Award recordCONTRACT

CAIN CONTRACTING, INC.

PIID VA245C0528· VHA· 512-BALTIMORE· AD61 · R&D- DEFENSE OTHER: CONSTRUCTION (BASIC RESEARCH)· FY2010· $3,960,590 net obligations· UEI L2NTWJMGFM81· MD

Description

DEDUCT FOR LANDSCAPING AND REIMBURSMENT FOR FILL DIRT

Base award description: CONSTRUCT NEW COMMUNITY BASE OUT PATIENT FACILITY AT FT.MEADE, MD PROJECT #512-515

First action · last action
2010-09-22 · 2013-04-26
Transactions
13
First transaction's obligation
$3,672,327
Base + all options value (sum of deltas)
$3,960,590
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
8
SDVOSB flag on record
Yes (self-representation)
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION

Modification chain · 13 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$3,983,340$0Base award · 2010-09-22 · this action $3,672,327 · running total $3,672,327Modification SA1 · 2011-07-13 · this action $93,113 · running total $3,765,440Modification SA2 · 2011-08-18 · this action $19,008 · running total $3,784,448Modification SA3 · 2011-08-31 · this action $51,606 · running total $3,836,054Modification 4 · 2011-09-22 · this action $0 · running total $3,836,054Modification P00005 · 2012-02-01 · this action $32,343 · running total $3,868,397Modification P00006 · 2012-02-22 · this action $50,853 · running total $3,919,250Modification P00007 · 2012-03-19 · this action $2,284 · running total $3,921,534Modification P00008 · 2012-05-22 · this action $35,764 · running total $3,957,298Modification P00009 · 2012-05-24 · this action $4,722 · running total $3,962,020Modification P00010 · 2012-05-31 · this action $21,320 · running total $3,983,340Modification P00011 · 2012-06-18 · this action $0 · running total $3,983,340Modification P00012 · 2013-04-26 · this action -$22,750 · running total $3,960,590
  • Base2010-09-22+$3,672,327= $3,672,327
  • Mod SA12011-07-13+$93,113= $3,765,440
  • Mod SA22011-08-18+$19,008= $3,784,448
  • Mod SA32011-08-31+$51,606= $3,836,054
  • Mod 42011-09-22+$0= $3,836,054
  • Mod P000052012-02-01+$32,343= $3,868,397
  • Mod P000062012-02-22+$50,853= $3,919,250
  • Mod P000072012-03-19+$2,284= $3,921,534
  • Mod P000082012-05-22+$35,764= $3,957,298
  • Mod P000092012-05-24+$4,722= $3,962,020
  • Mod P000102012-05-31+$21,320= $3,983,340
  • Mod P000112012-06-18+$0= $3,983,340
  • Mod P000122013-04-26-$22,750= $3,960,590
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2010-09-22+$3,672,327$3,672,327CONSTRUCT NEW COMMUNITY BASE OUT PATIENT FACILITY AT FT.MEADE, MD PROJECT #512-515
Mod SA1· CHANGE ORDER2011-07-13+$93,113$3,765,440UNFORESEEN SITE CONDITIONS CHANGE ORDER
Mod SA2· CHANGE ORDER2011-08-18+$19,008$3,784,448UNFORESEEN SITE CONDITIONS CHANGE ORDER
Mod SA3· CHANGE ORDER2011-08-31+$51,606$3,836,054UNFORESEEN SITE CONDITIONS CHANGE ORDER
Mod 4· OTHER ADMINISTRATIVE ACTION2011-09-22+$0$3,836,054UNFORESEEN SITE CONDITIONS CHANGE ORDER
Mod P00005· CHANGE ORDER2012-02-01+$32,343$3,868,397UNFORESEEN SITE CONDITIONS CHANGE ORDER
Mod P00006· CHANGE ORDER2012-02-22+$50,853$3,919,250UNFORESEEN SITE CONDITIONS CHANGE ORDER
Mod P00007· CHANGE ORDER2012-03-19+$2,284$3,921,534UNFORESEEN SITE CONDITIONS CHANGE ORDER
Mod P00008· CHANGE ORDER2012-05-22+$35,764$3,957,298UNFORESEEN SITE CONDITIONS CHANGE ORDER
Mod P00009· CHANGE ORDER2012-05-24+$4,722$3,962,020UNFORESEEN SITE CONDITIONS CHANGE ORDER
Mod P00010· CHANGE ORDER2012-05-31+$21,320$3,983,340UNFORESEEN SITE CONDITIONS CHANGE ORDER
Mod P00011· CHANGE ORDER2012-06-18+$0$3,983,340UNFORESEEN SITE CONDITIONS CHANGE ORDER
Mod P00012· CHANGE ORDER2013-04-26−$22,750$3,960,590DEDUCT FOR LANDSCAPING AND REIMBURSMENT FOR FILL DIRT

Related awards · 8

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI L2NTWJMGFM81)

AwardOffice · PSC / listingNet obligationsFY
VA24814P4564248-NETWORK CONTRACT OFFICE 8 · J044 · MAINT/REPAIR/REBUILD OF EQUIPMENT- FURNACE, STEAM PLANT, AND DRYING EQUIPMENT; NUCLEAR REACTOR$14,162FY2014
VA245C0585245-NETWORK CONTRACT OFFICE 5 (36C245) · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY$2,106,682FY2011
VA246C0651652-RICHMOND · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY$988,090FY2010
VA245C0506512-BALTIMORE · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY$946,184FY2010
VA245C0479512-BALTIMORE · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY$2,254,883FY2010
VA245RA0445688-WASHINGTON DC · C111 · BLDGS & FAC / ADMIN & SVC BLDGS$427,416FY2010

Other recipients under AD61 from 512-BALTIMORE (most recent first)

AwardRecipientOfficeNet obligationsFY
VA512C00618DONLEY CONSTRUCTION LLC512-BALTIMORE$179,751FY2010
VA245C0168METROPOLITAN ENTERPRISES INC512-BALTIMORE$1,047,629FY2008

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA245C0528_3600_-NONE-_-NONE- · retrieved 2026-09-26.