Award recordCONTRACT

ALBRITTON COMPANY, INC., THE

PIID VA247P0981· VHA· 247-NETWORK CONTRACT OFFICE 7· S299 · HOUSEKEEPING- OTHER· FY2009· $833,191 net obligations· UEI VYA7HQCY27C1· NC

Description

FOR RESTORATION AND MAINTENANCE OF TILE AND GROUT USING SANIGLAZE SYSTEM.

Base award description: RESTORATION AND MAINTENANCE OF TILE AND GROUT USING SANIGLAZE SYSTEM

First action · last action
2009-06-23 · 2014-06-16
Transactions
11
First transaction's obligation
$297,551
Base + all options value (sum of deltas)
$858,698
Extent competed
NOT COMPETED
Other than full & open authority
ONLY ONE SOURCE - OTHER
Set-aside
NO SET ASIDE USED.
Offers received
1
SDVOSB flag on record
No
NAICS
444190 · OTHER BUILDING MATERIAL DEALERS

Modification chain · 11 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$839,019$0Base award · 2009-06-23 · this action $297,551 · running total $297,551Modification 1 · 2009-09-09 · this action $186,007 · running total $483,558Modification 2 · 2010-06-08 · this action $95,067 · running total $578,625Modification 3 · 2010-09-22 · this action -$26,124 · running total $552,501Modification 4 · 2011-06-22 · this action $98,150 · running total $650,651Modification P0005 · 2012-06-14 · this action $101,234 · running total $751,885Modification P00006 · 2012-10-30 · this action -$17,183 · running total $734,702Modification P00007 · 2013-07-13 · this action $98,150 · running total $832,852Modification P00008 · 2013-07-29 · this action $6,167 · running total $839,019Modification P00009 · 2013-08-06 · this action -$5,828 · running total $833,191Modification P00010 · 2014-06-16 · this action $0 · running total $833,191
  • Base2009-06-23+$297,551= $297,551
  • Mod 12009-09-09+$186,007= $483,558
  • Mod 22010-06-08+$95,067= $578,625
  • Mod 32010-09-22-$26,124= $552,501
  • Mod 42011-06-22+$98,150= $650,651
  • Mod P00052012-06-14+$101,234= $751,885
  • Mod P000062012-10-30-$17,183= $734,702
  • Mod P000072013-07-13+$98,150= $832,852
  • Mod P000082013-07-29+$6,167= $839,019
  • Mod P000092013-08-06-$5,828= $833,191
  • Mod P000102014-06-16+$0= $833,191
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2009-06-23+$297,551$297,551RESTORATION AND MAINTENANCE OF TILE AND GROUT USING SANIGLAZE SYSTEM
Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-09-09+$186,007$483,558ADD 19,767 SQ FT RESTORATION AND MAINTENANCE OF TILE AND GROUT USING SANIGLAZE SYSTEM ADD 19,767 SQ FT.
Mod 2· EXERCISE AN OPTION2010-06-08+$95,067$578,625EXERCISE OPTION YEAR ONE PERIOD OF PERFORMANCE 1 JULY 2010 THROUGH 30 JUNE 2011.FOR RESTORATION AND MAINTENANC…
Mod 3· FUNDING ONLY ACTION2010-09-22−$26,124$552,501EXERCISE OPTION YEAR ONE PERIOD OF PERFORMANCE 1 JULY 2010 THROUGH 30 JUNE 2011.FOR RESTORATION AND MAINTENANC…
Mod 4· EXERCISE AN OPTION2011-06-22+$98,150$650,651EXERCISE OPTION YEAR TWO PERIOD OF PERFORMANCE 1 JULY 2011 THROUGH 30 JUNE 2012.FOR RESTORATION AND MAINTENANC…
Mod P0005· EXERCISE AN OPTION2012-06-14+$101,234$751,885EXERCISE OPTION YEAR TWO PERIOD OF PERFORMANCE 1 JULY 2011 THROUGH 30 JUNE 2012.FOR RESTORATION AND MAINTENANC…
Mod P00006· EXERCISE AN OPTION2012-10-30−$17,183$734,702EXERCISE OPTION YEAR TWO PERIOD OF PERFORMANCE 1 JULY 2011 THROUGH 30 JUNE 2012.FOR RESTORATION AND MAINTENANC…
Mod P00007· EXERCISE AN OPTION2013-07-13+$98,150$832,852EXERCISE OPTION YEAR TWO PERIOD OF PERFORMANCE 1 JULY 2011 THROUGH 30 JUNE 2012.FOR RESTORATION AND MAINTENANC…
Mod P00008· EXERCISE AN OPTION2013-07-29+$6,167$839,019EXERCISE OPTION YEAR FOUR PERIOD OF PERFORMANCE 1 JULY 2013 THROUGH 30 JUNE 2014.FOR RESTORATION AND MAINTENAN…
Mod P00009· EXERCISE AN OPTION2013-08-06−$5,828$833,191EXERCISE OPTION YEAR FOUR PERIOD OF PERFORMANCE 1 JULY 2013 THROUGH 30 JUNE 2014.FOR RESTORATION AND MAINTENAN…
Mod P00010· EXERCISE AN OPTION2014-06-16+$0$833,191FOR RESTORATION AND MAINTENANCE OF TILE AND GROUT USING SANIGLAZE SYSTEM.

Related awards · 11

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI VYA7HQCY27C1)

AwardOffice · PSC / listingNet obligationsFY
VA24712P0417534-CHARLESTON · 6515 · MEDICAL AND SURGICAL INSTRUMENTS, EQUIPMENT, AND SUPPLIES$4,657FY2012
VA246P0380558-DURHAM · R499 · OTHER PROFESSIONAL SERVICES$58,584FY2009
V534C85516534S-CHARLESTON SMALL PURCHASE · R499 · OTHER PROFESSIONAL SERVICES$16,821FY2008
V558C80763558S-DURHAM SMALL PURCHASE · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY$17,750FY2008
V534C85378534S-CHARLESTON SMALL PURCHASE · R499 · OTHER PROFESSIONAL SERVICES$5,435FY2008
V534N82425534S-CHARLESTON SMALL PURCHASE · 7910 · FLOOR POLISHERS & VACUUM CLEANERS$200FY2008

Other recipients under S299 from 247-NETWORK CONTRACT OFFICE 7 (most recent first)

AwardRecipientOfficeNet obligationsFY
VA24714P2242NEIE MEDICAL WASTE SERVICES, LLC247-NETWORK CONTRACT OFFICE 7$21,600FY2014
VA24714F2656WEST SANITATION SERVICES INC247-NETWORK CONTRACT OFFICE 7$10,625FY2014
VA24712P5033ROCKTENN CP, LLC247-NETWORK CONTRACT OFFICE 7$2,751FY2013
VA24712F2916WEST SANITATION SERVICES INC247-NETWORK CONTRACT OFFICE 7$12,838FY2013
VA24713P0021AUGUSTA JAYCEES-VETERANS ADMINISTRATION PRE-EMPLOYMENT CLINIC, INC.247-NETWORK CONTRACT OFFICE 7$13,120FY2013

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA247P0981_3600_-NONE-_-NONE- · retrieved 2026-09-26.