Description
IGF:OT::IGF AMBULATORY SURGERY PHASE 3
Base award description: AMBULATORY SURGERY PHASE 3
Modification chain · 22 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2011-05-10+$1,676,897= $1,676,897
- Mod P000012012-01-31+$53,292= $1,730,189
- Mod P000032012-04-30+$0= $1,730,189
- Mod P000042012-07-30+$0= $1,730,189
- Mod P000062012-09-28+$0= $1,730,189
- Mod P000082012-10-29+$0= $1,730,189
- Mod P000052012-11-09+$57,370= $1,787,559
- Mod P000092012-11-15+$0= $1,787,559
- Mod P000072013-01-02+$19,000= $1,806,558
- Mod P000112013-02-06+$0= $1,806,558
- Mod P000122013-02-19+$0= $1,806,558
- Mod P000102013-03-11+$42,602= $1,849,161
- Mod P000132013-03-29+$0= $1,849,161
- Mod P000142013-04-08+$0= $1,849,161
- Mod P000152013-04-18+$0= $1,849,161
- Mod P000162013-05-09+$0= $1,849,161
- Mod P000172013-06-10+$0= $1,849,161
- Mod P000182013-11-07+$0= $1,849,161
- Mod P000192014-02-25+$20,266= $1,869,427
- Mod P000202014-04-23+$163,813= $2,033,240
- Mod P000212014-05-19+$11,093= $2,044,333
- Mod P000222014-06-17+$521= $2,044,854
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2011-05-10 | +$1,676,897 | $1,676,897 | AMBULATORY SURGERY PHASE 3 |
| Mod P00001· CHANGE ORDER | 2012-01-31 | +$53,292 | $1,730,189 | AMBULATORY SURGERY PHASE 3 |
| Mod P00003· CHANGE ORDER | 2012-04-30 | +$0 | $1,730,189 | AMBULATORY SURGERY PHASE 3 |
| Mod P00004· CHANGE ORDER | 2012-07-30 | +$0 | $1,730,189 | AMBULATORY SURGERY PHASE 3 |
| Mod P00006· CHANGE ORDER | 2012-09-28 | +$0 | $1,730,189 | AMBULATORY SURGERY PHASE 3 |
| Mod P00008· CHANGE ORDER | 2012-10-29 | +$0 | $1,730,189 | AMBULATORY SURGERY PHASE 3 |
| Mod P00005· CHANGE ORDER | 2012-11-09 | +$57,370 | $1,787,559 | AMBULATORY SURGERY PHASE 3 |
| Mod P00009· CHANGE ORDER | 2012-11-15 | +$0 | $1,787,559 | AMBULATORY SURGERY PHASE 3 |
| Mod P00007· CHANGE ORDER | 2013-01-02 | +$19,000 | $1,806,558 | IGF::OT:IGF AMBULATORY SURGERY PHASE 3 |
| Mod P00011· CHANGE ORDER | 2013-02-06 | +$0 | $1,806,558 | IGF::OT:IGF AMBULATORY SURGERY PHASE 3 |
| Mod P00012· OTHER ADMINISTRATIVE ACTION | 2013-02-19 | +$0 | $1,806,558 | IGF::OT:IGF AMBULATORY SURGERY PHASE 3 |
| Mod P00010· CHANGE ORDER | 2013-03-11 | +$42,602 | $1,849,161 | IGF:OT::IGF AMBULATORY SURGERY PHASE 3 |
| Mod P00013· CHANGE ORDER | 2013-03-29 | +$0 | $1,849,161 | IGF:OT::IGF AMBULATORY SURGERY PHASE 3 |
| Mod P00014· CHANGE ORDER | 2013-04-08 | +$0 | $1,849,161 | IGF:OT::IGF AMBULATORY SURGERY PHASE 3 |
| Mod P00015· CHANGE ORDER | 2013-04-18 | +$0 | $1,849,161 | IGF:OT::IGF AMBULATORY SURGERY PHASE 3 |
| Mod P00016· CHANGE ORDER | 2013-05-09 | +$0 | $1,849,161 | IGF:OT::IGF AMBULATORY SURGERY PHASE 3 |
| Mod P00017· CHANGE ORDER | 2013-06-10 | +$0 | $1,849,161 | IGF:OT::IGF AMBULATORY SURGERY PHASE 3 |
| Mod P00018· CHANGE ORDER | 2013-11-07 | +$0 | $1,849,161 | IGF:OT::IGF AMBULATORY SURGERY PHASE 3 |
| Mod P00019· CHANGE ORDER | 2014-02-25 | +$20,266 | $1,869,427 | IGF:OT::IGF AMBULATORY SURGERY PHASE 3 |
| Mod P00020· CHANGE ORDER | 2014-04-23 | +$163,813 | $2,033,240 | IGF:OT::IGF AMBULATORY SURGERY PHASE 3 |
| Mod P00021· CHANGE ORDER | 2014-05-19 | +$11,093 | $2,044,333 | IGF:OT::IGF AMBULATORY SURGERY PHASE 3 |
| Mod P00022· CHANGE ORDER | 2014-06-17 | +$521 | $2,044,854 | IGF:OT::IGF AMBULATORY SURGERY PHASE 3 |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI H61LKCMRF271)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA24913C0139 | 626-NASHVILLE · Z2NB · REPAIR OR ALTERATION OF HEATING AND COOLING PLANTS | $32,331 | FY2013 |
| VA24913C0143 | 626-NASHVILLE · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $22,658 | FY2013 |
| VA24913C0083 | 626-NASHVILLE (00626) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $5,372,315 | FY2013 |
| VA24913C0076 | 626-NASHVILLE · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $1,522,638 | FY2013 |
| VA24913C0069 | 626-NASHVILLE · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $343,174 | FY2013 |
| VA24913C0072 | 626-NASHVILLE · J056 · MAINT/REPAIR/REBUILD OF EQUIPMENT- CONSTRUCTION AND BUILDING MATERIALS | $1,153,196 | FY2013 |
Other recipients under Z141 from 626-NASHVILLE (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA626C11166 | HICAPS INC | 626-NASHVILLE | $5,561 | FY2011 |
| VA249C1136 | VYKON INCORPORATED | 626-NASHVILLE | $54,964 | FY2011 |
| VA249C1131 | FIDELIS VETERAN CONSTRUCTION INCORPORATED | 626-NASHVILLE | $28,880 | FY2011 |
| VA626C10805 | HICAPS INC | 626-NASHVILLE | $60,680 | FY2011 |
| VA249C1121 | VYKON INCORPORATED | 626-NASHVILLE | $4,774 | FY2011 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA249C1122_3600_-NONE-_-NONE- · retrieved 2026-09-26.