Award recordCONTRACT

HARRELL DESIGN GROUP PC

PIID VA24812C0197· VHA· 248-NETWORK CONTRACT OFFICE 8 (36C248)· C1NB · ARCHITECT AND ENGINEERING- CONSTRUCTION: HEATING AND COOLING PLANTS· FY2012· $347,475 net obligations· UEI FDMWG5FJLRQ3· NC

Description

IGF::OT::IGF - DECREASE 6 OF SITE VISITS - A-E REPLACE BOILER LAKE CITY

Base award description: A-E REPLACE BOILER LAKE CITY

First action · last action
2012-05-08 · 2018-02-22
Transactions
4
First transaction's obligation
$306,516
Base + all options value (sum of deltas)
$347,475
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
1
SDVOSB flag on record
Yes (self-representation)
NAICS
541330 · ENGINEERING SERVICES

Modification chain · 4 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$354,025$0Base award · 2012-05-08 · this action $306,516 · running total $306,516Modification P00001 · 2012-09-26 · this action $47,509 · running total $354,025Modification P00002 · 2016-04-04 · this action $0 · running total $354,025Modification P00003 · 2018-02-22 · this action -$6,550 · running total $347,475
  • Base2012-05-08+$306,516= $306,516
  • Mod P000012012-09-26+$47,509= $354,025
  • Mod P000022016-04-04+$0= $354,025
  • Mod P000032018-02-22-$6,550= $347,475
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2012-05-08+$306,516$306,516A-E REPLACE BOILER LAKE CITY
Mod P00001· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2012-09-26+$47,509$354,025A-E REPLACE BOILER LAKE CITY
Mod P00002· OTHER ADMINISTRATIVE ACTION2016-04-04+$0$354,025IGF::OT::IGF - TIME - A-E REPLACE BOILER LAKE CITY
Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-02-22−$6,550$347,475IGF::OT::IGF - DECREASE 6 OF SITE VISITS - A-E REPLACE BOILER LAKE CITY

Related awards · 8

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI FDMWG5FJLRQ3)

AwardOffice · PSC / listingNet obligationsFY
36C24626C0015246-NETWORK CONTRACTING OFFICE 6 (36C246) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES$68,914FY2026
36C24126C0004241-NETWORK CONTRACT OFFICE 01 (36C241) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES$941,157FY2026
36C24525C0130245-NETWORK CONTRACT OFFICE 5 (36C245) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES$3,161,639FY2025
36C25025C0148250-NETWORK CONTRACT OFFICE 10 (36C250) · C1NB · ARCHITECT AND ENGINEERING- CONSTRUCTION: HEATING AND COOLING PLANTS$840,487FY2025
36C24725C0054247-NETWORK CONTRACT OFFICE 7 (36C247) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES$355,167FY2025
36C24625C0024246-NETWORK CONTRACTING OFFICE 6 (36C246) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES$593,224FY2025

Other recipients under C1NB from 248-NETWORK CONTRACT OFFICE 8 (36C248) (most recent first)

AwardRecipientOfficeNet obligationsFY
VA24817C0134ABOVE GROUP INC.248-NETWORK CONTRACT OFFICE 8 (36C248)$105,390FY2017
VA24816C0144MES GROUP INC248-NETWORK CONTRACT OFFICE 8 (36C248)$372,496FY2016