Description
A/E IDIQ>$50K; REPLACE SITE PAVING PROJECT AT CHALMERS P. WYLIE VA AMBULATORY CARE CENTER - COLUMBUS, OH; NRM PROJECT NUMBER 757-15-205; ADMINISTRATIVE MODIFICATION NEW CONTRACTING OFFICER REPRESENTATIVE (COR)- PHILIP BRUNO; IGF::OT::IGF
Base award description: A/E IDIQ>$50K; REPLACE SITE PAVING PROJECT AT CHALMERS P. WYLIE VA AMBULATORY CARE CENTER - COLUMBUS, OH; NRM PROJECT NUMBER 757-15-205; IGF::OT::IGF
Modification chain · 2 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2013-09-12+$54,702= $54,702
- Mod P000012014-01-22+$0= $54,702
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2013-09-12 | +$54,702 | $54,702 | A/E IDIQ>$50K; REPLACE SITE PAVING PROJECT AT CHALMERS P. WYLIE VA AMBULATORY CARE CENTER - COLUMBUS, OH; NRM… |
| Mod P00001· OTHER ADMINISTRATIVE ACTION | 2014-01-22 | +$0 | $54,702 | A/E IDIQ>$50K; REPLACE SITE PAVING PROJECT AT CHALMERS P. WYLIE VA AMBULATORY CARE CENTER - COLUMBUS, OH; NRM… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI N597YDYWH699)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C25024P1724 | 250-NETWORK CONTRACT OFFICE 10 (36C250) · H345 · INSPECTION- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT | $18,500 | FY2024 |
| VA70114J0137 | PCAC NATIONAL ENERGY BUSINESS CENTER (36E776) · C211 · ARCHITECT AND ENGINEERING- GENERAL: LANDSCAPING, INTERIOR LAYOUT, AND DESIGNING | $1,362,424 | FY2014 |
| VA25014J1675 | 250-NETWORK CONTRACT OFFICE 10 (36C250) · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $127,167 | FY2014 |
| VA70114J0081 | PCAC NATIONAL ENERGY BUSINESS CENTER · C1MC · ARCHITECT AND ENGINEERING- CONSTRUCTION: EPG FACILITIES - GEOTHERMAL | $544,131 | FY2014 |
| VA25014J0573 | 757-COLUMBUS · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $409,945 | FY2014 |
| VA25014J0196 | 539-CINCINNATI · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $51,204 | FY2014 |
Other recipients under C1DZ from 757-COLUMBUS (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA25016J0713 | GUIDON DESIGN INC | 757-COLUMBUS | $86,485 | FY2016 |
| VA25016J0715 | CBLH DESIGN INC | 757-COLUMBUS | $93,121 | FY2016 |
| VA25015J1130 | GUIDON DESIGN INC | 757-COLUMBUS | $18,059 | FY2015 |
| VA25015J1043 | MEACHAM & APEL, ARCHITECTS, INC. | 757-COLUMBUS | $13,675 | FY2015 |
| VA25014J1916 | DYNAMIX ENGINEERING LTD | 757-COLUMBUS | $18,022 | FY2014 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA25013J1838_3600_VA25012D0009_3600 · retrieved 2026-09-26.