Description
IGF::OT::IGF MODIFICATION OF DELIVERY ORDER THAT COMPENSATES CONTRACTOR FOR UTILITY COSTS.
Base award description: INSTALLATION OF TWO MODULAR BUILDINGS
Modification chain · 14 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2014-09-26+$5,799,414= $5,799,414
- Mod P000012015-08-03+$56,800= $5,856,214
- Mod P000022015-10-01+$0= $5,856,214
- Mod P000032015-10-07+$0= $5,856,214
- Mod P000042015-12-11+$133,478= $5,989,692
- Mod P000052015-12-22+$0= $5,989,692
- Mod P000062016-02-16+$0= $5,989,692
- Mod P000072016-03-08+$0= $5,989,692
- Mod P000082016-03-28+$0= $5,989,692
- Mod P00092016-08-16+$39,095= $6,028,787
- Mod P000102016-10-04+$189,751= $6,218,538
- Mod P000112017-05-26+$18,396= $6,236,934
- Mod P000122017-07-21-$42,455= $6,194,479
- Mod P000132017-11-22+$519,045= $6,713,523
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2014-09-26 | +$5,799,414 | $5,799,414 | INSTALLATION OF TWO MODULAR BUILDINGS |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-08-03 | +$56,800 | $5,856,214 | MODIFIED TO EXERCISE SUPPLEMENTAL OPTIONS TO ADD MECHANICAL ENCLOSURE GATE AND PROVIDE OVERHEAD PAGING SYSTEM… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-10-01 | +$0 | $5,856,214 | MODIFIED TO SUSPEND WORK AT THE NASHVILLE FACILITY. |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-10-07 | +$0 | $5,856,214 | MODIFIED TO EXTEND THE COMPLETION DATE TO ACCOUNT FOR WEATHER DELAYS AND UNSUITABLE SOILS. |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-12-11 | +$133,478 | $5,989,692 | MODIFIED TO RELOCATE TELEPHONE LINES. |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-12-22 | +$0 | $5,989,692 | MODIFIED TO EXTEND THE PERIOD OF PERFORMANCE TO 2/16/2016. |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-02-16 | +$0 | $5,989,692 | MODIFIED TO EXTEND THE PERIOD OF PERFORMANCE TO 2/25/2016 AND EXTENDED 3/17/16 TO ALLOW ADDITIONAL TIME FOR GR… |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-03-08 | +$0 | $5,989,692 | MODIFIED TO EXTEND THE PERIOD OF PERFORMANCE TO 3/25/2016 AND IN CONSIDERATION FOR A TIME EXTENSION, THE CONTR… |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-03-28 | +$0 | $5,989,692 | MODIFIED TO EXTEND THE PERIOD OF PERFORMANCE TO 04/15/2016 AND IN CONSIDERATION FOR A 21 DAY TIME EXTENSION, T… |
| Mod P0009· CHANGE ORDER | 2016-08-16 | +$39,095 | $6,028,787 | IGF::OT::IGF MODIFICATION OF DELIVERY ORDER THAT PROVIDES EXTRA FUNDING FOR THE CONCRETE SUBCONTRACTOR AND EXT… |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-10-04 | +$189,751 | $6,218,538 | IGF::OT::IGF MODIFICATION OF DELIVERY ORDER THAT ACCELERATES THE SCHEDULE FOR THE NASHVILLE MODULAR PROJECT. |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-05-26 | +$18,396 | $6,236,934 | IGF::OT::IGF MODIFICATION OF DELIVERY ORDER THAT COMPENSATES CONTRACTOR FOR UTILITY COSTS. |
| Mod P00012· OTHER ADMINISTRATIVE ACTION | 2017-07-21 | −$42,455 | $6,194,479 | IGF::OT::IGF MODIFICATION OF DELIVERY ORDER THAT COMPENSATES CONTRACTOR FOR UTILITY COSTS. |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-11-22 | +$519,045 | $6,713,523 | IGF::OT::IGF MODIFICATION OF DELIVERY ORDER THAT COMPENSATES CONTRACTOR FOR UTILITY COSTS. |
Related awards · 6
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI E5FHVYFNF2L7)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA24613F0890 | 246-NETWORK CONTRACTING OFFICE 6 · W054 · LEASE OR RENTAL OF EQUIPMENT- PREFABRICATED STRUCTURES AND SCAFFOLDING | $230,896 | FY2013 |
| VA590C10434 | 246-NETWORK CONTRACTING OFFICE 6 · N054 · INSTALLATION OF EQUIPMENT- PREFABRICATED STRUCTURES AND SCAFFOLDING | $498,559 | FY2011 |
| VA590C10433 | 246-NETWORK CONTRACTING OFFICE 6 · N054 · INSTALLATION OF EQUIPMENT- PREFABRICATED STRUCTURES AND SCAFFOLDING | $498,100 | FY2011 |
| VA590C00562 | 246-NETWORK CONTRACTING OFFICE 6 · Y149 · CONSTRUCT/OTHER HOSPITAL BLDGS | $667,135 | FY2010 |
| VA570A00465 | 570-FRESNO · 5410 · PREFABRICATED & PORTABLE BUILDINGS | $159,550 | FY2010 |
| VA644Z00016 | 644-PHOENIX · Z224 · MAINT-REP-ALT/PARKING FACILITIES | $6,638 | FY2010 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA24914F3236_3600_GS07F0549T_4730 · retrieved 2026-09-26.