Description
IGF::OT::IGF PROJECT 573A4-14-801, REPLACE PIPING IN CLC-2 MODIFICATION P00002
Base award description: IGF::OT::IGF PROJECT 573A4-14-801, REPLACE PIPING IN CLC-2
Modification chain · 3 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2014-09-11+$406,315= $406,315
- Mod P000012014-12-22+$3,550= $409,865
- Mod P000022015-04-09-$14,908= $394,956
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2014-09-11 | +$406,315 | $406,315 | IGF::OT::IGF PROJECT 573A4-14-801, REPLACE PIPING IN CLC-2 |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-12-22 | +$3,550 | $409,865 | IGF::OT::IGF PROJECT 573A4-14-801, REPLACE PIPING IN CLC-2 MODIFICATION P00001 |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-04-09 | −$14,908 | $394,956 | IGF::OT::IGF PROJECT 573A4-14-801, REPLACE PIPING IN CLC-2 MODIFICATION P00002 |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI L4FUJ4JYDAJ8)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24824N0183 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · F115 · ENVIRONMENTAL SYSTEMS PROTECTION- ENVIRONMENTAL CONSULTING AND LEGAL SUPPORT | $151,370 | FY2024 |
| 36C24823P1483 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · F107 · ENVIRONMENTAL SYSTEMS PROTECTION- TOXIC AND HAZARDOUS SUBSTANCE ANALYSIS | $56,160 | FY2023 |
| 36C24823N0507 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · F115 · ENVIRONMENTAL SYSTEMS PROTECTION- ENVIRONMENTAL CONSULTING AND LEGAL SUPPORT | $103,770 | FY2023 |
| 36C24822N0355 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · F108 · ENVIRONMENTAL SYSTEMS PROTECTION- ENVIRONMENTAL REMEDIATION | $115,000 | FY2022 |
| 36C24722P0324 | 247-NETWORK CONTRACT OFFICE 7 (36C247) · N045 · INSTALLATION OF EQUIPMENT- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT | $0 | FY2022 |
| 36C24822N0183 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · F115 · ENVIRONMENTAL SYSTEMS PROTECTION- ENVIRONMENTAL CONSULTING AND LEGAL SUPPORT | $54,345 | FY2022 |
Other recipients under Y1DA from 248-NETWORK CONTRACT OFFICE 8 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA24816J0922 | POINTER CONSTRUCTION GROUP LLC | 248-NETWORK CONTRACT OFFICE 8 | $23,509 | FY2016 |
| VA24816J1777 | POINTER CONSTRUCTION GROUP LLC | 248-NETWORK CONTRACT OFFICE 8 | $37,504 | FY2016 |
| VA24816J0661 | POINTER CONSTRUCTION GROUP LLC | 248-NETWORK CONTRACT OFFICE 8 | $13,339 | FY2016 |
| VA24816J0550 | SDPM JFM CONSTRUCCIONES JOINT VENTURE | 248-NETWORK CONTRACT OFFICE 8 | $310,725 | FY2016 |
| VA24816J0381 | POINTER CONSTRUCTION GROUP LLC | 248-NETWORK CONTRACT OFFICE 8 | $9,651 | FY2016 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA24814C0195_3600_-NONE-_-NONE- · retrieved 2026-09-26.