MODIFICATION TO EXTEND CONTRACT PERIOD OF PERFORMANCE.
Base award description: HEMODIALYSIS UNIT RELOCATION - JAHVAH, TAMPA, FL.
Modification chain · 7 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-06-12+$2,420,000= $2,420,000
- Mod SA012009-12-18+$0= $2,420,000
- Mod SA022010-02-16+$0= $2,420,000
- Mod SA032010-08-23+$72,547= $2,492,547
- Mod SA042011-01-31+$66,578= $2,559,125
- Mod SA052011-02-09+$14,200= $2,573,325
- Mod SA062011-03-31+$0= $2,573,325
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-06-12 | +$2,420,000 | $2,420,000 | HEMODIALYSIS UNIT RELOCATION - JAHVAH, TAMPA, FL. |
| Mod SA01· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-12-18 | +$0 | $2,420,000 | MODIFICATION TO INCORPORATE REVISED (OCT. 2009) SECTION 10000R (GENERAL REQUIREMENTS). |
| Mod SA02· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-02-16 | +$0 | $2,420,000 | MODIFICATION TO INCORPORATE NOVATION AGREEMENT BETWWEN BLUE CORD CONSTRUCTION, INC., BLUE CORD DESIGN AND CONS… |
| Mod SA03· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-08-23 | +$72,547 | $2,492,547 | MODIFICATION TO INCORPORATE CHANGES TO SPECIFICATIONS FOR MECANICAL ROOM LAY-OUT AND SHOT BLAST METHOD OF MAST… |
| Mod SA04· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-01-31 | +$66,578 | $2,559,125 | MODIFICATION TO INCORPORATE THE DEMO&ABATEMENT OF A/C SHAFT. |
| Mod SA05· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-02-09 | +$14,200 | $2,573,325 | MODIFICATION TO INCORPORATE ADDITIONAL CONSTRUCTION EFFORT; INSTALL MED GAS VALVES AND REPAIR ROOF DRAINS. |
| Mod SA06· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-03-31 | +$0 | $2,573,325 | MODIFICATION TO EXTEND CONTRACT PERIOD OF PERFORMANCE. |
Related awards · 9
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI KZ11UCBDMW84)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA248C1944 | 573-NF/SG VETERANS HEALTH SYSTEM · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $52,508 | FY2011 |
| VA248C1071 | 673-TAMPA · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $97,450 | FY2009 |
| VA248C1054 | 516-BAY PINES · Y300 · CONSTRUCT/RESTORATION | $1,680 | FY2009 |
| VA248C0895 | 673-TAMPA · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $7,757 | FY2009 |
Other recipients under Z141 from 673-TAMPA (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA248C1928 | BLUE CORD DESIGN AND CONSTRUCTION, LLC | 673-TAMPA | $41,363 | FY2011 |
| VA248C1886 | TL SERVICES, INC. | 673-TAMPA | $48,870 | FY2011 |
| VA248C1838 | MIDWESTERN CONSTRUCTION SERVICES, INC. | 673-TAMPA | $61,216 | FY2011 |
| VA673C10506 | ACRO CONSTRUCTION, LLC | 673-TAMPA | $33,774 | FY2011 |
| VA673C10503 | UNLIMITED SERVICE ASSOCIATES INC. | 673-TAMPA | $11,319 | FY2011 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA248C1107_3600_-NONE-_-NONE- · retrieved 2026-09-26.