Description
DESIGN / BUILD ADA HANDICAP RAMP AND STAIRWAY (JAHVAH). TIME EXTENSION REQUIRED TO COMPLETE ADDITIONAL RAMP CHANGES RESULTING FROM DIFFERING SITE CONDITION.
Base award description: DESIGN / BUILD ADA HANDICAP RAMP AND STAIRWAY (JAHVAH)
Modification chain · 4 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-07-31+$95,951= $95,951
- Mod SA012010-02-25+$26,794= $122,745
- Mod SA022010-05-25+$31,812= $154,558
- Mod SA032010-07-29+$0= $154,558
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-07-31 | +$95,951 | $95,951 | DESIGN / BUILD ADA HANDICAP RAMP AND STAIRWAY (JAHVAH) |
| Mod SA01· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-02-25 | +$26,794 | $122,745 | DESIGN / BUILD ADA HANDICAP RAMP AND STAIRWAY (JAHVAH). MODIFICATION FOR ADDITIONAL DESIGN AND CONSTRUCTION TO… |
| Mod SA02· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-05-25 | +$31,812 | $154,558 | DESIGN / BUILD ADA HANDICAP RAMP AND STAIRWAY (JAHVAH). MODIFICATION FOR ADDITIONAL RAMP CHANGES RESULTING FRO… |
| Mod SA03· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-07-29 | +$0 | $154,558 | DESIGN / BUILD ADA HANDICAP RAMP AND STAIRWAY (JAHVAH). TIME EXTENSION REQUIRED TO COMPLETE ADDITIONAL RAMP CH… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI EERXQPG9J2W7)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24626P1040 | 246-NETWORK CONTRACTING OFFICE 6 (36C246) · J045 · MAINT/REPAIR/REBUILD OF EQUIPMENT- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT | $54,813 | FY2026 |
| 36C24126P0345 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · J035 · MAINT/REPAIR/REBUILD OF EQUIPMENT- SERVICE AND TRADE EQUIPMENT | $82,950 | FY2026 |
| 36C24626C0024 | 246-NETWORK CONTRACTING OFFICE 6 (36C246) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $682,942 | FY2026 |
| 36C24825P1955 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · J041 · MAINT/REPAIR/REBUILD OF EQUIPMENT- REFRIGERATION, AIR CONDITIONING, AND AIR CIRCULATING EQUIPMENT | $99,400 | FY2025 |
| 36C24723P0980 | 247-NETWORK CONTRACT OFFICE 7 (36C247) · J043 · MAINT/REPAIR/REBUILD OF EQUIPMENT- PUMPS AND COMPRESSORS | $64,457 | FY2023 |
| 36C24823D0028 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $0 | FY2023 |
Other recipients under Z149 from 673-TAMPA (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA248C1958 | UNLIMITED SERVICE ASSOCIATES INC. | 673-TAMPA | $37,770 | FY2011 |
| VA248C1907 | BECKWITH SERVICES, INC. | 673-TAMPA | $42,409 | FY2011 |
| VA673C10752 | JOHNSON CONTROLS INC | 673-TAMPA | $37,158 | FY2011 |
| VA248C1870 | ABRAMS GROUP CONSTRUCTION LLC | 673-TAMPA | $122,961 | FY2011 |
| VA248C1831 | UNLIMITED SERVICE ASSOCIATES INC. | 673-TAMPA | $126,211 | FY2011 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA248C1140_3600_-NONE-_-NONE- · retrieved 2026-09-26.