OPTION YEAR 4 - UPS MAINTENANCE
Base award description: UPS PREVENTATIVE MAINTENANCE
Modification chain · 9 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2010-06-22+$26,200= $26,200
- Mod 12010-08-11+$0= $26,200
- Mod 22010-11-08+$13,110= $39,310
- Mod 32011-06-22+$26,200= $65,510
- Mod P000042012-06-01+$26,200= $91,710
- Mod P000052012-06-01+$0= $91,710
- Mod P000062012-09-17+$17,738= $109,448
- Mod P000072013-05-23+$26,200= $135,648
- Mod P000082014-05-21+$26,200= $161,848
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2010-06-22 | +$26,200 | $26,200 | UPS PREVENTATIVE MAINTENANCE |
| Mod 1· OTHER ADMINISTRATIVE ACTION | 2010-08-11 | +$0 | $26,200 | UPS PREVENTATIVE MAINTENANCE |
| Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-11-08 | +$13,110 | $39,310 | UPS PREVENTATIVE MAINTENANCE |
| Mod 3· EXERCISE AN OPTION | 2011-06-22 | +$26,200 | $65,510 | UPS PREVENTATIVE MAINTENANCE OPTION YEAR 1 |
| Mod P00004· EXERCISE AN OPTION | 2012-06-01 | +$26,200 | $91,710 | UPS PREVENTATIVE MAINTENANCE OPTION YEAR 2 |
| Mod P00005· OTHER ADMINISTRATIVE ACTION | 2012-06-01 | +$0 | $91,710 | CORRECTION TO DATES OF MOD 003 |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-09-17 | +$17,738 | $109,448 | CRITICAL MAINTENANCE AND REPAIRS UPS |
| Mod P00007· EXERCISE AN OPTION | 2013-05-23 | +$26,200 | $135,648 | OPTION YEAR 3 - UPS MAINTENANCE |
| Mod P00008· EXERCISE AN OPTION | 2014-05-21 | +$26,200 | $161,848 | OPTION YEAR 4 - UPS MAINTENANCE |
Related awards · 10
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI JV16MG5JV5V1)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA24815P1607 | 248-NETWORK CONTRACT OFFICE 8 · 6135 · BATTERIES, NONRECHARGEABLE | $14,098 | FY2015 |
| VA24813P0146 | 248-NETWORK CONTRACT OFFICE 8 · 6140 · BATTERIES, RECHARGEABLE | $12,322 | FY2013 |
| VA24812P3066 | 548-WEST PALM · 6140 · BATTERIES, RECHARGEABLE | $7,598 | FY2012 |
| VA24812P2295 | 548-WEST PALM · J059 · MAINT/REPAIR/REBUILD OF EQUIPMENT- ELECTRICAL AND ELECTRONIC EQUIPMENT COMPONENTS | $4,339 | FY2012 |
| VA248P0741 | 248-NETWORK CONTRACT OFFICE 8 · 6150 · MISCELLANEOUS ELECTRIC POWER AND DISTRIBUTION EQUIPMENT | $88,117 | FY2009 |
Other recipients under J059 from 248-NETWORK CONTRACT OFFICE 8 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA24816P0523 | MIAMI BREAKER, INC. | 248-NETWORK CONTRACT OFFICE 8 | $6,800 | FY2016 |
| VA24815F3164 | TL SERVICES, INC. | 248-NETWORK CONTRACT OFFICE 8 | $21,878 | FY2015 |
| VA24815P3056 | ASCO POWER SERVICES INC | 248-NETWORK CONTRACT OFFICE 8 | $14,027 | FY2015 |
| VA24815P3112 | EATON CORPORATION | 248-NETWORK CONTRACT OFFICE 8 | $9,700 | FY2015 |
| VA24815P2579 | SAN DIEGO PROJECT MANAGEMENT PSC | 248-NETWORK CONTRACT OFFICE 8 | $5,004 | FY2015 |