TAS::36 0158::TAS REPLACE BOILERS; 9-16-2010: ADMINISTRATIVE CHANGE ORDER REQUEST TO CONTRACTOR

Base award description: TAS::36 0158::TAS REPLACE BOILERS

First action · last action
2010-05-21 · 2012-02-02
Transactions
13
First transaction's obligation
$4,412,800
Base + all options value (sum of deltas)
$4,988,879
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
5
SDVOSB flag on record
Yes (self-representation)
NAICS
238220 · PLUMBING, HEATING, AND AIR-CONDITIONING CONTRACTORS

Modification chain · 13 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$4,988,879$0Base award · 2010-05-21 · this action $4,412,800 · running total $4,412,800Modification 1 · 2010-09-16 · this action $0 · running total $4,412,800Modification 2 · 2010-09-30 · this action $351,702 · running total $4,764,502Modification 3 · 2010-12-08 · this action $3,364 · running total $4,767,866Modification 4 · 2011-03-10 · this action $7,734 · running total $4,775,600Modification 5 · 2011-03-10 · this action $6,140 · running total $4,781,740Modification P00009 · 2011-04-11 · this action $8,208 · running total $4,789,948Modification P00010 · 2011-05-11 · this action $1,227 · running total $4,791,175Modification 6 · 2011-08-27 · this action $15,985 · running total $4,807,160Modification 7 · 2011-08-27 · this action $2,769 · running total $4,809,929Modification 8 · 2011-08-27 · this action $3,651 · running total $4,813,580Modification P00011 · 2012-02-02 · this action $2,998 · running total $4,816,578Modification P00012 · 2012-02-02 · this action $172,301 · running total $4,988,879
  • Base2010-05-21+$4,412,800= $4,412,800
  • Mod 12010-09-16+$0= $4,412,800
  • Mod 22010-09-30+$351,702= $4,764,502
  • Mod 32010-12-08+$3,364= $4,767,866
  • Mod 42011-03-10+$7,734= $4,775,600
  • Mod 52011-03-10+$6,140= $4,781,740
  • Mod P000092011-04-11+$8,208= $4,789,948
  • Mod P000102011-05-11+$1,227= $4,791,175
  • Mod 62011-08-27+$15,985= $4,807,160
  • Mod 72011-08-27+$2,769= $4,809,929
  • Mod 82011-08-27+$3,651= $4,813,580
  • Mod P000112012-02-02+$2,998= $4,816,578
  • Mod P000122012-02-02+$172,301= $4,988,879
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2010-05-21+$4,412,800$4,412,800TAS::36 0158::TAS REPLACE BOILERS
Mod 1· OTHER ADMINISTRATIVE ACTION2010-09-16+$0$4,412,800TAS::36 0158::TAS REPLACE BOILERS; 9-16-2010: ADMINISTRATIVE CHANGE ORDER REQUEST TO CONTRACTOR
Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-30+$351,702$4,764,502TAS::36 0158::TAS REPLACE BOILERS. 9-30-2010: CONTRACTOR TO PROVIDE CONSTRUCTION SERVICES FOR ASBESTOS ABATEME…
Mod 3· OTHER ADMINISTRATIVE ACTION2010-12-08+$3,364$4,767,866TAS::36 0158::TAS REPLACE BOILERS; 9-16-2010: ADMINISTRATIVE CHANGE ORDER REQUEST TO CONTRACTOR
Mod 4· OTHER ADMINISTRATIVE ACTION2011-03-10+$7,734$4,775,600TAS::36 0158::TAS REPLACE BOILERS; 9-16-2010: ADMINISTRATIVE CHANGE ORDER REQUEST TO CONTRACTOR
Mod 5· OTHER ADMINISTRATIVE ACTION2011-03-10+$6,140$4,781,740TAS::36 0158::TAS REPLACE BOILERS; 9-16-2010: ADMINISTRATIVE CHANGE ORDER REQUEST TO CONTRACTOR
Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-04-11+$8,208$4,789,948TAS::36 0158::TAS REPLACE BOILERS; 9-16-2010: ADMINISTRATIVE CHANGE ORDER REQUEST TO CONTRACTOR
Mod P00010· OTHER ADMINISTRATIVE ACTION2011-05-11+$1,227$4,791,175TAS::36 0158::TAS REPLACE BOILERS; 9-16-2010: ADMINISTRATIVE CHANGE ORDER REQUEST TO CONTRACTOR
Mod 6· OTHER ADMINISTRATIVE ACTION2011-08-27+$15,985$4,807,160TAS::36 0158::TAS REPLACE BOILERS; 9-16-2010: ADMINISTRATIVE CHANGE ORDER REQUEST TO CONTRACTOR
Mod 7· OTHER ADMINISTRATIVE ACTION2011-08-27+$2,769$4,809,929TAS::36 0158::TAS REPLACE BOILERS; 9-16-2010: ADMINISTRATIVE CHANGE ORDER REQUEST TO CONTRACTOR
Mod 8· OTHER ADMINISTRATIVE ACTION2011-08-27+$3,651$4,813,580TAS::36 0158::TAS REPLACE BOILERS; 9-16-2010: ADMINISTRATIVE CHANGE ORDER REQUEST TO CONTRACTOR
Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-02+$2,998$4,816,578TAS::36 0158::TAS REPLACE BOILERS; 9-16-2010: ADMINISTRATIVE CHANGE ORDER REQUEST TO CONTRACTOR
Mod P00012· OTHER ADMINISTRATIVE ACTION2012-02-02+$172,301$4,988,879TAS::36 0158::TAS REPLACE BOILERS; 9-16-2010: ADMINISTRATIVE CHANGE ORDER REQUEST TO CONTRACTOR

Related awards · 5

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other recipients under Y249 from 603-LOUISVILLE (most recent first)

AwardRecipientOfficeNet obligationsFY
VA249C0882UNITED CONSTRUCTION & DESIGN, LLC603-LOUISVILLE$1,491,125FY2011
VA249C0856FLEET SERVICES AND INSTALLATIONS, LLC603-LOUISVILLE$1,389,500FY2010
VA249C0839APOLLO INDUSTRIES, LLC603-LOUISVILLE$6,300FY2010
VA249C0596CONTRACNORTHVIEW ENTERPRISES, INC603-LOUISVILLE$993,550FY2010
VA249RA0597APOLLO INDUSTRIES, LLC603-LOUISVILLE$337,277FY2010

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA249RA0594_3600_-NONE-_-NONE- · retrieved 2026-09-26.