Description
RENOVATE RESEARCH LAB PHASE 3 - MOD-10 TIME EXTEND TO REVIEW OEM'S AND COMMISSIONING REPORT FOR CLOSEOUT
Base award description: RENOVATE RESEARCH LAB PHASE 3
Modification chain · 11 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2011-06-24+$502,910= $502,910
- Mod P000012012-08-14+$0= $502,910
- Mod P000022012-10-30+$0= $502,910
- Mod P000032013-09-06+$0= $502,910
- Mod P000042014-01-29+$0= $502,910
- Mod P000052014-10-10+$0= $502,910
- Mod P000062014-11-27+$0= $502,910
- Mod P000072015-03-15+$0= $502,910
- Mod P000082015-06-26+$0= $502,910
- Mod P000092015-07-24+$0= $502,910
- Mod P000102015-09-14+$0= $502,910
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2011-06-24 | +$502,910 | $502,910 | RENOVATE RESEARCH LAB PHASE 3 |
| Mod P00001· CHANGE ORDER | 2012-08-14 | +$0 | $502,910 | RENOVATE RESEARCH LAB PHASE 3 |
| Mod P00002· CHANGE ORDER | 2012-10-30 | +$0 | $502,910 | RENOVATE RESEARCH LAB PHASE 3 |
| Mod P00003· CHANGE ORDER | 2013-09-06 | +$0 | $502,910 | RENOVATE RESEARCH LAB PHASE 3 |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-01-29 | +$0 | $502,910 | RENOVATE RESEARCH LAB PHASE 3 |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-10-10 | +$0 | $502,910 | RENOVATE RESEARCH LAB PHASE 3 |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-11-27 | +$0 | $502,910 | RENOVATE RESEARCH LAB PHASE 3 - MOD-6 TIME EXTEND |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-03-15 | +$0 | $502,910 | RENOVATE RESEARCH LAB PHASE 3 - MOD-7 TIME EXTEND |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-06-26 | +$0 | $502,910 | RENOVATE RESEARCH LAB PHASE 3 - MOD-8 TIME EXTEND TO COMPLETE ALL REQUIREMENTS |
| Mod P00009· CHANGE ORDER | 2015-07-24 | +$0 | $502,910 | RENOVATE RESEARCH LAB PHASE 3 - MOD-9 TIME EXTEND TO COMPLETE ALL FINAL REQUIREMENTS |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-14 | +$0 | $502,910 | RENOVATE RESEARCH LAB PHASE 3 - MOD-10 TIME EXTEND TO REVIEW OEM'S AND COMMISSIONING REPORT FOR CLOSEOUT |
Related awards · 5
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other recipients under C114 from 626-NASHVILLE (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| V249P0981 | HFR INC | 626-NASHVILLE | $0 | FY2012 |
| VA249P0103 | HFR INC | 626-NASHVILLE | -$33,209 | FY2012 |
| VA249C1241 | DOUBLE R CONSTRUCTION, LLC | 626-NASHVILLE | $1,131,634 | FY2011 |
| VA249C1143 | MAZZETTI, INC. | 626-NASHVILLE | $0 | FY2011 |
| VA249P1124 | PINNACLE ENGINEERING INC | 626-NASHVILLE | $129,702 | FY2011 |