Description
ARCHITECTUAL ENGINEERING SERVICES FOR THE NHCU PH-II 529-CSI-311. THIS CONTRACTOR IS SELECTED AS A RESULT OF THE PREVIOUS COMPETITION AND WERE SUCCESSFUL. PHASE II&PHASE III WERE IDENTIFIED IN THAT COMPETITION BUT SEPERATED BY TIME AND APPROPORIATIONS.
Base award description: ARCHITECTUAL ENGINEERING SERVICES FOR THE NHCU PH-II 529-CSI-311. THIS CONTRACTOR IS SELECTED AS A RESULT OF THE PREVIOUS COMPETITION AND WERE SUCCESSFUL. PHASE II & PHASE III WERE IDENTIFIED IN THAT COMPETITION BUT SEPERATED BY TIME AND APPROPORIATIONS.
Modification chain · 2 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-01-09+$346,029= $346,029
- Mod P000012013-11-12-$2,781= $343,248
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-01-09 | +$346,029 | $346,029 | ARCHITECTUAL ENGINEERING SERVICES FOR THE NHCU PH-II 529-CSI-311. THIS CONTRACTOR IS SELECTED AS A RESULT OF… |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-11-12 | −$2,781 | $343,248 | ARCHITECTUAL ENGINEERING SERVICES FOR THE NHCU PH-II 529-CSI-311. THIS CONTRACTOR IS SELECTED AS A RESULT OF… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI G3EKTJAUMT15)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA24413C0200 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $61,255 | FY2013 |
| V244P01153 | 529-BUTLER · C211 · ARCHITECT AND ENGINEERING- GENERAL: LANDSCAPING, INTERIOR LAYOUT, AND DESIGNING | -$3,332 | FY2011 |
| VA244C1411 | 244-NETWORK CONTRACT OFFICE 4 · C211 · ARCHITECT AND ENGINEERING- GENERAL: LANDSCAPING, INTERIOR LAYOUT, AND DESIGNING | $467,269 | FY2010 |
| VA0005 | 540-CLARKSBURG · C215 · ARCHITECT AND ENGINEERING- GENERAL: PRODUCTION ENGINEERING | $478,645 | FY2009 |
| V540C95002 | 540S-CLARKSBURG SMALL PURCHASE · C215 · A/E PROD ENG SVCS (INCL DESIGN-CONT | $5,000 | FY2009 |
| VA244P0558 | 646-PITTSBURG · C212 · ENGINEERING DRAFTING SERVICES | $337,457 | FY2008 |
Other recipients under C211 from 529-BUTLER (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA244C1432 | CDI CORP. | 529-BUTLER | $51,750 | FY2011 |
| VA244C1428 | PARADIGM ENGINEERS AND CONSTRUCTORS, PLLC | 529-BUTLER | $51,287 | FY2011 |
| VA244C1426 | AE WORKS LTD | 529-BUTLER | $74,032 | FY2011 |
| VA244C1425 | AE WORKS LTD | 529-BUTLER | $41,253 | FY2011 |
| VA244C1424 | TOLMAN ENGINEERING ARCHITECTURE & SURVEYING PLLC | 529-BUTLER | $154,914 | FY2010 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA244P0799_3600_-NONE-_-NONE- · retrieved 2026-09-26.