Award recordCONTRACT

DOUBLE R CONSTRUCTION, LLC

PIID VA249C1122· VHA· 626-NASHVILLE· Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY· FY2011· $2,044,854 net obligations· UEI H61LKCMRF271· TN

Description

IGF:OT::IGF AMBULATORY SURGERY PHASE 3

Base award description: AMBULATORY SURGERY PHASE 3

First action · last action
2011-05-10 · 2014-06-17
Transactions
22
First transaction's obligation
$1,676,897
Base + all options value (sum of deltas)
$2,044,854
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
10
SDVOSB flag on record
Yes (self-representation)
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION

Modification chain · 22 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$2,044,854$0Base award · 2011-05-10 · this action $1,676,897 · running total $1,676,897Modification P00001 · 2012-01-31 · this action $53,292 · running total $1,730,189Modification P00003 · 2012-04-30 · this action $0 · running total $1,730,189Modification P00004 · 2012-07-30 · this action $0 · running total $1,730,189Modification P00006 · 2012-09-28 · this action $0 · running total $1,730,189Modification P00008 · 2012-10-29 · this action $0 · running total $1,730,189Modification P00005 · 2012-11-09 · this action $57,370 · running total $1,787,559Modification P00009 · 2012-11-15 · this action $0 · running total $1,787,559Modification P00007 · 2013-01-02 · this action $19,000 · running total $1,806,558Modification P00011 · 2013-02-06 · this action $0 · running total $1,806,558Modification P00012 · 2013-02-19 · this action $0 · running total $1,806,558Modification P00010 · 2013-03-11 · this action $42,602 · running total $1,849,161Modification P00013 · 2013-03-29 · this action $0 · running total $1,849,161Modification P00014 · 2013-04-08 · this action $0 · running total $1,849,161Modification P00015 · 2013-04-18 · this action $0 · running total $1,849,161Modification P00016 · 2013-05-09 · this action $0 · running total $1,849,161Modification P00017 · 2013-06-10 · this action $0 · running total $1,849,161Modification P00018 · 2013-11-07 · this action $0 · running total $1,849,161Modification P00019 · 2014-02-25 · this action $20,266 · running total $1,869,427Modification P00020 · 2014-04-23 · this action $163,813 · running total $2,033,240Modification P00021 · 2014-05-19 · this action $11,093 · running total $2,044,333Modification P00022 · 2014-06-17 · this action $521 · running total $2,044,854
  • Base2011-05-10+$1,676,897= $1,676,897
  • Mod P000012012-01-31+$53,292= $1,730,189
  • Mod P000032012-04-30+$0= $1,730,189
  • Mod P000042012-07-30+$0= $1,730,189
  • Mod P000062012-09-28+$0= $1,730,189
  • Mod P000082012-10-29+$0= $1,730,189
  • Mod P000052012-11-09+$57,370= $1,787,559
  • Mod P000092012-11-15+$0= $1,787,559
  • Mod P000072013-01-02+$19,000= $1,806,558
  • Mod P000112013-02-06+$0= $1,806,558
  • Mod P000122013-02-19+$0= $1,806,558
  • Mod P000102013-03-11+$42,602= $1,849,161
  • Mod P000132013-03-29+$0= $1,849,161
  • Mod P000142013-04-08+$0= $1,849,161
  • Mod P000152013-04-18+$0= $1,849,161
  • Mod P000162013-05-09+$0= $1,849,161
  • Mod P000172013-06-10+$0= $1,849,161
  • Mod P000182013-11-07+$0= $1,849,161
  • Mod P000192014-02-25+$20,266= $1,869,427
  • Mod P000202014-04-23+$163,813= $2,033,240
  • Mod P000212014-05-19+$11,093= $2,044,333
  • Mod P000222014-06-17+$521= $2,044,854
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2011-05-10+$1,676,897$1,676,897AMBULATORY SURGERY PHASE 3
Mod P00001· CHANGE ORDER2012-01-31+$53,292$1,730,189AMBULATORY SURGERY PHASE 3
Mod P00003· CHANGE ORDER2012-04-30+$0$1,730,189AMBULATORY SURGERY PHASE 3
Mod P00004· CHANGE ORDER2012-07-30+$0$1,730,189AMBULATORY SURGERY PHASE 3
Mod P00006· CHANGE ORDER2012-09-28+$0$1,730,189AMBULATORY SURGERY PHASE 3
Mod P00008· CHANGE ORDER2012-10-29+$0$1,730,189AMBULATORY SURGERY PHASE 3
Mod P00005· CHANGE ORDER2012-11-09+$57,370$1,787,559AMBULATORY SURGERY PHASE 3
Mod P00009· CHANGE ORDER2012-11-15+$0$1,787,559AMBULATORY SURGERY PHASE 3
Mod P00007· CHANGE ORDER2013-01-02+$19,000$1,806,558IGF::OT:IGF AMBULATORY SURGERY PHASE 3
Mod P00011· CHANGE ORDER2013-02-06+$0$1,806,558IGF::OT:IGF AMBULATORY SURGERY PHASE 3
Mod P00012· OTHER ADMINISTRATIVE ACTION2013-02-19+$0$1,806,558IGF::OT:IGF AMBULATORY SURGERY PHASE 3
Mod P00010· CHANGE ORDER2013-03-11+$42,602$1,849,161IGF:OT::IGF AMBULATORY SURGERY PHASE 3
Mod P00013· CHANGE ORDER2013-03-29+$0$1,849,161IGF:OT::IGF AMBULATORY SURGERY PHASE 3
Mod P00014· CHANGE ORDER2013-04-08+$0$1,849,161IGF:OT::IGF AMBULATORY SURGERY PHASE 3
Mod P00015· CHANGE ORDER2013-04-18+$0$1,849,161IGF:OT::IGF AMBULATORY SURGERY PHASE 3
Mod P00016· CHANGE ORDER2013-05-09+$0$1,849,161IGF:OT::IGF AMBULATORY SURGERY PHASE 3
Mod P00017· CHANGE ORDER2013-06-10+$0$1,849,161IGF:OT::IGF AMBULATORY SURGERY PHASE 3
Mod P00018· CHANGE ORDER2013-11-07+$0$1,849,161IGF:OT::IGF AMBULATORY SURGERY PHASE 3
Mod P00019· CHANGE ORDER2014-02-25+$20,266$1,869,427IGF:OT::IGF AMBULATORY SURGERY PHASE 3
Mod P00020· CHANGE ORDER2014-04-23+$163,813$2,033,240IGF:OT::IGF AMBULATORY SURGERY PHASE 3
Mod P00021· CHANGE ORDER2014-05-19+$11,093$2,044,333IGF:OT::IGF AMBULATORY SURGERY PHASE 3
Mod P00022· CHANGE ORDER2014-06-17+$521$2,044,854IGF:OT::IGF AMBULATORY SURGERY PHASE 3

Related awards · 11

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI H61LKCMRF271)

AwardOffice · PSC / listingNet obligationsFY
VA24913C0139626-NASHVILLE · Z2NB · REPAIR OR ALTERATION OF HEATING AND COOLING PLANTS$32,331FY2013
VA24913C0143626-NASHVILLE · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$22,658FY2013
VA24913C0083626-NASHVILLE (00626) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES$5,372,315FY2013
VA24913C0076626-NASHVILLE · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$1,522,638FY2013
VA24913C0069626-NASHVILLE · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$343,174FY2013
VA24913C0072626-NASHVILLE · J056 · MAINT/REPAIR/REBUILD OF EQUIPMENT- CONSTRUCTION AND BUILDING MATERIALS$1,153,196FY2013

Other recipients under Z141 from 626-NASHVILLE (most recent first)

AwardRecipientOfficeNet obligationsFY
VA626C11166HICAPS INC626-NASHVILLE$5,561FY2011
VA249C1136VYKON INCORPORATED626-NASHVILLE$54,964FY2011
VA249C1131FIDELIS VETERAN CONSTRUCTION INCORPORATED626-NASHVILLE$28,880FY2011
VA626C10805HICAPS INC626-NASHVILLE$60,680FY2011
VA249C1121VYKON INCORPORATED626-NASHVILLE$4,774FY2011