Description
SITE CONDITIONS REQUIRE ADDITIONAL WORK TO COMPLETE THE PROJECT - CHANGE ORDERS (8) UU THRU A9.
Base award description: EXPAND AND RENOVATE EMERGENCY DEPARTMENT BUILDING 310 AT VA MEDICAL CENTER DAYTON OHIO, CHANGE ORDER A.
Modification chain · 25 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2008-03-18+$0= $0
- Mod COD2008-04-08+$0= $0
- Mod SA0012008-07-07+$23,582= $23,582
- Mod SA0022009-03-12+$9,621= $33,203
- Mod SA0032009-05-21+$12,276= $45,479
- Mod SA0042009-05-29+$3,023= $48,502
- Mod SA0052009-05-29+$36,090= $84,592
- Mod COR2009-06-13+$0= $84,592
- Mod COS2009-06-15+$0= $84,592
- Mod SA0062009-07-24+$0= $84,592
- Mod SA0072009-08-31+$6,800= $91,392
- Mod SA0082009-10-16+$140,758= $232,150
- Mod SA0092009-11-05+$12,483= $244,633
- Mod COJJ2010-01-25+$0= $244,633
- Mod SA0102010-02-26+$13,405= $258,038
- Mod SA0112010-04-01+$16,145= $274,183
- Mod SA0122010-04-28+$1,814= $275,997
- Mod SA0132010-05-20+$16,000= $291,997
- Mod COA52010-06-17+$0= $291,997
- Mod SA0152010-07-06+$7,766= $299,763
- Mod A62010-07-19+$0= $299,763
- Mod COA62010-07-26+$0= $299,763
- Mod COA72010-07-30+$0= $299,763
- Mod COA82010-08-06+$0= $299,763
- Mod SA162010-12-29+$4,663= $304,426
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base· CHANGE ORDER | 2008-03-18 | +$0 | $0 | EXPAND AND RENOVATE EMERGENCY DEPARTMENT BUILDING 310 AT VA MEDICAL CENTER DAYTON OHIO, CHANGE ORDER A. |
| Mod COD· CHANGE ORDER | 2008-04-08 | +$0 | $0 | RENOVATE EXPAND EMERG DEPT CHANGE ORDER D |
| Mod SA001· CHANGE ORDER | 2008-07-07 | +$23,582 | $23,582 | EXPAND AND RENOVATE EMERGENCY DEPARTMENT BUILDING 310 AT VA MEDICAL CENTER DAYTON OHIO. |
| Mod SA002· CHANGE ORDER | 2009-03-12 | +$9,621 | $33,203 | EXISTING HEATERS NOT RE-USEABLE. PROVIDE/INSTALL NEW. |
| Mod SA003· CHANGE ORDER | 2009-05-21 | +$12,276 | $45,479 | SITE CONDITIONS REQUIRE RE-ROUTE WATER LINE, ADD EAST WALL REINFORCING FOOTER, AND INCREASE STRENGTH OF EXAM L… |
| Mod SA004· CHANGE ORDER | 2009-05-29 | +$3,023 | $48,502 | RE-ROUTE STORM LINE AROUND OBSTACLES AND POWER UP NURSE STATION FURNITURE AFTER INSTALLATION. |
| Mod SA005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-05-29 | +$36,090 | $84,592 | PROVIDE INSTALL ELECT, NURSE CALL, MED GAS, LIGHTS, AND FLOORING FOR TEMP LOCATION OF EMERG DEPT UNTIL PHASE I… |
| Mod COR· CHANGE ORDER | 2009-06-13 | +$0 | $84,592 | ADD TWO TEMPORARY DATA LINES. EST $900 FUNDS COMMITTED. |
| Mod COS· CHANGE ORDER | 2009-06-15 | +$0 | $84,592 | CONTINUE FENCE RENTAL UNTIL VA DETERMINES NOT NEEDED. FUNDS ARE COMMITTED FOR FINAL AMOUNT. EST $700 |
| Mod SA006· OTHER ADMINISTRATIVE ACTION | 2009-07-24 | +$0 | $84,592 | ADD FAR CLAUSE 52.236-11 |
| Mod SA007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-08-31 | +$6,800 | $91,392 | PROVIDE AND INSTALL METAL STUD WALL, DATA LINES, AND NURSE CALL IN ORDER TO TEMPORARILY OCCUP PHASE I. |
| Mod SA008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-10-16 | +$140,758 | $232,150 | PROVIDE INSTALL BATHROMM CONNECTION IN PHASE I, INSTALL TEMP DOOR, MOVE TRAILER AND TEMP FENCE, CHANGE COMPLET… |
| Mod SA009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-11-05 | +$12,483 | $244,633 | REMOVE/DISPOSE OF ASBESTOS FOUND AT SITE UNDER DIRECTION OF CERTIFIED PROFESSIONAL INDUSTRIAL HYGIENIST, AT BU… |
| Mod COJJ· CHANGE ORDER | 2010-01-25 | +$0 | $244,633 | ADD TWO TEMPORARY DATA LINES. EST $900 FUNDS COMMITTED. |
| Mod SA010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-02-26 | +$13,405 | $258,038 | CHANGES: Z, AA, DD, EE, FF, HH, II, JJ AT EMERGENCY DEPARTMENT, BUILDING 310 AT VA MEDICAL CENTER DAYTON OHIO. |
| Mod SA011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-04-01 | +$16,145 | $274,183 | CHANGE ORDER N UPDATE MENTAL HEALTH HOLDING ROOM, CONSULT ROOM, AND BATHROOM TO CURRENT REQUIREMENTS. |
| Mod SA012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-04-28 | +$1,814 | $275,997 | CHANGE ORDER N UPDATE MENTAL HEALTH HOLDING ROOM, CONSULT ROOM, AND BATHROOM TO CURRENT REQUIREMENTS. |
| Mod SA013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-05-20 | +$16,000 | $291,997 | CHANGE ORDER QQ ABATEMENT AND CPIH SERVICES |
| Mod COA5· CHANGE ORDER | 2010-06-17 | +$0 | $291,997 | ADD INSULATION TO AN ADDITIONAL 37' OF HVAC. ADDITIONAL WORK TO BE PERFORMED ON JUNE 18 ALONG WITH OTHER SCHE… |
| Mod SA015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-07-06 | +$7,766 | $299,763 | CHANGE ORDERS UU THRU ZZ AND A1 THROUGH A3 - ADDITIONAL WORK REQUIRED TO COMPLETE THE PROJECT. |
| Mod A6· CHANGE ORDER | 2010-07-19 | +$0 | $299,763 | CHANGE ORDER - PROVIDE AND INSTALL MAGLOCK AT EMERGENCY ROOM AUTOMATIC DOORS WITH CONTROLS AT NURSE STATION AN… |
| Mod COA6· CHANGE ORDER | 2010-07-26 | +$0 | $299,763 | CHANGE ORDER - MOVE MAGNETIC DOOR LOCK TO INNER DOOR AND CONNECT DOOR LOCK AND CAMERA TO POLICE FOR MONITORING |
| Mod COA7· CHANGE ORDER | 2010-07-30 | +$0 | $299,763 | CHANGE ORDER - DUE TO DIFERING SITE CONDITIONS AND IN ORDER TO MEET SAFETY OFFICE RECOMENDATIONS, PROVIDE AND… |
| Mod COA8· CHANGE ORDER | 2010-08-06 | +$0 | $299,763 | CHANGE ORDER A8 - PROVIDE AND INSTALL SPECIAL ORDER RAILS AND CURTAINS IN RM 127 AND 128 IN ORDER THAT CODE OR… |
| Mod SA16· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-29 | +$4,663 | $304,426 | SITE CONDITIONS REQUIRE ADDITIONAL WORK TO COMPLETE THE PROJECT - CHANGE ORDERS (8) UU THRU A9. |
Related awards · 7
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI NPPEJLNAES26)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA250C0045 | 541-BRECKSVILLE · Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES | $601,722 | FY2009 |
| VA250C0054 | 541-BRECKSVILLE · Z142 · MAINT-REP-ALT/LABS & CLINICS | $178,266 | FY2008 |
Other recipients under Y142 from 552-DAYTON (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA250C0360 | AH WEST GROUP, LLC | 552-DAYTON | $322,470 | FY2009 |
| VA250C0214 | CHEVRON CONSTRUCTION SERVICES, LLC | 552-DAYTON | $998,185 | FY2008 |
| VA250C0048 | STRYKER CONTRACTING LLC | 552-DAYTON | $9,028 | FY2008 |
| VA250C0039 | K & T CONSTRUCTION AND SUPPLY, INC. | 552-DAYTON | $27,951 | FY2008 |
| VA250C0066 | SIGMA CAPITAL, INC | 552-DAYTON | -$361,548 | FY2008 |