,127 | P00019 IS A SUPPLEMENTAL AGREEMENT WHICH DEFINITIZES UNILATERAL MODIFICATION P00014 WHICH INCORPORATED A/E BU… |
| Mod P00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-11-30 | +$72,000 | $4,211,127 | P00020 IS A SUPPLEMENTAL AGREEMENT WHICH PROVIDES FOR AN EQUITABLE ADJUSTMENT FOR GOVERNMENT CAUSED DELAY DURI… |
| Mod P00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-02-05 | +$12,419 | $4,223,546 | P00021 IS A SUPPLEMENTAL AGREEMENT WHICH PROVIDES FOR AN EQUITABLE ADJUSTMENT FOR GOVERNMENT INCORPORATING WIT… |
| Mod P00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-08-15 | +$243,010 | $4,466,556 | P00022 IS A SUPPLEMENTAL AGREEMENT WHICH PROVIDES FOR AN EQUITABLE ADJUSTMENT FOR GOVERNMENT DELAYS FROM NOVEM… |
| Mod P00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-10-10 | +$11,812 | $4,478,367 | P00023 IS A SUPPLEMENTAL AGREEMENT WHICH INCORPORATES THREE WITHIN SCOPE CHANGES RESULTANT OF DIFFERING SITE C… |
| Mod P00025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-04-14 | +$3,840 | $4,482,207 | P00025 INCORPORATES THREE CHANGES INTO THE CONTRACT, RE-ROUTING EXISTING STEAM PIPING, PROVIDING ELECTRICAL CO… |
| Mod P00026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-04-22 | +$50,072 | $4,532,279 | P00026 INCORPORATES FOUR CHANGES INTO THE CONTRACT, CHANGING SITE ACCESS POINT, WATER DAMAGE, REVISED ELECTRIC… |
| Mod P00027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-08-08 | +$3,642 | $4,535,921 | P00027 IS TO FUND THE BOND INCREASE AND OVERRUN INCURRED DURING CONTRACT COMPLETION |
| Mod P00028· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-09-05 | −$6,000 | $4,529,921 | P00028 IS TO DE-OBLGIATE $6K FOR UNFINISHED PUNCHLIST ITEMS. |
| Mod P00029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-03-02 | +$241,800 | $4,771,721 | P00029 IS TO ADD COST OF SETTLEMENT AGREEMENT FOR DISPUTED ACTION. |
Related awards · 6
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI KN51D6GPPBL1)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA250C0444 | 539-CINCINNATI · Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES | $50,192 | FY2009 |
| VA250C0410 | 539-CINCINNATI · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $18,072 | FY2009 |
| VA250C0398 | 539-CINCINNATI · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $914,715 | FY2009 |
| VA250C0405 | 552-DAYTON · Z149 · MAINT-REP-ALT/OTHER HOSPITAL BLDGS | $686,289 | FY2009 |
| VA250C0400 | 539-CINCINNATI · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $4,970,222 | FY2009 |
| VA250C0392 | 539-CINCINNATI · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $177,932 | FY2009 |