Award recordCONTRACT

UNLIMITED SERVICE ASSOCIATES INC.

PIID VA24815C0097· VHA· 248-NETWORK CONTRACT OFFICE 8· Y1LZ · CONSTRUCTION OF PARKING FACILITIES· FY2015· $1,766,113 net obligations· UEI KF62ABNCA498· FL

Description

IGF::OT::IGF - ST. AUGUSTINE MANDATED SITE CHANGES - DESIGN BUILD SITE PREP CONSTRUCT PARKING LOT AT ST AUGUSTINE INTERIM CBOC, ST AUGUSTINE FL

Base award description: IGF::OT::IGF - DESIGN BUILD SITE PREP CONSTRUCT PARKING LOT AT ST AUGUSTINE INTERIM CBOC, ST AUGUSTINE FL

First action · last action
2015-04-02 · 2015-09-30
Transactions
13
First transaction's obligation
$1,240,003
Base + all options value (sum of deltas)
$1,766,113
Extent competed
NOT AVAILABLE FOR COMPETITION
Other than full & open authority
AUTHORIZED BY STATUTE
Set-aside
SDVOSB SOLE SOURCE
Offers received
1
SDVOSB flag on record
Yes (self-representation)
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION

Modification chain · 13 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$1,766,113$0Base award · 2015-04-02 · this action $1,240,003 · running total $1,240,003Modification P00001 · 2015-05-22 · this action $21,500 · running total $1,261,503Modification P00002 · 2015-06-10 · this action $27,425 · running total $1,288,928Modification P00003 · 2015-07-01 · this action $98,100 · running total $1,387,028Modification P00004 · 2015-07-07 · this action -$4,383 · running total $1,382,645Modification P00005 · 2015-07-29 · this action $70,368 · running total $1,453,013Modification P00006 · 2015-08-12 · this action $0 · running total $1,453,013Modification P00007 · 2015-08-12 · this action $27,152 · running total $1,480,165Modification P00008 · 2015-08-18 · this action $81,127 · running total $1,561,292Modification P00009 · 2015-08-26 · this action $31,696 · running total $1,592,988Modification P00010 · 2015-08-31 · this action $25,198 · running total $1,618,186Modification P00011 · 2015-09-25 · this action $10,251 · running total $1,628,437Modification P00012 · 2015-09-30 · this action $137,676 · running total $1,766,113
  • Base2015-04-02+$1,240,003= $1,240,003
  • Mod P000012015-05-22+$21,500= $1,261,503
  • Mod P000022015-06-10+$27,425= $1,288,928
  • Mod P000032015-07-01+$98,100= $1,387,028
  • Mod P000042015-07-07-$4,383= $1,382,645
  • Mod P000052015-07-29+$70,368= $1,453,013
  • Mod P000062015-08-12+$0= $1,453,013
  • Mod P000072015-08-12+$27,152= $1,480,165
  • Mod P000082015-08-18+$81,127= $1,561,292
  • Mod P000092015-08-26+$31,696= $1,592,988
  • Mod P000102015-08-31+$25,198= $1,618,186
  • Mod P000112015-09-25+$10,251= $1,628,437
  • Mod P000122015-09-30+$137,676= $1,766,113
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2015-04-02+$1,240,003$1,240,003IGF::OT::IGF - DESIGN BUILD SITE PREP CONSTRUCT PARKING LOT AT ST AUGUSTINE INTERIM CBOC, ST AUGUSTINE FL
Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-05-22+$21,500$1,261,503IGF::OT::IGF - DESIGN BUILD SITE PREP CONSTRUCT PARKING LOT AT ST AUGUSTINE INTERIM CBOC, ST AUGUSTINE FL
Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-06-10+$27,425$1,288,928IGF::OT::IGF - DESIGN BUILD SITE PREP CONSTRUCT PARKING LOT AT ST AUGUSTINE INTERIM CBOC, ST AUGUSTINE FL
Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-07-01+$98,100$1,387,028IGF::OT::IGF - ADD CLEAN FILL FOR PROPER ELEVATION - DESIGN BUILD SITE PREP CONSTRUCT PARKING LOT AT ST AUGUST…
Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-07-07−$4,383$1,382,645IGF::OT::IGF - CREDIT - DESIGN BUILD SITE PREP CONSTRUCT PARKING LOT AT ST AUGUSTINE INTERIM CBOC, ST AUGUSTIN…
Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-07-29+$70,368$1,453,013IGF::OT::IGF - DIFFERING SITE CONDITIONS - DESIGN BUILD SITE PREP CONSTRUCT PARKING LOT AT ST AUGUSTINE INTERI…
Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-08-12+$0$1,453,013IGF::OT::IGF - TIME EXTENSION - DESIGN BUILD SITE PREP CONSTRUCT PARKING LOT AT ST AUGUSTINE INTERIM CBOC, ST…
Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-08-12+$27,152$1,480,165IGF::OT::IGF - DIFFERING SITE CONDITIONS - DESIGN BUILD SITE PREP CONSTRUCT PARKING LOT AT ST AUGUSTINE INTERI…
Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-08-18+$81,127$1,561,292IGF::OT::IGF - DIFFERING SITE CONDITIONS - DESIGN BUILD SITE PREP CONSTRUCT PARKING LOT AT ST AUGUSTINE INTERI…
Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-08-26+$31,696$1,592,988IGF::OT::IGF - DIFFERING SITE CONDITIONS - DESIGN BUILD SITE PREP CONSTRUCT PARKING LOT AT ST AUGUSTINE INTERI…
Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-08-31+$25,198$1,618,186IGF::OT::IGF - DIFFERING SITE CONDITIONS - DESIGN BUILD SITE PREP CONSTRUCT PARKING LOT AT ST AUGUSTINE INTERI…
Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-09-25+$10,251$1,628,437IGF::OT::IGF - TIME EXTENSION - DELAY COSTS AND ST. AUGUSTINE MANDATED FEES - DESIGN BUILD SITE PREP CONSTRUCT…
Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-09-30+$137,676$1,766,113IGF::OT::IGF - ST. AUGUSTINE MANDATED SITE CHANGES - DESIGN BUILD SITE PREP CONSTRUCT PARKING LOT AT ST AUGUST…

Related awards · 8

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI KF62ABNCA498)

AwardOffice · PSC / listingNet obligationsFY
36C24818C0177248-NETWORK CONTRACT OFFICE 8 (36C248) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$157,194FY2018
36C24818C0139248-NETWORK CONTRACT OFFICE 8 (36C248) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS$2,258,439FY2018
36C10E18P0441VBA FIELD CONTRACTING (36C10E) · Z2AA · REPAIR OR ALTERATION OF OFFICE BUILDINGS$85,126FY2018
VA24817C0108248-NETWORK CONTRACT OFFICE 8 (36C248) · Z1AZ · MAINTENANCE OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS$1,315,245FY2017
VA101V17P0274VBA FIELD CONTRACTING (36C10E) · Z2FA · REPAIR OR ALTERATION OF FAMILY HOUSING FACILITIES$39,710FY2017
VA24816P5277248-NETWORK CONTRACT OFFICE 8 (36C248) · N099 · INSTALLATION OF EQUIPMENT- MISCELLANEOUS$72,173FY2016

Other recipients under Y1LZ from 248-NETWORK CONTRACT OFFICE 8 (most recent first)

AwardRecipientOfficeNet obligationsFY
VA24813C0206CONTRACT AND PURCHASING SOLUTIONS, INC.248-NETWORK CONTRACT OFFICE 8$601,103FY2013
VA24813P0870ARC DEVELOPMENT INC248-NETWORK CONTRACT OFFICE 8$2,200FY2013

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA24815C0097_3600_-NONE-_-NONE- · retrieved 2026-09-26.