AMENDMENT (DECREASE) 4/1/13-6/30/13 PO#620C30032 AMENDMENT (INCREASE)TO CLOSEOUT FY12 PO#. PO#620-C20060 AMENDMENT (INCREASE) TO CLOSEOUT FY 11 PO#620-C10105 EXERCISING OPTION YEAR 3 (10/1/10-9/30/11) FOR VISN 3 MULTIPLE AWARD CONTRACT FOR CODERS/BILLERS&AR. P.O.#620-C10105
Base award description: VISN 3 MULTIPLE AWARD CONTRACT FOR (BILLERS, CODERS & A/R) - VA HUDSON VALLEY HEALTHCARE SYSTEM. EFFECTIVE 3/31/08 - 9/30/12 (BASE + 4 ONE YR. OPTIONS FOR RENEWAL; ESTIMATED $'S).
Modification chain · 40 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2008-03-31+$156,935= $156,935
- Mod 22008-10-16+$78,660= $235,595
- Mod 52009-09-24+$3,600= $239,195
- Mod 62009-09-30-$1,446= $237,749
- Mod 72009-10-01+$125,000= $362,749
- Mod 92010-01-04+$125,000= $487,749
- Mod 82010-01-26+$7,166= $494,915
- Mod 102010-04-01+$150,000= $644,915
- Mod 112010-04-01+$17,773= $662,688
- Mod 122010-07-06+$17,773= $680,461
- Mod 132010-07-27+$159,845= $840,306
- Mod 142010-10-01+$37,500= $877,806
- Mod 152010-10-01+$50,417= $928,223
- Mod 162011-01-31+$29,524= $957,746
- Mod 172011-01-31+$116,000= $1,073,746
- Mod 0018JT2011-03-30+$18,767= $1,092,513
- Mod 0021JT2011-04-01+$37,503= $1,130,016
- Mod 192011-04-01+$26,136= $1,156,152
- Mod 202011-04-01+$174,000= $1,330,152
- Mod 232011-07-29+$53,173= $1,383,325
- Mod 252011-07-29+$127,000= $1,510,325
- Mod 262011-09-29+$42,897= $1,553,222
- Mod 0027JT2011-10-24+$43,072= $1,596,294
- Mod 282011-10-24+$200,000= $1,796,294
- Mod 292011-12-06+$22,528= $1,818,822
- Mod 0030JK2012-02-21+$134,929= $1,953,751
- Mod 0031JK2012-02-29-$8,478= $1,945,274
- Mod 0033JT2012-04-04-$51,484= $1,893,789
- Mod 322012-04-04+$65,622= $1,959,412
- Mod 0034KJ2012-04-16-$910= $1,958,502
- Mod 0035KJ2012-04-24+$36,770= $1,995,272
- Mod 0036KJ2012-04-26+$240,000= $2,235,272
- Mod P000372012-11-01+$40,126= $2,275,398
- Mod P000392012-11-01+$33,000= $2,308,398
- Mod P000402012-11-09+$1,471= $2,309,869
- Mod P000412013-01-25-$30,782= $2,279,087
- Mod P000422013-01-28+$66,000= $2,345,087
- Mod P000432013-03-13+$55,693= $2,400,780
- Mod P000442013-03-13+$41,328= $2,442,108
- Mod P000452013-06-25-$49,378= $2,392,730
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2008-03-31 | +$156,935 | $156,935 | VISN 3 MULTIPLE AWARD CONTRACT FOR (BILLERS, CODERS & A/R) - VA HUDSON VALLEY HEALTHCARE SYSTEM. EFFECTIVE 3/3… |
| Mod 2· EXERCISE AN OPTION | 2008-10-16 | +$78,660 | $235,595 | VISN 3 MULTIPLE AWARD CONTRACT FOR (BILLERS, CODERS & A/R) - VA HUDSON VALLEY HEALTHCARE SYSTEM. EFFECTIVE 3/3… |
| Mod 5· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-09-24 | +$3,600 | $239,195 | VISN 3 MULTIPLE AWARD CONTRACT FOR (BILLERS, CODERS & A/R) - VA HUDSON VALLEY HEALTHCARE SYSTEM. EFFECTIVE 3/3… |
| Mod 6· CHANGE ORDER | 2009-09-30 | −$1,446 | $237,749 | VISN 3 MULTIPLE AWARD CONTRACT FOR (BILLERS, CODERS & A/R) - VA HUDSON VALLEY HEALTHCARE SYSTEM. EFFECTIVE 3/3… |
| Mod 7· EXERCISE AN OPTION | 2009-10-01 | +$125,000 | $362,749 | VISN 3 MULTIPLE AWARD CONTRACT FOR MCCF (CODERS/BILLERS &A/R) - CASTLEPOINT CAMPUS(BILLERS/AR). EXERCISING OPT… |
| Mod 9· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-01-04 | +$125,000 | $487,749 | AMENDMENT (INCREASE) - 2ND Q. 1/4/10-3/31/10. VISN 3 MULTIPLE AWARD CONTRACT FOR MCCF (CODERS/BILLERS &A/R) -… |
| Mod 8· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-01-26 | +$7,166 | $494,915 | AMENDMENT (INCREASE) 1ST Q. (10/1/09-12/31/09) VISN 3 MULTIPLE AWARD CONTRACT FOR MCCF (CODERS/BILLERS &A/R) -… |
| Mod 10· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-04-01 | +$150,000 | $644,915 | AMENDMENT (INCREASE) - 3RD Q. 4/1/10-6/30/10. VISN 3 MULTIPLE AWARD CONTRACT FOR MCCF (CODERS/BILLERS &A/R) -… |
| Mod 11· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-04-01 | +$17,773 | $662,688 | AMENDMENT (INCREASE) - 3RD Q. 4/1/10-6/30/10. VISN 3 MULTIPLE AWARD CONTRACT FOR MCCF (CODERS/BILLERS &A/R) -… |
| Mod 12· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-07-06 | +$17,773 | $680,461 | AMENDMENT (INCREASE) - 4TH Q. 7/1/10-9/30/10. VISN 3 MULTIPLE AWARD CONTRACT FOR MCCF (CODERS/BILLERS &A/R) -… |
| Mod 13· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-07-27 | +$159,845 | $840,306 | ADDITIONAL AMENNDMENT INCREASE TO CLOSEOUT PENDING INVOICES. AMENDMENT (INCREASE) - 4TH Q. 7/1/10-9/30/10.… |
| Mod 14· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-10-01 | +$37,500 | $877,806 | EXERCISING OPTION YEAR 1(10/1/10-9/30/11)(MONTROSE) CODING 1ST Q. (10/1/10 - 12/31/10). PO#: 620-C10104 - VIS… |
| Mod 15· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-10-01 | +$50,417 | $928,223 | EXERCISING OPTION YEAR 3(10/1/10-9/30/11 - 1ST Q. (10/1/10 - 12/31/10). PO#: 620-C10105 - VISN 3 MULTIPLE AWA… |
| Mod 16· OTHER ADMINISTRATIVE ACTION | 2011-01-31 | +$29,524 | $957,746 | AMENDMENT (INCREASE) - 1ST Q. TO COMPLETE PENDING INVOICES PO#: 620-C10105. EXERCISING OPTION YEAR 3(10/1/10-… |
| Mod 17· OTHER ADMINISTRATIVE ACTION | 2011-01-31 | +$116,000 | $1,073,746 | AMENDMENT (INCREASE) - 2ND Q. FUNDING (1/2/11 - 3/31/11) PO#: 620-C10105. AMENDMENT (INCREASE) - 1ST Q. TO CO… |
| Mod 0018JT· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-03-30 | +$18,767 | $1,092,513 | AMENDMENT (INCREASE) - 2ND Q. FUNDING (2/28/11 - 3/31/11) PO#: 620-C10104. ADDITIONAL HIRE FOR "CODING". AMEN… |
| Mod 0021JT· FUNDING ONLY ACTION | 2011-04-01 | +$37,503 | $1,130,016 | AMENDMENT (INCREASE)- 3RD Q. FUNDING (4/1/11 - 6/30/11) PO#: 620-C10104 **CODING*** EXERCISING OPTION YEAR… |
| Mod 19· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-04-01 | +$26,136 | $1,156,152 | AMENDMENT (INCREASE) - 2ND Q. FUNDING (3/31/11 - 3/31/11) TO COMPLETE PENDING INVOICES. PO#: 620-C10105 EXERC… |
| Mod 20· FUNDING ONLY ACTION | 2011-04-01 | +$174,000 | $1,330,152 | AMENDMENT (INCREASE)- 3RDQ. FUNDING (4/1/11 - 6/30/11) PO#: 620-C10105 EXERCISING OPTION YEAR 3(10/1/10-9/30… |
| Mod 23· FUNDING ONLY ACTION | 2011-07-29 | +$53,173 | $1,383,325 | AMENDMENT (INCREASE)- 3RD Q. (4/1/11 - 6/30/11) PO#: 620-C10105 PENDING INVOICES. EXERCISING OPTION YEAR 3(1… |
| Mod 25· FUNDING ONLY ACTION | 2011-07-29 | +$127,000 | $1,510,325 | AMENDMENT (INCREASE) - 4TH Q. FUNDING (7/1/11 - 9/30/11) PO#: 620-C10105 EXERCISING OPTION YEAR 3(10/1/10… |
| Mod 26· FUNDING ONLY ACTION | 2011-09-29 | +$42,897 | $1,553,222 | AMENDMENT (INCREASE) - 4TH Q. FUNDING(7/1/11-9/30/11) TO COMPLETE (SEPTEMBER) PO#: 620-C10105 EXERCISING… |
| Mod 0027JT· EXERCISE AN OPTION | 2011-10-24 | +$43,072 | $1,596,294 | EXERCISING OPTION YEAR 4 (10/1/11-9/30/12) FOR VISN 3 MULTIPLE AWARD CONTRACT FOR CODERS/BILLERS&AR. HIMS COD… |
| Mod 28· EXERCISE AN OPTION | 2011-10-24 | +$200,000 | $1,796,294 | EXERCISING OPTION YEAR 4 (10/1/11-9/30/12) FOR VISN 3 MULTIPLE AWARD CONTRACT FOR CODERS/BILLERS&AR. BILLER&A… |
| Mod 29· FUNDING ONLY ACTION | 2011-12-06 | +$22,528 | $1,818,822 | AMENDMENT (INCREASE) TO CLOSEOUT FY 11 PO#620-C10105 EXERCISING OPTION YEAR 3 (10/1/10-9/30/11) FOR VISN 3 MU… |
| Mod 0030JK· FUNDING ONLY ACTION | 2012-02-21 | +$134,929 | $1,953,751 | AMENDMENT (INCREASE) 2ND Q. FUNDING(1/3/12-3/31/12) - PO#620-C20060. AMENDMENT (INCREASE) TO CLOSEOUT FY 11… |
| Mod 0031JK· FUNDING ONLY ACTION | 2012-02-29 | −$8,478 | $1,945,274 | AMENDMENT (DECREASE) 2ND Q. FUNDING (1/3/12-3/31/12) - PO#620-C20060. AMENDMENT (INCREASE) TO CLOSEOUT FY 11… |
| Mod 0033JT· FUNDING ONLY ACTION | 2012-04-04 | −$51,484 | $1,893,789 | AMENDMENT (DECREASE) TO CLOSEOUT HIMS FY11(10/1/10-9/30/11) PO#. PO#620-C10104 AMENDMENT (INCREASE) TO CLOS… |
| Mod 32· FUNDING ONLY ACTION | 2012-04-04 | +$65,622 | $1,959,412 | AMENDMENT (INCREASE) 3RD-4TH Q. FUNDING (4/1/12 - 9/30/12) - HIMS. PO#620-C20059. AMENDMENT (INCREASE) TO CL… |
| Mod 0034KJ· FUNDING ONLY ACTION | 2012-04-16 | −$910 | $1,958,502 | AMENDMENT (DECREASE) TO CLOSEOUT HIMS FY11(10/1/10-9/30/11) PO#. PO#620-C10105 AMENDMENT (INCREASE) TO CLOS… |
| Mod 0035KJ· FUNDING ONLY ACTION | 2012-04-24 | +$36,770 | $1,995,272 | AMENDMENT (INCREASE) FOR 2ND Q.(1/3/12-3/31/12) PENDING INVOICES HIMS PO#. PO#620-C20060 AMENDMENT (INCREAS… |
| Mod 0036KJ· FUNDING ONLY ACTION | 2012-04-26 | +$240,000 | $2,235,272 | AMENDMENT (INCREASE) FULL FUNDING TO COMPLETE FY 12 3RD&4TH Q. (4/1/12 - 9/30/12) PO#. PO#620-C20060 AMENDM… |
| Mod P00037· EXERCISE AN OPTION | 2012-11-01 | +$40,126 | $2,275,398 | EXERCISE OPTION EFFECTIVE 10/1/12-3/31/13 (6)MONTHS. AMENDMENT (INCREASE) FULL FUNDING TO COMPLETE FY 12 3RD… |
| Mod P00039· EXERCISE AN OPTION | 2012-11-01 | +$33,000 | $2,308,398 | EXERCISING OPTION TO EXTEND (10/1/12-3/31/13). AMENDMENT (INCREASE) FULL FUNDING TO COMPLETE FY 12 3RD&4TH Q… |
| Mod P00040· FUNDING ONLY ACTION | 2012-11-09 | +$1,471 | $2,309,869 | AMENDMENT (INCREASE)TO CLOSEOUT FY12 PO#. PO#620-C20059 AMENDMENT (INCREASE) TO CLOSEOUT FY 11 PO#620-C1010… |
| Mod P00041· FUNDING ONLY ACTION | 2013-01-25 | −$30,782 | $2,279,087 | AMENDMENT (DECREASE) TO CLOSEOUT FY12 PO#. AMENDMENT (INCREASE)TO CLOSEOUT FY12 PO#. PO#620-C20060 AMENDME… |
| Mod P00042· FUNDING ONLY ACTION | 2013-01-28 | +$66,000 | $2,345,087 | AMENDMENT (INCREASE) TO ADJUST 1ST&2ND Q FUNDING (10/1/12-3/31/13). PO#620C30035 AMENDMENT (INCREASE)TO… |
| Mod P00043· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-03-13 | +$55,693 | $2,400,780 | AMENDMENT (INCREASE) 4/1/13-6/30/13 PO#620C30032 AMENDMENT (INCREASE)TO CLOSEOUT FY12 PO#. PO#620-C200… |
| Mod P00044· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-03-13 | +$41,328 | $2,442,108 | AMENDMENT (INCREASE) 4/1/13-6/30/13 PO#620C30035 AMENDMENT (INCREASE)TO CLOSEOUT FY12 PO#. PO#620-C200… |
| Mod P00045· FUNDING ONLY ACTION | 2013-06-25 | −$49,378 | $2,392,730 | AMENDMENT (DECREASE) 4/1/13-6/30/13 PO#620C30032 AMENDMENT (INCREASE)TO CLOSEOUT FY12 PO#. PO#620-C200… |
Related awards · 6
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI R5T8XWNNCFP1)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA243P0198 | 243-NETWORK CONTRACTING OFFICE 03 · R699 · SUPPORT- ADMINISTRATIVE: OTHER | $972,348 | FY2008 |
Other recipients under R699 from 243-NETWORK CONTRACTING OFFICE 03 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA24316A0012 | MANAGED RESOURCES INC | 243-NETWORK CONTRACTING OFFICE 03 | $0 | FY2016 |
| VA24315F1908 | ALANTE SECURITY GROUP, INC | 243-NETWORK CONTRACTING OFFICE 03 | $191,941 | FY2015 |
| VA24315A0038 | MANAGED RESOURCES INC | 243-NETWORK CONTRACTING OFFICE 03 | $0 | FY2015 |
| VA24314C0098 | ASSOCIATE RESOURCE MANAGEMENT, INC | 243-NETWORK CONTRACTING OFFICE 03 | $570,222 | FY2014 |
| VA24314J2667 | MANAGED RESOURCES INC | 243-NETWORK CONTRACTING OFFICE 03 | $378,091 | FY2014 |