Award recordCONTRACT

FIREWATCH CONTRACTING OF FLORIDA LLC

PIID VA246C0606· VHA· 246-NETWORK CONTRACTING OFFICE 6· Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY· FY2010· $7,644,439 net obligations· UEI SHFYKKBP26E1· FL

Description

SALISBURY MENTAL HEALTH PHASE I.

Base award description: SALISBURY MENTAL HEALTH PHASE I

First action · last action
2010-09-29 · 2014-10-02
Transactions
11
First transaction's obligation
$6,900,000
Base + all options value (sum of deltas)
$7,644,439
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
9
SDVOSB flag on record
Yes (self-representation)
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION

Modification chain · 11 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$7,645,439$0Base award · 2010-09-29 · this action $6,900,000 · running total $6,900,000Modification 1 · 2011-05-04 · this action $570,000 · running total $7,470,000Modification P00002 · 2012-05-21 · this action $78,656 · running total $7,548,656Modification P00003 · 2012-05-21 · this action $84,883 · running total $7,633,540Modification P00004 · 2012-12-20 · this action $0 · running total $7,633,540Modification P00005 · 2013-02-04 · this action -$2,542 · running total $7,630,997Modification P00006 · 2013-04-16 · this action -$91,990 · running total $7,539,007Modification P00007 · 2013-07-25 · this action $52,553 · running total $7,591,561Modification P00008 · 2013-09-23 · this action $50,878 · running total $7,642,439Modification P00009 · 2013-10-21 · this action $3,000 · running total $7,645,439Modification P00010 · 2014-10-02 · this action -$1,000 · running total $7,644,439
  • Base2010-09-29+$6,900,000= $6,900,000
  • Mod 12011-05-04+$570,000= $7,470,000
  • Mod P000022012-05-21+$78,656= $7,548,656
  • Mod P000032012-05-21+$84,883= $7,633,540
  • Mod P000042012-12-20+$0= $7,633,540
  • Mod P000052013-02-04-$2,542= $7,630,997
  • Mod P000062013-04-16-$91,990= $7,539,007
  • Mod P000072013-07-25+$52,553= $7,591,561
  • Mod P000082013-09-23+$50,878= $7,642,439
  • Mod P000092013-10-21+$3,000= $7,645,439
  • Mod P000102014-10-02-$1,000= $7,644,439
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2010-09-29+$6,900,000$6,900,000SALISBURY MENTAL HEALTH PHASE I
Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-04+$570,000$7,470,000SALISBURY MENTAL HEALTH PHASE I
Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-05-21+$78,656$7,548,656SALISBURY MENTAL HEALTH PHASE I - S/A #1 - ADDITIONAL FUNDING FOR THE INCREASED PRICE OF MATERIALS.
Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-05-21+$84,883$7,633,540SALISBURY MENTAL HEALTH PHASE I - S/A #2 - ADD 2 HOLED ELEVATORS
Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-12-20+$0$7,633,540SALISBURY MENTAL HEALTH PHASE I - S/A #2 - ADD 2 HOLED ELEVATORS
Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-02-04−$2,542$7,630,997SALISBURY MENTAL HEALTH PHASE I - S/A #2 - ADD 2 HOLED ELEVATORS
Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-04-16−$91,990$7,539,007SALISBURY MENTAL HEALTH PHASE I - S/A #6 - ACCOUNT FOR DEDUCT OF ROOF AND DIFFERING SITE CONDITIONS.
Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-07-25+$52,553$7,591,561SALISBURY MENTAL HEALTH PHASE I.
Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-09-23+$50,878$7,642,439SALISBURY MENTAL HEALTH PHASE I.
Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-10-21+$3,000$7,645,439SALISBURY MENTAL HEALTH PHASE I.
Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-10-02−$1,000$7,644,439SALISBURY MENTAL HEALTH PHASE I.

Related awards · 11

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI SHFYKKBP26E1)

AwardOffice · PSC / listingNet obligationsFY
36C24926C0005249-NETWORK CONTRACT OFFICE 9 (36C249) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES$6,109,411FY2026
36C24925C0024249-NETWORK CONTRACT OFFICE 9 (36C249) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$21,517FY2025
36C24924C0017249-NETWORK CONTRACT OFFICE 9 (36C249) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$5,208,823FY2024
36C77623C0071PCAC (36C776) · DC01 · IT AND TELECOM - DATA CENTER SUPPORT SERVICES (LABOR)$28,624FY2023
36C24223C0028242-NETWORK CONTRACT OFFICE 02 (36C242) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES$6,845,403FY2023
36C24622C0076246-NETWORK CONTRACTING OFFICE 6 (36C246) · J045 · MAINT/REPAIR/REBUILD OF EQUIPMENT- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT$1,442,929FY2022

Other recipients under Z141 from 246-NETWORK CONTRACTING OFFICE 6 (most recent first)

AwardRecipientOfficeNet obligationsFY
VA246C0736VET BUILT, INC.246-NETWORK CONTRACTING OFFICE 6$1,096,119FY2011
VA246C0792VET BUILT, INC.246-NETWORK CONTRACTING OFFICE 6$1,034,558FY2011
VA246C0793GULF TECH CONSTRUCTION LLC246-NETWORK CONTRACTING OFFICE 6$24,951FY2011
VA246C0779ATKINSON INCORPORATED246-NETWORK CONTRACTING OFFICE 6$67,750FY2011
VA565C10386JOHNSON CONTROLS FIRE PROTECTION LP246-NETWORK CONTRACTING OFFICE 6$4,380FY2011

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA246C0606_3600_-NONE-_-NONE- · retrieved 2026-09-26.