Award recordCONTRACT

STAR COMMUNICATION INC

PIID VA245C0406· VHA· 512-BALTIMORE· C215 · ARCHITECT AND ENGINEERING- GENERAL: PRODUCTION ENGINEERING· FY2009· $852,143 net obligations· UEI JCXKCRSJVQ99· MD

Description

NO COST MODIFICATION TO REDUCE SITE VISITS AND REPLACE WITH MEDICAL PHYSICIST TO REVIEW RADIATION DESIGN CALCULATIONS OF THE LOW CONCRETE DENSITIES

Base award description: PROVIDE PROFESSIONAL ARCHITECTURAL AND ENGINEERING SERVICES, TO INCLUDE CONSTRUSTION DOCUMENTS AND COST ESTIMATES FOR LINEAR ACCELERATOR DESIGN FOR VA MEDICAL CENTR, BALTIMORE MD

First action · last action
2009-09-18 · 2015-05-06
Transactions
12
First transaction's obligation
$540,039
Base + all options value (sum of deltas)
$852,143
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
10
SDVOSB flag on record
Yes (self-representation)
NAICS
541310 · ARCHITECTURAL SERVICES

Modification chain · 12 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$852,143$0Base award · 2009-09-18 · this action $540,039 · running total $540,039Modification 1 · 2010-02-09 · this action $18,370 · running total $558,409Modification 2 · 2010-03-10 · this action $6,644 · running total $565,053Modification 3 · 2010-07-16 · this action $2,167 · running total $567,220Modification 4 · 2010-08-05 · this action $57,101 · running total $624,321Modification 5 · 2011-06-08 · this action $36,110 · running total $660,431Modification 6 · 2011-06-08 · this action $40,000 · running total $700,431Modification 7 · 2012-01-11 · this action $34,596 · running total $735,027Modification P00008 · 2012-09-18 · this action $86,790 · running total $821,817Modification P00009 · 2013-05-29 · this action $0 · running total $821,817Modification P00010 · 2013-12-24 · this action $0 · running total $821,817Modification P00011 · 2015-05-06 · this action $30,327 · running total $852,143
  • Base2009-09-18+$540,039= $540,039
  • Mod 12010-02-09+$18,370= $558,409
  • Mod 22010-03-10+$6,644= $565,053
  • Mod 32010-07-16+$2,167= $567,220
  • Mod 42010-08-05+$57,101= $624,321
  • Mod 52011-06-08+$36,110= $660,431
  • Mod 62011-06-08+$40,000= $700,431
  • Mod 72012-01-11+$34,596= $735,027
  • Mod P000082012-09-18+$86,790= $821,817
  • Mod P000092013-05-29+$0= $821,817
  • Mod P000102013-12-24+$0= $821,817
  • Mod P000112015-05-06+$30,327= $852,143
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2009-09-18+$540,039$540,039PROVIDE PROFESSIONAL ARCHITECTURAL AND ENGINEERING SERVICES, TO INCLUDE CONSTRUSTION DOCUMENTS AND COST ESTIMA…
Mod 1· CHANGE ORDER2010-02-09+$18,370$558,409A PHYSICIST IS REQUIRED FOR THIS PROJECT TO INSURE CODE REQUIREMENTS ARE MET FOR THE DESIGN AND DEVELOPMENT OF…
Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-03-10+$6,644$565,053TO PERFORM BORING DURING THE WEEKEND. DUE TO EXCESSIVE LOUD NOISE AND SAFTEY HAZZARDS, IT WAS DETERMINED BY TH…
Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-07-16+$2,167$567,220TO PERFORM ADDITIONAL DESIGN SERVICES AND MODIFICATIONS BASED ON REVISION TO THE HVAC UPGRADE
Mod 4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-08-05+$57,101$624,321FOR ADDITIONAL DESIGN SO THAT THE LINEAR ACCELERATOR MAY BE BID AND CONSTRUCTED IN PHASES. ADDITIONAL DESIGN A…
Mod 5· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-06-08+$36,110$660,431THE LINEAR ACCELERATOR PROJECT SHALL BE DESIGNED FOR THE NEWEST VARIAN'S ACCELERATOR, ALSO KNOWN AS THE TRUEBE…
Mod 6· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-06-08+$40,000$700,431TO PROVIDE CHANGES AS RECOMMENDED BY NATIONAL HEALTH PHYSICS PROGRAM TO INCLUDE A SHEILDING MAZE AND A SAFER D…
Mod 7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-01-11+$34,596$735,027THE A/E PROVIDED ADDITINAL WORK INCLUDONG ADDITINAL SITE VISITS, FEES INCURRED FROM DELAYS AND ESCALATING FEES…
Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-09-18+$86,790$821,817THE A/E PROVIDED ADDITINAL WORK INCLUDONG ADDITINAL SITE VISITS, FEES INCURRED FROM DELAYS AND ESCALATING FEES…
Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-05-29+$0$821,817NO COST MODIFICATION TO REDUCE SITE VISITS AND REPLACE WITH MEDICAL PHYSICIST TO REVIEW RADIATION DESIGN CALCU…
Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-12-24+$0$821,817NO COST MODIFICATION TO REDUCE SITE VISITS AND REPLACE WITH MEDICAL PHYSICIST TO REVIEW RADIATION DESIGN CALCU…
Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-05-06+$30,327$852,143NO COST MODIFICATION TO REDUCE SITE VISITS AND REPLACE WITH MEDICAL PHYSICIST TO REVIEW RADIATION DESIGN CALCU…

Related awards · 1

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other recipients under C215 from 512-BALTIMORE (most recent first)

AwardRecipientOfficeNet obligationsFY
VA245RA0397ENVIRONMENTAL SOLUTIONS GROUP, INC512-BALTIMORE$223,522FY2009

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA245C0406_3600_-NONE-_-NONE- · retrieved 2026-09-26.