Description
IGF::OT::IGF TASK ORDER #8 WATER TOWER REPAIRS SUPPLEMENTAL AGREEMENT FOR ULTRASONIC TRANSDUCER AND WATER TAP
Base award description: IGF::OT::IGF TASK ORDER #8 WATER TOWER REPAIRS
Modification chain · 10 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2015-03-23+$307,697= $307,697
- Mod P000012016-01-23+$0= $307,697
- Mod P000022016-02-26+$0= $307,697
- Mod P000032016-03-28+$0= $307,697
- Mod P000042016-04-12+$15,583= $323,280
- Mod P000052016-05-02+$0= $323,280
- Mod P000062016-06-30+$0= $323,280
- Mod P000072016-09-20+$0= $323,280
- Mod P000082016-09-23+$0= $323,280
- Mod P000092016-10-06+$5,200= $328,480
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2015-03-23 | +$307,697 | $307,697 | IGF::OT::IGF TASK ORDER #8 WATER TOWER REPAIRS |
| Mod P00001· OTHER ADMINISTRATIVE ACTION | 2016-01-23 | +$0 | $307,697 | IGF::OT::IGF TASK ORDER #8 WATER TOWER REPAIRS TIME EXTENSION |
| Mod P00002· CHANGE ORDER | 2016-02-26 | +$0 | $307,697 | IGF::OT::IGF TASK ORDER #8 WATER TOWER REPAIRS CHANGE ORDER; ADDITIONAL CONDUIT AND OUTLET |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-03-28 | +$0 | $307,697 | IGF::OT::IGF TASK ORDER #8 WATER TOWER REPAIRS CHANGE ORDER; ADDITIONAL CONDUIT AND OUTLET |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-04-12 | +$15,583 | $323,280 | IGF::OT::IGF TASK ORDER #8 WATER TOWER REPAIRS CHANGE ORDER; ADDITIONAL CONDUIT AND OUTLET |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-05-02 | +$0 | $323,280 | IGF::OT::IGF TASK ORDER #8 WATER TOWER REPAIRS CHANGE ORDER; ADDITIONAL CONDUIT AND OUTLET-DATE EXTENSION |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-06-30 | +$0 | $323,280 | IGF::OT::IGF TASK ORDER #8 WATER TOWER REPAIRS TIME EXTENSION |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-09-20 | +$0 | $323,280 | IGF::OT::IGF TASK ORDER #8 WATER TOWER REPAIRS TIME EXTENSION |
| Mod P00008· CHANGE ORDER | 2016-09-23 | +$0 | $323,280 | IGF::OT::IGF TASK ORDER #8 WATER TOWER REPAIRS CHANGE ORDER FOR ULTRASONIC TRANSDUCER AND WATER TAP |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-10-06 | +$5,200 | $328,480 | IGF::OT::IGF TASK ORDER #8 WATER TOWER REPAIRS SUPPLEMENTAL AGREEMENT FOR ULTRASONIC TRANSDUCER AND WATER TAP |
Related awards · 6
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI CKYLMFTCHF65)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24519C0149 | 245-NETWORK CONTRACT OFFICE 5 (36C245) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $255,032 | FY2019 |
| 36C25519N0299 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $975,246 | FY2019 |
| 36C25519N0300 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $444,095 | FY2019 |
| 36C25519N0294 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $165,722 | FY2019 |
| 36C25519N0298 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $155,393 | FY2019 |
| 36C25519N0171 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $300,082 | FY2019 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA24514J1398_3600_VA24513D0093_3600 · retrieved 2026-09-26.