Award recordCONTRACT

AMERICAN VETERAN CONSTRUCTION CO.

PIID VA246C0318· VHA· 246-NETWORK CONTRACTING OFFICE 6· Z149 · MAINT-REP-ALT/OTHER HOSPITAL BLDGS· FY2009· $5,792,107 net obligations· UEI LP57TPK2N641· VA

Description

MOD #11 SURGICAL DELAYS OF PROJECT AND OTHER WORK

Base award description: REPLACE/UPGRADE HVAC IN MULTIPLE BUILDINGS

First action · last action
2009-06-24 · 2011-03-23
Transactions
12
First transaction's obligation
$4,799,000
Base + all options value (sum of deltas)
$5,792,107
Extent competed
NOT AVAILABLE FOR COMPETITION
Other than full & open authority
AUTHORIZED BY STATUTE
Set-aside
SDVOSB SOLE SOURCE
Offers received
1
SDVOSB flag on record
Yes (self-representation)
NAICS
238220 · PLUMBING, HEATING, AND AIR-CONDITIONING CONTRACTORS

Modification chain · 12 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$5,792,107$0Base award · 2009-06-24 · this action $4,799,000 · running total $4,799,000Modification 1 · 2009-10-23 · this action -$94,756 · running total $4,704,244Modification 2 · 2010-02-11 · this action $20,000 · running total $4,724,244Modification 3 · 2010-02-25 · this action -$4,538 · running total $4,719,706Modification 4 · 2010-03-01 · this action $55,295 · running total $4,775,001Modification 5 · 2010-04-09 · this action -$44,323 · running total $4,730,678Modification 6 · 2010-04-19 · this action $641,108 · running total $5,371,786Modification 7 · 2010-05-07 · this action $63,507 · running total $5,435,293Modification 8 · 2010-06-22 · this action $64,309 · running total $5,499,602Modification 9 · 2010-08-20 · this action $258,016 · running total $5,757,618Modification 10 · 2011-01-06 · this action $12,838 · running total $5,770,456Modification 11 · 2011-03-23 · this action $21,651 · running total $5,792,107
  • Base2009-06-24+$4,799,000= $4,799,000
  • Mod 12009-10-23-$94,756= $4,704,244
  • Mod 22010-02-11+$20,000= $4,724,244
  • Mod 32010-02-25-$4,538= $4,719,706
  • Mod 42010-03-01+$55,295= $4,775,001
  • Mod 52010-04-09-$44,323= $4,730,678
  • Mod 62010-04-19+$641,108= $5,371,786
  • Mod 72010-05-07+$63,507= $5,435,293
  • Mod 82010-06-22+$64,309= $5,499,602
  • Mod 92010-08-20+$258,016= $5,757,618
  • Mod 102011-01-06+$12,838= $5,770,456
  • Mod 112011-03-23+$21,651= $5,792,107
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2009-06-24+$4,799,000$4,799,000REPLACE/UPGRADE HVAC IN MULTIPLE BUILDINGS
Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-10-23−$94,756$4,704,244REPLACE/UPGRADE HVAC IN MULTIPLE BUILDINGS
Mod 2· CHANGE ORDER2010-02-11+$20,000$4,724,244CHANGE ORDER FOR EMERGENCY WORK ON HVAC IN PHONE SWITCHING AREA
Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-02-25−$4,538$4,719,706MODIFICATION FOR SUPPLEMENTAL AGREEMENT OF CHANGE ORDER #2 FOR THE HVAC PHONE ROOM SYSTEM WIRING
Mod 4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-03-01+$55,295$4,775,001CORRECT MED GAS DEFICIENCIES
Mod 5· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-04-09−$44,323$4,730,678ADD CHILLER 110B AND DELETE WORK IN BLDG 146
Mod 6· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-04-19+$641,108$5,371,786ROOF REPLACEMENT
Mod 7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-07+$63,507$5,435,293OPERATING ROOM LIGHT
Mod 8· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-06-22+$64,309$5,499,602MOD 8 FOR DESIGN DEFICIENCIES AND COTR REQUESTED CHANGES
Mod 9· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-08-20+$258,016$5,757,618MOD #9 INCORPORATES 6 MODS TO CONTRACT PER SOW
Mod 10· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-01-06+$12,838$5,770,456MOD #10 ELECTRICAL WORK
Mod 11· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-03-23+$21,651$5,792,107MOD #11 SURGICAL DELAYS OF PROJECT AND OTHER WORK

Related awards · 8

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI LP57TPK2N641)

AwardOffice · PSC / listingNet obligationsFY
VA590C10355246-NETWORK CONTRACTING OFFICE 6 · N041 · INSTALL OF REFRIGERATION - AC EQ$9,240FY2011
VA246C0333246-NETWORK CONTRACTING OFFICE 6 · Y149 · CONSTRUCT/OTHER HOSPITAL BLDGS$2,311,084FY2008
V59083P314590S-HAMPTON SMALL PURCHASE · J059 · MAINT-REP OF ELECT-ELCT EQ$1,800FY2008

Other recipients under Z149 from 246-NETWORK CONTRACTING OFFICE 6 (most recent first)

AwardRecipientOfficeNet obligationsFY
VA246C0002ADIRA CONSTRUCTION, INC.246-NETWORK CONTRACTING OFFICE 6-$574,992FY2013
VA246C0716LANIER CONTRACTING SERVICES, INC.246-NETWORK CONTRACTING OFFICE 6$532,384FY2011
VA246C0715KSA-KRANTZ SYSTEMS & ASSOCIATES, LLC246-NETWORK CONTRACTING OFFICE 6$695,006FY2011
VA590C10634M&S CONCEPTS, LLC246-NETWORK CONTRACTING OFFICE 6$517,630FY2011
VA590C10635M&S CONCEPTS, LLC246-NETWORK CONTRACTING OFFICE 6$266,788FY2011

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA246C0318_3600_-NONE-_-NONE- · retrieved 2026-09-26.