Award recordCONTRACT

PATRIOT GOVERNMENT SERVICES, INC.

PIID VA245C0221· VHA· 512-BALTIMORE· Z149 · MAINT-REP-ALT/OTHER HOSPITAL BLDGS· FY2008· $5,606,323 net obligations· UEI PAZWX6KEN9H8· DE

Description

RENOVATE BLDG. 19H, VAMC PERRY POINT PROJECT 512-516

First action · last action
2008-09-25 · 2010-09-13
Transactions
20
First transaction's obligation
$4,505,000
Base + all options value (sum of deltas)
$5,606,323
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
6
SDVOSB flag on record
Yes (self-representation)
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION

Modification chain · 20 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$5,606,323$0Base award · 2008-09-25 · this action $4,505,000 · running total $4,505,000Modification SA1 · 2009-01-23 · this action $14,616 · running total $4,519,616Modification SA2 · 2009-01-23 · this action $58,618 · running total $4,578,234Modification 3 · 2009-04-08 · this action $31,813 · running total $4,610,047Modification SA4 · 2009-04-08 · this action $20,049 · running total $4,630,096Modification SA5 · 2009-05-20 · this action $84,555 · running total $4,714,651Modification SA6 · 2009-05-21 · this action $18,196 · running total $4,732,847Modification SA7 · 2009-05-22 · this action $2,991 · running total $4,735,838Modification SA8 · 2009-06-02 · this action $8,279 · running total $4,744,117Modification SA9 · 2009-07-14 · this action $54,394 · running total $4,798,511Modification SA10 · 2009-07-16 · this action $89,813 · running total $4,888,324Modification SA11 · 2009-08-21 · this action $89,687 · running total $4,978,011Modification SA12 · 2009-11-02 · this action $89,493 · running total $5,067,504Modification SA13 · 2009-11-04 · this action $95,927 · running total $5,163,431Modification SA14 · 2009-11-10 · this action $67,881 · running total $5,231,312Modification SA15 · 2010-01-08 · this action $98,881 · running total $5,330,193Modification SA16 · 2010-03-18 · this action $97,285 · running total $5,427,478Modification SA17 · 2010-04-01 · this action $90,686 · running total $5,518,164Modification SA18 · 2010-05-10 · this action $81,345 · running total $5,599,509Modification SA19 · 2010-09-13 · this action $6,814 · running total $5,606,323
  • Base2008-09-25+$4,505,000= $4,505,000
  • Mod SA12009-01-23+$14,616= $4,519,616
  • Mod SA22009-01-23+$58,618= $4,578,234
  • Mod 32009-04-08+$31,813= $4,610,047
  • Mod SA42009-04-08+$20,049= $4,630,096
  • Mod SA52009-05-20+$84,555= $4,714,651
  • Mod SA62009-05-21+$18,196= $4,732,847
  • Mod SA72009-05-22+$2,991= $4,735,838
  • Mod SA82009-06-02+$8,279= $4,744,117
  • Mod SA92009-07-14+$54,394= $4,798,511
  • Mod SA102009-07-16+$89,813= $4,888,324
  • Mod SA112009-08-21+$89,687= $4,978,011
  • Mod SA122009-11-02+$89,493= $5,067,504
  • Mod SA132009-11-04+$95,927= $5,163,431
  • Mod SA142009-11-10+$67,881= $5,231,312
  • Mod SA152010-01-08+$98,881= $5,330,193
  • Mod SA162010-03-18+$97,285= $5,427,478
  • Mod SA172010-04-01+$90,686= $5,518,164
  • Mod SA182010-05-10+$81,345= $5,599,509
  • Mod SA192010-09-13+$6,814= $5,606,323
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2008-09-25+$4,505,000$4,505,000RENOVATE BLDG. 19H, VAMC PERRY POINT PROJECT 512-516
Mod SA1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-01-23+$14,616$4,519,616RENOVATE BLDG. 19H, VAMC PERRY POINT PROJECT 512-516
Mod SA2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-01-23+$58,618$4,578,234RENOVATE BLDG. 19H, VAMC PERRY POINT PROJECT 512-516
Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-04-08+$31,813$4,610,047RENOVATE BLDG. 19H, VAMC PERRY POINT PROJECT 512-516
Mod SA4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-04-08+$20,049$4,630,096RENOVATE BLDG. 19H, VAMC PERRY POINT PROJECT 512-516
Mod SA5· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-05-20+$84,555$4,714,651RENOVATE BLDG. 19H, VAMC PERRY POINT PROJECT 512-516
Mod SA6· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-05-21+$18,196$4,732,847RENOVATE BLDG. 19H, VAMC PERRY POINT PROJECT 512-516
Mod SA7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-05-22+$2,991$4,735,838RENOVATE BLDG. 19H, VAMC PERRY POINT PROJECT 512-516
Mod SA8· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-06-02+$8,279$4,744,117RENOVATE BLDG. 19H, VAMC PERRY POINT PROJECT 512-516
Mod SA9· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-07-14+$54,394$4,798,511RENOVATE BLDG. 19H, VAMC PERRY POINT PROJECT 512-516
Mod SA10· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-07-16+$89,813$4,888,324RENOVATE BLDG. 19H, VAMC PERRY POINT PROJECT 512-516
Mod SA11· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-08-21+$89,687$4,978,011RENOVATE BLDG. 19H, VAMC PERRY POINT PROJECT 512-516
Mod SA12· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-11-02+$89,493$5,067,504RENOVATE BLDG. 19H, VAMC PERRY POINT PROJECT 512-516
Mod SA13· CHANGE ORDER2009-11-04+$95,927$5,163,431RENOVATE BLDG. 19H, VAMC PERRY POINT PROJECT 512-516
Mod SA14· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-11-10+$67,881$5,231,312RENOVATE BLDG. 19H, VAMC PERRY POINT PROJECT 512-516
Mod SA15· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-01-08+$98,881$5,330,193RENOVATE BLDG. 19H, VAMC PERRY POINT PROJECT 512-516
Mod SA16· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-03-18+$97,285$5,427,478RENOVATE BLDG. 19H, VAMC PERRY POINT PROJECT 512-516
Mod SA17· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-04-01+$90,686$5,518,164RENOVATE BLDG. 19H, VAMC PERRY POINT PROJECT 512-516
Mod SA18· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-10+$81,345$5,599,509RENOVATE BLDG. 19H, VAMC PERRY POINT PROJECT 512-516
Mod SA19· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-13+$6,814$5,606,323RENOVATE BLDG. 19H, VAMC PERRY POINT PROJECT 512-516

Related awards · 11

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI PAZWX6KEN9H8)

AwardOffice · PSC / listingNet obligationsFY
VA24416J1648244-NETWORK CONTRACT OFFICE 4 (36C244) · Y1AA · CONSTRUCTION OF OFFICE BUILDINGS$24,185FY2016
VA24415J7388244-NETWORK CONTRACT OFFICE 4 · Y1AA · CONSTRUCTION OF OFFICE BUILDINGS$14,110FY2015
VA24415P7480244-NETWORK CONTRACT OFFICE 4 · J056 · MAINT/REPAIR/REBUILD OF EQUIPMENT- CONSTRUCTION AND BUILDING MATERIALS$7,971FY2015
VA24415J6598244-NETWORK CONTRACT OFFICE 4 (36C244) · Y1AA · CONSTRUCTION OF OFFICE BUILDINGS$1,328,347FY2015
VA24414J2239244-NETWORK CONTRACT OFFICE 4 (36C244) · Y1AA · CONSTRUCTION OF OFFICE BUILDINGS$4,702,126FY2014
VA24414J1894244-NETWORK CONTRACT OFFICE 4 (36C244) · Y1AA · CONSTRUCTION OF OFFICE BUILDINGS$1,752,511FY2014

Other recipients under Z149 from 512-BALTIMORE (most recent first)

AwardRecipientOfficeNet obligationsFY
VA512C10932WHELAN PROPERTIES, LLC512-BALTIMORE$280,481FY2011
VA512C10960WHELAN PROPERTIES, LLC512-BALTIMORE$73,360FY2011
VA512C10935WHELAN PROPERTIES, LLC512-BALTIMORE$82,447FY2011
VA245C0659JTS CM SERVICES, LLC512-BALTIMORE$5,542,697FY2011
VA512C10659DONLEY CONSTRUCTION LLC512-BALTIMORE$45,751FY2011

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA245C0221_3600_-NONE-_-NONE- · retrieved 2026-09-26.