Description
CLINICAL ADDITION, B31 MODIFICATION P00028 - SUPPLEMENTAL AGREEMENT FOR EXISTING FLOOR PLAN THICKNESS WORK, FIREWALL CHANGES WORK, AND TO COMPLETE THE VESTIBULE SOFFIT CHANGE.
Base award description: IGF::OT::IGF CLINICAL ADDITION, B31
Modification chain · 36 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2014-09-30+$8,274,000= $8,274,000
- Mod P000012015-08-14+$73,695= $8,347,695
- Mod PCOA2015-08-14+$0= $8,347,695
- Mod PCOA22015-12-03+$0= $8,347,695
- Mod P000022016-03-03+$29,016= $8,376,711
- Mod P000032016-04-13+$34,894= $8,411,605
- Mod PC0A32016-05-10+$33,735= $8,445,340
- Mod P000042016-07-08+$58,580= $8,503,920
- Mod P000052016-10-03-$52,890= $8,451,030
- Mod P000062017-01-25+$19,096= $8,470,126
- Mod P000072017-03-30+$19,242= $8,489,368
- Mod P000082017-05-01+$4,950= $8,494,318
- Mod P000092017-05-09+$0= $8,494,318
- Mod P000102017-05-16-$8,030= $8,486,288
- Mod P000112017-06-30+$16,382= $8,502,670
- Mod P000122017-11-21+$44,209= $8,546,879
- Mod P000132017-11-22+$0= $8,546,879
- Mod PCOA42017-12-12+$0= $8,546,879
- Mod P000142018-01-05-$9,215= $8,537,664
- Mod PCOA52018-06-14+$0= $8,537,664
- Mod PCOA62018-08-09+$0= $8,537,664
- Mod P000152018-08-21+$28,966= $8,566,630
- Mod P000162018-08-29+$0= $8,566,630
- Mod P000172018-10-24+$8,167= $8,574,797
- Mod P000182019-01-25+$9,562= $8,584,359
- Mod PCOA72019-03-14+$0= $8,584,359
- Mod P000192019-04-26+$0= $8,584,359
- Mod P000202019-05-08+$1,927= $8,586,286
- Mod P000212019-06-10+$11,333= $8,597,619
- Mod P000222019-06-20+$6,249= $8,603,868
- Mod P000232019-07-23+$75= $8,603,943
- Mod P000242019-08-30+$30,183= $8,634,127
- Mod P000252019-09-27-$3,500= $8,630,627
- Mod P000262019-10-30+$10,931= $8,641,559
- Mod P000272019-11-08+$8,458= $8,650,017
- Mod P000282020-12-10+$3,035= $8,653,052
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2014-09-30 | +$8,274,000 | $8,274,000 | IGF::OT::IGF CLINICAL ADDITION, B31 |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-08-14 | +$73,695 | $8,347,695 | IGF::OT::IGF CLINICAL ADDITION, B31 SA #1 WATER LINE/FIRE LINE AND STORM LINE EASTSIDE |
| Mod PCOA· CHANGE ORDER | 2015-08-14 | +$0 | $8,347,695 | IGF::OT::IGF CLINICAL ADDITION, B31 CHANGE ORDER TO DIRECT WORK |
| Mod PCOA2· CHANGE ORDER | 2015-12-03 | +$0 | $8,347,695 | IGF::OT::IGF CLINICAL ADDITION, B31 CHANGE ORDER TO DIRECT WORK |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-03-03 | +$29,016 | $8,376,711 | IGF::OT::IGF CLINICAL ADDITION, B31 CHANGE ORDER TO DIRECT WORK |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-04-13 | +$34,894 | $8,411,605 | IGF::OT::IGF CLINICAL ADDITION, B31 CHANGE ORDER TO DIRECT WORK |
| Mod PC0A3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-05-10 | +$33,735 | $8,445,340 | IGF::OT::IGF CLINICAL ADDITION, B31 CHANGE ORDER TO DIRECT WORK OF CHANGE ORDER PCOA 3 |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-07-08 | +$58,580 | $8,503,920 | IGF::OT::IGF CLINICAL ADDITION, B31 SUPPLEMENTAL AGREEMENT FOR SHEET PILING FOR SUMP-SEWAGE PITS |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-10-03 | −$52,890 | $8,451,030 | IGF::OT::IGF CLINICAL ADDITION, B31 SUPPLEMENTAL AGREEMENT FOR CHANGES |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-01-25 | +$19,096 | $8,470,126 | IGF::OT::IGF CLINICAL ADDITION, B31 SUPPLEMENTAL AGREEMENT FOR CHANGES TO MODIFY CURTAIN WALL AND SLAB ASSEMB… |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-03-30 | +$19,242 | $8,489,368 | IGF::OT::IGF CLINICAL ADDITION, B31 SUPPLEMENTAL AGREEMENT FOR CHANGES UNDER BULLETIN 1R, 13 AND 30. |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-05-01 | +$4,950 | $8,494,318 | IGF::OT::IGF CLINICAL ADDITION, B31 SUPPLEMENTAL AGREEMENT P00008 FOR DIFFERING SITE CONDITIONS FOUND REF. EX… |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-05-09 | +$0 | $8,494,318 | IGF::OT::IGF CLINICAL ADDITION, B31 CONVERTS CHANGE ORDER PCOA3 TO SUPPLEMENTAL AGREEMENT |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-05-16 | −$8,030 | $8,486,288 | IGF::OT::IGF CLINICAL ADDITION, B31 SUPPLEMENTAL AGREEMENT P0010 DEDUCT FOR STEEL CHANGES |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-06-30 | +$16,382 | $8,502,670 | IGF::OT::IGF CLINICAL ADDITION, B31 SUPPLEMENTAL AGREEMENT P0010 DEDUCT FOR STEEL CHANGES |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-11-21 | +$44,209 | $8,546,879 | IGF::OT::IGF CLINICAL ADDITION, B31 SUPPLEMENTAL AGREEMENT MODIFICATIONS P00012 |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-11-22 | +$0 | $8,546,879 | IGF::OT::IGF CLINICAL ADDITION, B31 SUPPLEMENTAL AGREEMENT NO-COST CHANGES |
| Mod PCOA4· CHANGE ORDER | 2017-12-12 | +$0 | $8,546,879 | IGF::OT::IGF CLINICAL ADDITION, B31 CHANGE ORDER TO DIRECT WORK OF CHANGE ORDER PCOA 4 WINDOW TINTING |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-01-05 | −$9,215 | $8,537,664 | IGF::OT::IGF CLINICAL ADDITION, B31 MODIFICATION FOR MULTIPLE CHANGES |
| Mod PCOA5· CHANGE ORDER | 2018-06-14 | +$0 | $8,537,664 | IGF::OT::IGF CLINICAL ADDITION, B31 PCOA 5 - CHANGE ORDER TO DIRECT CONTRACTOR TO COMPLETE ALL WORK OUTLINE… |
| Mod PCOA6· CHANGE ORDER | 2018-08-09 | +$0 | $8,537,664 | IGF::OT::IGF CLINICAL ADDITION, B31 PCOA 6 - CHANGE ORDER TO DIRECT CONTRACTOR TO PROVIDE NEW STEEL SUPPORT… |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-08-21 | +$28,966 | $8,566,630 | IGF::OT::IGF CLINICAL ADDITION, B31 MODIFICATION P00015 - SUPPLEMENTAL AGREEMENT FOR WORK OUTLINED IN BULLE… |
| Mod P00016· OTHER ADMINISTRATIVE ACTION | 2018-08-29 | +$0 | $8,566,630 | IGF::OT::IGF CLINICAL ADDITION, B31 MODIFICATION P00016 - ADMINISTRATIVE MODIFICATION TO REFLECT NEW PHYSIC… |
| Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-10-24 | +$8,167 | $8,574,797 | IGF::OT::IGF CLINICAL ADDITION, B31 MODIFICATION P00017 - CONTRACT VA250-14-C-0102 CLINICAL ADDITION BLDG.… |
| Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-01-25 | +$9,562 | $8,584,359 | IGF::OT::IGF CLINICAL ADDITION, B31 MODIFICATION P00018 - SUPPLEMENTAL AGREEMENT FOR ADDITIONAL WORK OUTL… |
| Mod PCOA7· CHANGE ORDER | 2019-03-14 | +$0 | $8,584,359 | IGF::OT::IGF CLINICAL ADDITION, B31 MODIFICATION PCOA 7 - CHANGE ORDER WORK IN ACCORDANCE WITH BULLETIN #… |
| Mod P00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-04-26 | +$0 | $8,584,359 | IGF::OT::IGF CLINICAL ADDITION, B31 MODIFICATION P00019 - CONTRACTOR TO PROVIDE ALL LABOR, MATERIALS, AND… |
| Mod P00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-05-08 | +$1,927 | $8,586,286 | IGF::OT::IGF CLINICAL ADDITION, B31 MODIFICATION P00020 REDUCED SOFFIT DEMO IN ACCORDANCE WITH BULLETIN #… |
| Mod P00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-06-10 | +$11,333 | $8,597,619 | IGF::OT::IGF CLINICAL ADDITION, B31 MODIFICATION P00021 CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO C… |
| Mod P00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-06-20 | +$6,249 | $8,603,868 | IGF::OT::IGF CLINICAL ADDITION, B31 MODIFICATION P00022 CONTRACTOR TO PROVIDE ALL LABOR AND EQUIPMENT TO… |
| Mod P00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-07-23 | +$75 | $8,603,943 | CLINICAL ADDITION, B31 MODIFICATION P00023 CONTRACTOR TO PROVIDE ALL MATERIALS IN ACCORDANCE WITH BULLETIN… |
| Mod P00024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-08-30 | +$30,183 | $8,634,127 | CLINICAL ADDITION, B31 MODIFICATION P00024 SUPPLEMENTAL AGREEMENT FOR SEWER EJECTOR WORK AND OTHER WORK OUT… |
| Mod P00025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-09-27 | −$3,500 | $8,630,627 | CLINICAL ADDITION, B31 MODIFICATION P00025 - SUPPLEMENTAL AGREEMENT FOR CREDIT FOR DELETE ASPHALT AND DELETE… |
| Mod P00026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-10-30 | +$10,931 | $8,641,559 | CLINICAL ADDITION, B31 MODIFICATION P00026 - SUPPLEMENTAL AGREEMENT FOR WORK IN ACCORDANCE WITH BULLETIN #49… |
| Mod P00027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-11-08 | +$8,458 | $8,650,017 | CLINICAL ADDITION, B31 MODIFICATION P00027 - SUPPLEMENTAL AGREEMENT FOR WORK IN ACCORDANCE WITH BULLETIN #66 |
| Mod P00028· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-12-10 | +$3,035 | $8,653,052 | CLINICAL ADDITION, B31 MODIFICATION P00028 - SUPPLEMENTAL AGREEMENT FOR EXISTING FLOOR PLAN THICKNESS WORK,… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI GKUMJS8XRVP5)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24225P1478 | 242-NETWORK CONTRACT OFFICE 02 (36C242) · J036 · MAINT/REPAIR/REBUILD OF EQUIPMENT- SPECIAL INDUSTRY MACHINERY | $244,837 | FY2025 |
| 36C24818N4749 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $1,000 | FY2018 |
| 36C24818D0110 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $0 | FY2018 |
| 36C24818C0024 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $334,198 | FY2018 |
| VA24817C0225 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $232,796 | FY2017 |
| VA24817P3530 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · 4410 · INDUSTRIAL BOILERS | $50,000 | FY2017 |
Other recipients under Y1DZ from 250-NETWORK CONTRACT OFFICE 10 (36C250) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C25026P0850 | UTILITIES INSTRUMENTATION SERVICE INCORPORATED | 250-NETWORK CONTRACT OFFICE 10 (36C250) | $52,825 | FY2026 |
| 36C25025P1168 | C. SMITH CONSTRUCTION LLC | 250-NETWORK CONTRACT OFFICE 10 (36C250) | $23,438 | FY2025 |
| 36C25024P1827 | ED RIKE PLUMBING, INC. | 250-NETWORK CONTRACT OFFICE 10 (36C250) | $201,096 | FY2024 |
| 36C25023C0095 | ANDERSON & SONS CONTRACTING LLC | 250-NETWORK CONTRACT OFFICE 10 (36C250) | $37,750 | FY2023 |
| 36C25022P1806 | EAGLE CONTRACTORS, INC. | 250-NETWORK CONTRACT OFFICE 10 (36C250) | $24,117 | FY2022 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA25014C0102_3600_-NONE-_-NONE- · retrieved 2026-09-26.