Description
FURNISH AND INSTALL HATCO 3CS SANITIZING SINK HEATER
Base award description: CONSTRUCTION SERVICES TO RENOVATE SPD SUITE AND STORE ROOM
Modification chain · 14 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2011-09-01+$1,049,000= $1,049,000
- Mod 12012-01-24+$0= $1,049,000
- Mod 22012-02-08+$4,234= $1,053,234
- Mod 32012-03-26-$1,953= $1,051,281
- Mod 42012-04-02+$16,567= $1,067,849
- Mod 52012-07-13+$0= $1,067,849
- Mod 62012-07-26+$19,601= $1,087,450
- Mod 72012-10-05+$0= $1,087,450
- Mod P000082012-12-26+$0= $1,087,450
- Mod P000092013-01-25+$24,537= $1,111,987
- Mod P000102013-06-04+$24,643= $1,136,630
- Mod P000112013-06-07+$0= $1,136,630
- Mod P000122013-09-25+$6,901= $1,143,530
- Mod P000132014-02-04+$6,908= $1,150,439
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2011-09-01 | +$1,049,000 | $1,049,000 | CONSTRUCTION SERVICES TO RENOVATE SPD SUITE AND STORE ROOM |
| Mod 1· CHANGE ORDER | 2012-01-24 | +$0 | $1,049,000 | CONSTRUCTION SERVICES TO REPAIR UNFORESEEN EMERGENCY REPAIR ON DETERIORATED GAS PIPE - UNILATERAL MOD DUE TO U… |
| Mod 2· CHANGE ORDER | 2012-02-08 | +$4,234 | $1,053,234 | CONSTRUCTION SERVICES TO REPAIR UNFORESEEN EMERGENCY REPAIR ON DETERIORATED GAS PIPE |
| Mod 3· CHANGE ORDER | 2012-03-26 | −$1,953 | $1,051,281 | DELETE SANITARY PIPING AND UTILITY SINK |
| Mod 4· CHANGE ORDER | 2012-04-02 | +$16,567 | $1,067,849 | PROVIDE AND INSTALL HOT WATER PIPING TO NEW RE-HEAT COILS IN BUILDING 1 BASEMENT |
| Mod 5· CHANGE ORDER | 2012-07-13 | +$0 | $1,067,849 | CORRECT DESIGN DEFICIT RE DOOR HRDWR PER SUBMITTAL NO. 079 AND TIME EXTENSION |
| Mod 6· CHANGE ORDER | 2012-07-26 | +$19,601 | $1,087,450 | CORRECT DESIGN DEFICIT RE DOOR HRDWR PER SUBMITTAL NO. 079 AND TIME EXTENSION |
| Mod 7· CHANGE ORDER | 2012-10-05 | +$0 | $1,087,450 | TIME EXTENSION TO CORRECT DESIGN DEFICIT RE DOOR HRDWR PER SUBMITTAL NO. 079 |
| Mod P00008· CHANGE ORDER | 2012-12-26 | +$0 | $1,087,450 | UNILATERAL MOD TO PERMIT CONTRACTOR TO PROCEED WITH JUNCTION BOX, WIRING AND SLAB DEMO(W/FISCAL CONCURRENCE)SO… |
| Mod P00009· CHANGE ORDER | 2013-01-25 | +$24,537 | $1,111,987 | MODIFICATION TO PROVIDE JUNCTION BOX, WIRING AND SLAB DEMO PER RFIS 005 AND 007. |
| Mod P00010· CHANGE ORDER | 2013-06-04 | +$24,643 | $1,136,630 | MODIFICATION TO PROVIDE 6-VOICE AND DATA DROPS, DOOR FRAME, WD DOOR, HARDWARE,EYE WASH STATION,SECURITY FENCE. |
| Mod P00011· CHANGE ORDER | 2013-06-07 | +$0 | $1,136,630 | MODIFICATION TO ADJUST FUNDING AMOUNT |
| Mod P00012· CHANGE ORDER | 2013-09-25 | +$6,901 | $1,143,530 | EXTEND AND CONNECT RO SCHEDULE 80 PIPING,HANGERS,FITTINGS, VALVES FROM RO MAIN TO NEW WASHER DISINFECTOR; RELO… |
| Mod P00013· CHANGE ORDER | 2014-02-04 | +$6,908 | $1,150,439 | FURNISH AND INSTALL HATCO 3CS SANITIZING SINK HEATER |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI HN5KSCMQHW13)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24423C0032 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $333,646 | FY2023 |
| 36C24421C0045 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $2,636,824 | FY2021 |
| 36C24421N0036 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $0 | FY2021 |
| 36C24421D0007 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $0 | FY2021 |
| 36C24421P0142 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · N059 · INSTALLATION OF EQUIPMENT- ELECTRICAL AND ELECTRONIC EQUIPMENT COMPONENTS | $14,500 | FY2021 |
| 36C24419C0198 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $12,556 | FY2019 |
Other recipients under Z141 from 542-COATESVILLE (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA244C1961 | WESCOTT ELECTRIC CO | 542-COATESVILLE | $779,331 | FY2011 |
| VA244C1891 | WESCOTT ELECTRIC CO | 542-COATESVILLE | $1,030,309 | FY2011 |
| VA542C10363 | WHELAN PROPERTIES, LLC | 542-COATESVILLE | $93,704 | FY2011 |
| VA542P14608 | RIDGE ROOFING INC | 542-COATESVILLE | $16,500 | FY2011 |
| VA244C1765 | CASTLE CONSTRUCTION AND CONSULTING, INC. | 542-COATESVILLE | $44,995 | FY2011 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA244C1869_3600_-NONE-_-NONE- · retrieved 2026-09-26.