Description
MOD TO DECREASE FUNDS TO REPROCURE WORK NOT PERFORMED
Base award description: CONSTRUCT A RESEARCH BUILDING AT THE LOCH RAVEN FACILITY. PROJECT WAS AWARDED TO MITSUBISHI BUR WAS VOIDED BY THE GOV'T FOR STATUS AND THEN AWARDED TO RESAPT SEVERAL MONTHS LATER
Modification chain · 6 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2011-02-24+$4,850,916= $4,850,916
- Mod P000032013-03-05+$36,000= $4,886,916
- Mod P000012013-05-24+$85,695= $4,972,611
- Mod P000022013-07-10+$64,978= $5,037,588
- Mod P000042013-09-11+$66,155= $5,103,743
- Mod P000052015-06-02-$10,000= $5,093,743
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2011-02-24 | +$4,850,916 | $4,850,916 | CONSTRUCT A RESEARCH BUILDING AT THE LOCH RAVEN FACILITY. PROJECT WAS AWARDED TO MITSUBISHI BUR WAS VOIDED BY… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-03-05 | +$36,000 | $4,886,916 | CONSTRUCT A RESEARCH BUILDING AT THE LOCH RAVEN FACILITY. PROJECT WAS AWARDED TO MITSUBISHI BUR WAS VOIDED BY… |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-05-24 | +$85,695 | $4,972,611 | CONSTRUCT A RESEARCH BUILDING AT THE LOCH RAVEN FACILITY. PROJECT WAS AWARDED TO MITSUBISHI BUR WAS VOIDED BY… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-07-10 | +$64,978 | $5,037,588 | CONSTRUCT A RESEARCH BUILDING AT THE LOCH RAVEN FACILITY. PROJECT WAS AWARDED TO MITSUBISHI BUR WAS VOIDED BY… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-09-11 | +$66,155 | $5,103,743 | MODIFICATION FOR PCOS 25, 27, 36, 53, 54, 55, 57, 58, 59, 60, 61, 62, 64, 65, 66, 67, 68, 69, 70 AND 72. |
| Mod P00005· CHANGE ORDER | 2015-06-02 | −$10,000 | $5,093,743 | MOD TO DECREASE FUNDS TO REPROCURE WORK NOT PERFORMED |
Related awards · 9
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI S4GAJ9JLVEY6)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA512Z10005 | 512-BALTIMORE · Y149 · CONSTRUCT/OTHER HOSPITAL BLDGS | $5,394 | FY2011 |
| VA245RA0408 | 512-BALTIMORE · Z149 · MAINT-REP-ALT/OTHER HOSPITAL BLDGS | $397,138 | FY2009 |
| VA245RA0389 | 512-BALTIMORE · Y111 · CONSTRUCTION OF OFFICE BUILDINGS | $112,867 | FY2009 |
| VA245C0377 | 512-BALTIMORE · Y164 · CONSTRUCTION OF DINING FACILITIES | $326,077 | FY2009 |
Other recipients under Y149 from 512-BALTIMORE (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA245C0394 | MITSUBISHI CONSTRUCTION CORPORATION | 512-BALTIMORE | $3,482,455 | FY2009 |
| VA245RA0393 | DONE DEAL GENERAL CONSTRUCTION AND ELECTRICAL INCORPORATED | 512-BALTIMORE | $983,000 | FY2009 |
| VA245C0091 | MEM/EDCO JV, LLC | 512-BALTIMORE | $1,551,240 | FY2008 |
| VA245C0192 | IACOBONI SITE SPECIALISTS, INC. | 512-BALTIMORE | $27,475 | FY2008 |
| VA512C80425 | DONLEY CONSTRUCTION LLC | 512-BALTIMORE | $32,053 | FY2008 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA245C0526_3600_-NONE-_-NONE- · retrieved 2026-09-26.