Description
IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. DE-OBLIGATION CLOSEOUT MODIFICATION
Base award description: IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION.
Modification chain · 30 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2013-03-01+$23,329,058= $23,329,058
- Mod P000012013-07-01+$0= $23,329,058
- Mod P000022014-01-13-$147,475= $23,181,584
- Mod P000032014-03-04+$0= $23,181,584
- Mod P000042014-06-26+$0= $23,181,584
- Mod P000052014-08-25-$35,460= $23,146,123
- Mod P000062014-09-29+$0= $23,146,123
- Mod P000072014-10-15-$288,018= $22,858,105
- Mod P000082014-11-13+$0= $22,858,105
- Mod P000092015-01-14-$535,436= $22,322,669
- Mod P000102015-03-11+$381,858= $22,704,527
- Mod P000112015-08-06-$300,640= $22,403,887
- Mod P000122015-09-11+$0= $22,403,887
- Mod P000132015-10-02+$0= $22,403,887
- Mod P000142015-11-03+$0= $22,403,887
- Mod P000152015-11-23+$0= $22,403,887
- Mod P000162015-12-17+$0= $22,403,887
- Mod P000172016-01-28+$0= $22,403,887
- Mod P000182016-02-17+$0= $22,403,887
- Mod P000192016-03-16+$0= $22,403,887
- Mod P000202016-04-18+$0= $22,403,887
- Mod P000212016-05-13+$0= $22,403,887
- Mod P000222016-05-16+$0= $22,403,887
- Mod P000232016-07-08+$0= $22,403,887
- Mod P000242016-08-16+$0= $22,403,887
- Mod P000252016-09-09+$0= $22,403,887
- Mod P000262016-09-30+$0= $22,403,887
- Mod P000272016-10-14+$0= $22,403,887
- Mod P000282016-10-21+$0= $22,403,887
- Mod P000292017-07-19-$5,467,353= $16,936,534
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2013-03-01 | +$23,329,058 | $23,329,058 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. |
| Mod P00001· OTHER ADMINISTRATIVE ACTION | 2013-07-01 | +$0 | $23,329,058 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-01-13 | −$147,475 | $23,181,584 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-03-04 | +$0 | $23,181,584 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-06-26 | +$0 | $23,181,584 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-08-25 | −$35,460 | $23,146,123 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-09-29 | +$0 | $23,146,123 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-10-15 | −$288,018 | $22,858,105 | VISN 20 REAL TIME LOCATION SYSTEM - MODIFICATION #7: SSLIN CORRECTIONS FOR ALL SITES AND POST SITE-ASSESSMENT… |
| Mod P00008· OTHER ADMINISTRATIVE ACTION | 2014-11-13 | +$0 | $22,858,105 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-01-14 | −$535,436 | $22,322,669 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM- POST SITE-ASSESSMENT ADJUSTMENT MODFICATION FOR ROSEBURG AND&… |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-03-11 | +$381,858 | $22,704,527 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. POST PHDD ADJUSTMENTS FOR SPOKANE, BOISE, AND… |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-08-06 | −$300,640 | $22,403,887 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. CLEAN-UP MODIFICATION. |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-11 | +$0 | $22,403,887 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. CLEAN-UP MODIFICATION. |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-10-02 | +$0 | $22,403,887 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. CLEAN-UP MODIFICATION. |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-11-03 | +$0 | $22,403,887 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. SHORT-TERM POP EXTENSION. |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-11-23 | +$0 | $22,403,887 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. SHORT-TERM EXTENSION MODIFICATION. |
| Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-12-17 | +$0 | $22,403,887 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. CLEAN-UP MODIFICATION. |
| Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-01-28 | +$0 | $22,403,887 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM DEPLOYMENT, SHORT-TERM EXTENSION MODIFICATION. |
| Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-02-17 | +$0 | $22,403,887 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM DEPLOYMENT, SHORT-TERM EXTENSION MODIFICATION. |
| Mod P00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-03-16 | +$0 | $22,403,887 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM DEPLOYMENT, SHORT-TERM EXTENSION MODIFICATION. |
| Mod P00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-04-18 | +$0 | $22,403,887 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. SHORT-TERM POP EXTENSION. |
| Mod P00021· OTHER ADMINISTRATIVE ACTION | 2016-05-13 | +$0 | $22,403,887 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. POP EXTENSION THROUGH 7-11-16. |
| Mod P00022· OTHER ADMINISTRATIVE ACTION | 2016-05-16 | +$0 | $22,403,887 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. PARTIAL STOP WORK FOR ASSET TRACKING AND TEMPE… |
| Mod P00023· OTHER ADMINISTRATIVE ACTION | 2016-07-08 | +$0 | $22,403,887 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. POP EXTENSION THROUGH 09-09-16. |
| Mod P00024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-08-16 | +$0 | $22,403,887 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. SHORT-TERM POP EXTENSION. |
| Mod P00025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-09-09 | +$0 | $22,403,887 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. STOP WORK ORDER LIFT AND EXTENSION |
| Mod P00026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-09-30 | +$0 | $22,403,887 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. POP EXTENSION |
| Mod P00027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-10-14 | +$0 | $22,403,887 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. POP EXTENSION |
| Mod P00028· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-10-21 | +$0 | $22,403,887 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. POP EXTENSION |
| Mod P00029· CLOSE OUT | 2017-07-19 | −$5,467,353 | $16,936,534 | IGF::OT::IGF. VISN 20 REAL TIME LOCATION SYSTEM IMPLEMENTATION. DE-OBLIGATION CLOSEOUT MODIFICATION |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI MBSRAWAQ9559)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24125N0499 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · DA01 · IT AND TELECOM - BUSINESS APPLICATION/APPLICATION DEVELOPMENT SUPPORT SERVICES (LABOR) | $95,363 | FY2025 |
| 36C24124N1423 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · J065 · MAINT/REPAIR/REBUILD OF EQUIPMENT- MEDICAL, DENTAL, AND VETERINARY EQUIPMENT AND SUPPLIES | $174,841 | FY2024 |
| 36C24124N1377 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · J065 · MAINT/REPAIR/REBUILD OF EQUIPMENT- MEDICAL, DENTAL, AND VETERINARY EQUIPMENT AND SUPPLIES | $196,314 | FY2024 |
| 36C24124N1308 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · J065 · MAINT/REPAIR/REBUILD OF EQUIPMENT- MEDICAL, DENTAL, AND VETERINARY EQUIPMENT AND SUPPLIES | $1,911,132 | FY2024 |
| 36C24124N1035 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · J065 · MAINT/REPAIR/REBUILD OF EQUIPMENT- MEDICAL, DENTAL, AND VETERINARY EQUIPMENT AND SUPPLIES | $23,596 | FY2024 |
| 36C24124N0336 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · J065 · MAINT/REPAIR/REBUILD OF EQUIPMENT- MEDICAL, DENTAL, AND VETERINARY EQUIPMENT AND SUPPLIES | $747,910 | FY2024 |
Other recipients under 7035 from TECHNOLOGY ACQUISITION CENTER AUSTIN (36C10A) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C10A21N0005 | DYNATOUCH CORPORATION | TECHNOLOGY ACQUISITION CENTER AUSTIN (36C10A) | $27,682 | FY2021 |
| 36C10A20F0334 | FOUR POINTS TECHNOLOGY, L.L.C. | TECHNOLOGY ACQUISITION CENTER AUSTIN (36C10A) | $486,666 | FY2020 |
| 36C10A20F0305 | MINBURN TECHNOLOGY GROUP, LLC | TECHNOLOGY ACQUISITION CENTER AUSTIN (36C10A) | $8,177,961 | FY2020 |
| 36C10A20F0292 | MINBURN TECHNOLOGY GROUP, LLC | TECHNOLOGY ACQUISITION CENTER AUSTIN (36C10A) | $67,899 | FY2020 |
| 36C10A20F0265 | FEDSTORE CORPORATION | TECHNOLOGY ACQUISITION CENTER AUSTIN (36C10A) | $1,295,617 | FY2020 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA118A13J0037_3600_VA118A12D0025_3600 · retrieved 2026-09-26.