Description
OGF::OT::OGF REMOVE DALT AFTER MAY 21, 2013 AND BACKER BOARD/CERAMIC TILE WORK.
Base award description: HVAC REPLACEMENT BUILDING 146
Modification chain · 6 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2011-04-21+$2,520,480= $2,520,480
- Mod P000012012-05-11+$2,064= $2,522,544
- Mod P000022012-10-09+$0= $2,522,544
- Mod P000032012-12-05+$29,165= $2,551,709
- Mod P000042013-02-08+$0= $2,551,709
- Mod P000052013-07-03-$5,104= $2,546,605
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2011-04-21 | +$2,520,480 | $2,520,480 | HVAC REPLACEMENT BUILDING 146 |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-05-11 | +$2,064 | $2,522,544 | HVAC REPLACEMENT BUILDING 146 ADD BUCKET ASSEMBLIES AND ADD/REMOVE CONTRACT LINE ITEMS. |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-09 | +$0 | $2,522,544 | HVAC REPLACEMENT BUILDING 146 ADD BUCKET ASSEMBLIES AND ADD/REMOVE CONTRACT LINE ITEMS. |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-12-05 | +$29,165 | $2,551,709 | VARIOUS RFI ISSUES |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-02-08 | +$0 | $2,551,709 | OGF::OT::OGF NO COST EXTENSION TO ASSESS NEW PROGRESS SCHEDULE. |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-07-03 | −$5,104 | $2,546,605 | OGF::OT::OGF REMOVE DALT AFTER MAY 21, 2013 AND BACKER BOARD/CERAMIC TILE WORK. |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI R5LTEKESKV11)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA24514P0985 | 512-BALTIMORE · J042 · MAINT/REPAIR/REBUILD OF EQUIP- FIRE FIGHTING/RESCUE/SAFETY EQUIP; ENVIRON PROTECT EQUIP/MATLS | $2,570 | FY2014 |
| VA24612C0122 | 246-NETWORK CONTRACTING OFFICE 6 · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $122,788 | FY2012 |
| VA786A12C0048 | NATIONAL CEMETERY ADMINISTRATION · Y1JZ · CONSTRUCTION OF MISCELLANEOUS BUILDINGS | $78,263 | FY2012 |
| VA24512P1689 | 512-BALTIMORE · J042 · MAINT/REPAIR/REBUILD OF EQUIP- FIRE FIGHTING/RESCUE/SAFETY EQUIP; ENVIRON PROTECT EQUIP/MATLS | $5,212 | FY2012 |
| VA24612C0049 | 246-NETWORK CONTRACTING OFFICE 6 · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $888,164 | FY2012 |
| VA245P0702 | 512-BALTIMORE · H163 · QUALITY CONTROL- ALARM, SIGNAL, AND SECURITY DETECTION SYSTEMS | $401,480 | FY2011 |
Other recipients under Z141 from 246-NETWORK CONTRACTING OFFICE 6 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA246C0736 | VET BUILT, INC. | 246-NETWORK CONTRACTING OFFICE 6 | $1,096,119 | FY2011 |
| VA246C0792 | VET BUILT, INC. | 246-NETWORK CONTRACTING OFFICE 6 | $1,034,558 | FY2011 |
| VA246C0793 | GULF TECH CONSTRUCTION LLC | 246-NETWORK CONTRACTING OFFICE 6 | $24,951 | FY2011 |
| VA246C0779 | ATKINSON INCORPORATED | 246-NETWORK CONTRACTING OFFICE 6 | $67,750 | FY2011 |
| VA565C10386 | JOHNSON CONTROLS FIRE PROTECTION LP | 246-NETWORK CONTRACTING OFFICE 6 | $4,380 | FY2011 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA246C0709_3600_-NONE-_-NONE- · retrieved 2026-09-26.