Description
MODIFY CONTROL VALVES ON THE RADIANT PANELS TO RESOLVE TEMPERATURE CONTROL ISSUES.
Base award description: DESIGN BUILD RENOVATION OF 1 NORTH AND BUILDING 51
Modification chain · 13 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2010-01-21+$3,298,273= $3,298,273
- Mod 12011-05-18+$0= $3,298,273
- Mod 22011-07-18+$0= $3,298,273
- Mod 32011-09-15+$0= $3,298,273
- Mod 42011-11-11+$0= $3,298,273
- Mod 52012-01-09+$0= $3,298,273
- Mod 62012-04-06+$185,947= $3,484,220
- Mod 72012-04-09+$0= $3,484,220
- Mod 82012-04-09+$0= $3,484,220
- Mod 92012-07-25+$0= $3,484,220
- Mod P000102012-11-20+$0= $3,484,220
- Mod P000112012-12-18+$50,493= $3,534,713
- Mod P000122013-06-13+$92,365= $3,627,078
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2010-01-21 | +$3,298,273 | $3,298,273 | DESIGN BUILD RENOVATION OF 1 NORTH AND BUILDING 51 |
| Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-18 | +$0 | $3,298,273 | DESIGN BUILD RENOVATION OF 1 NORTH AND BUILDING 51 |
| Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-18 | +$0 | $3,298,273 | DESIGN BUILD RENOVATION OF 1 NORTH AND BUILDING 51 |
| Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-15 | +$0 | $3,298,273 | DESIGN BUILD RENOVATION OF 1 NORTH AND BUILDING 51 |
| Mod 4· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-11-11 | +$0 | $3,298,273 | DESIGN BUILD RENOVATION OF 1 NORTH AND BUILDING 51 |
| Mod 5· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-01-09 | +$0 | $3,298,273 | DESIGN BUILD RENOVATION OF 1 NORTH AND BUILDING 51 |
| Mod 6· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-06 | +$185,947 | $3,484,220 | OTHER FUNCTIONS - DESIGN BUILD RENOVATION OF 1 NORTH AND BUILDING 51 |
| Mod 7· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-04-09 | +$0 | $3,484,220 | CHANGE CONTRACTING OFFICER TO LYNNE DICKERHOFF FROM ANGELAMARIE SCOTT. |
| Mod 8· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-09 | +$0 | $3,484,220 | CLARIFY LANGUAGE IN MOD 0006. |
| Mod 9· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-25 | +$0 | $3,484,220 | CLARIFY LANGUAGE IN MOD 0006. |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-11-20 | +$0 | $3,484,220 | CLARIFY LANGUAGE IN MOD 0006. |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-12-18 | +$50,493 | $3,534,713 | STOVE AND FIRE SUPPRESSION. |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-06-13 | +$92,365 | $3,627,078 | MODIFY CONTROL VALVES ON THE RADIANT PANELS TO RESOLVE TEMPERATURE CONTROL ISSUES. |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI EN25YD2VC6Z6)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA24416J7051 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $486,461 | FY2017 |
| VA24416J5061 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $1,251,000 | FY2016 |
| VA78616P0618 | NATIONAL CEMETERY ADMIN (36C786) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS | $3,311 | FY2016 |
| VA24416C0139 | 244-NETWORK CONTRACT OFFICE 4 · J071 · MAINT/REPAIR/REBUILD OF EQUIPMENT- FURNITURE | $2,701 | FY2016 |
| VA24416J1339 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $723,702 | FY2016 |
| VA24415J6002 | 244-NETWORK CONTRACT OFFICE 4 · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $74,000 | FY2015 |
Other recipients under Z141 from 646-PITTSBURG (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA244C2039 | HI-DEF CONTRACTING, INC. | 646-PITTSBURG | $236,400 | FY2011 |
| VA244C2040 | HI-DEF CONTRACTING, INC. | 646-PITTSBURG | $794,347 | FY2011 |
| VA646C11220 | GREEN SITE TECH ENVIRONMENTAL LLC | 646-PITTSBURG | $4,252 | FY2011 |
| V646C11169 | GREEN SITE TECH ENVIRONMENTAL LLC | 646-PITTSBURG | $3,227 | FY2011 |
| VA244C1779 | MARE SOLUTIONS INC | 646-PITTSBURG | $124,000 | FY2011 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA244C1243_3600_-NONE-_-NONE- · retrieved 2026-09-26.