Description
CONSTRUCT RESEARCH CENTER - BAY PINES - SUPPLEMENTAL AGREEMENT TO INCORPORATE CHANGES WITHIN SCOPE
Base award description: CONSTRUCT RESEARCH CENTER - BAY PINES; IGF::OT::IGF
Modification chain · 16 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2014-02-26+$8,196,000= $8,196,000
- Mod P000012015-01-21+$8,757= $8,204,757
- Mod P000022015-04-07+$4,200= $8,208,957
- Mod P000032015-06-10+$3,227= $8,212,184
- Mod P000042015-09-30-$3,650= $8,208,533
- Mod P000052015-11-23+$15,450= $8,223,983
- Mod P000062015-12-03+$0= $8,223,983
- Mod P000072016-01-20+$0= $8,223,983
- Mod P000082016-03-09+$12,251= $8,236,234
- Mod P000092016-09-30+$29,089= $8,265,322
- Mod P000102017-04-28+$20,240= $8,285,563
- Mod P000112017-12-08+$46,002= $8,331,565
- Mod P000122018-10-26+$55,795= $8,387,360
- Mod P000132018-12-10+$29,642= $8,417,002
- Mod P000142019-03-28+$41,792= $8,458,793
- Mod P000152020-03-30-$11,000= $8,447,793
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2014-02-26 | +$8,196,000 | $8,196,000 | CONSTRUCT RESEARCH CENTER - BAY PINES; IGF::OT::IGF |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-01-21 | +$8,757 | $8,204,757 | CONSTRUCT RESEARCH CENTER - BAY PINES; IGF::OT::IGF |
| Mod P00002· CHANGE ORDER | 2015-04-07 | +$4,200 | $8,208,957 | CONSTRUCT RESEARCH CENTER - BAY PINES; IGF::OT::IGF - CHANGE ORDER TO PREVENT DELAY TO "ADD TOP MAT REINFORCEM… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-06-10 | +$3,227 | $8,212,184 | CONSTRUCT RESEARCH CENTER - BAY PINES; IGF::OT::IGF - SUPP AGREE TO DEFINITIZE CHANGE ORDER TO PREVENT DELAY T… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-30 | −$3,650 | $8,208,533 | CONSTRUCT RESEARCH CENTER - BAY PINES; IGF::OT::IGF - SUPP AGREE TO INCORPORATE CHANGES TO ALLOW FOR DIRECT EX… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-11-23 | +$15,450 | $8,223,983 | CONSTRUCT RESEARCH CENTER - BAY PINES; IGF::OT::IGF - SUPP AGREE TO INCORPORATE CHANGES WITHIN SCOPE |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-12-03 | +$0 | $8,223,983 | CONSTRUCT RESEARCH CENTER - BAY PINES; IGF::OT::IGF - SUPP AGREE TO INCORPORATE CHANGES WITHIN SCOPE |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-01-20 | +$0 | $8,223,983 | CONSTRUCT RESEARCH CENTER - BAY PINES; IGF::OT::IGF - SUPP AGREE TO INCORPORATE CHANGES WITHIN SCOPE |
| Mod P00008· CHANGE ORDER | 2016-03-09 | +$12,251 | $8,236,234 | CONSTRUCT RESEARCH CENTER - BAY PINES; IGF::OT::IGF - CHANGE ORDER TO INCORPORATE CHANGES WITHIN SCOPE |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-09-30 | +$29,089 | $8,265,322 | CONSTRUCT RESEARCH CENTER - BAY PINES; IGF::OT::IGF - SUPPLEMENTAL AGREEMENT TO INCORPORATE CHANGES WITHIN SC… |
| Mod P00010· CHANGE ORDER | 2017-04-28 | +$20,240 | $8,285,563 | CONSTRUCT RESEARCH CENTER - BAY PINES; IGF::OT::IGF - CHANGE ORDER TO INCORPORATE CHANGES WITHIN SCOPE |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-12-08 | +$46,002 | $8,331,565 | CONSTRUCT RESEARCH CENTER - BAY PINES; IGF::OT::IGF - SUPPLEMENTAL AGREEMENT TO INCORPORATE CHANGES WITHIN SC… |
| Mod P00012· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES) | 2018-10-26 | +$55,795 | $8,387,360 | CONSTRUCT RESEARCH CENTER - BAY PINES; IGF::OT::IGF - SUPPLEMENTAL AGREEMENT TO INCORPORATE CHANGES WITHIN SC… |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-12-10 | +$29,642 | $8,417,002 | CONSTRUCT RESEARCH CENTER - BAY PINES; IGF::OT::IGF - SUPPLEMENTAL AGREEMENT TO INCORPORATE CHANGES WITHIN SC… |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-03-28 | +$41,792 | $8,458,793 | CONSTRUCT RESEARCH CENTER - BAY PINES; IGF::OT::IGF - SUPPLEMENTAL AGREEMENT TO INCORPORATE CHANGES WITHIN SC… |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-03-30 | −$11,000 | $8,447,793 | CONSTRUCT RESEARCH CENTER - BAY PINES - SUPPLEMENTAL AGREEMENT TO INCORPORATE CHANGES WITHIN SCOPE |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI GKUMJS8XRVP5)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24225P1478 | 242-NETWORK CONTRACT OFFICE 02 (36C242) · J036 · MAINT/REPAIR/REBUILD OF EQUIPMENT- SPECIAL INDUSTRY MACHINERY | $244,837 | FY2025 |
| 36C24818N4749 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $1,000 | FY2018 |
| 36C24818D0110 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $0 | FY2018 |
| 36C24818C0024 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $334,198 | FY2018 |
| VA24817C0225 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $232,796 | FY2017 |
| VA24817P3530 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · 4410 · INDUSTRIAL BOILERS | $50,000 | FY2017 |
Other recipients under Y1DZ from 248-NETWORK CONTRACT OFFICE 8 (36C248) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C24826C0044 | CAVU CONSULTING LLC | 248-NETWORK CONTRACT OFFICE 8 (36C248) | $3,195,423 | FY2026 |
| 36C24826C0051 | MIDWESTERN CONSTRUCTION SERVICES, INC. | 248-NETWORK CONTRACT OFFICE 8 (36C248) | $258,795 | FY2026 |
| 36C24826C0009 | MIDWESTERN CONSTRUCTION SERVICES, INC. | 248-NETWORK CONTRACT OFFICE 8 (36C248) | $1,028,339 | FY2026 |
| 36C24825C0035 | YERKES SOUTH INC. | 248-NETWORK CONTRACT OFFICE 8 (36C248) | $5,135,880 | FY2025 |
| 36C24825N0851 | MIDWESTERN CONSTRUCTION SERVICES, INC. | 248-NETWORK CONTRACT OFFICE 8 (36C248) | $194,964 | FY2025 |