Award recordCONTRACT

THUNDERCAT TECHNOLOGY, LLC

PIID VA11814F0567· VA Staff Offices· TECHNOLOGY ACQUISITION CENTER - NJ· 7050 · INFORMATION TECHNOLOGY COMPONENTS· FY2014· $16,843,056 net obligations· UEI UER4AJLUB8D5· VA

Description

IGF::OT::IGF THE PURPOSE OF THIS MODIFICATION IS TO CONSOLIDATE AND CHANGE SERVER DEPLOYMENT LOCATIONS, UPDATE HARDWARE DELIVERY OPTIONS, AND INCORPORATE A 122 DAY PERIOD OF PERFORMANCE EXTENSION.

Base award description: IGF::OT::IGF EXCHANGE HARDWARE REPLACEMENT TO INCLUDE HARDWARE, ASSOCIATED WARRANTIES AND INSTALLATION AND TESTING OF EQUIPMENT. VA IS CURRENTLY AT RISK DUE TO A MATERIAL WEAKNESS IN ACTIVE DIRECTORY. IN ORDER TO ADDRESS THE MATERIAL WEAKNESS, THE EXISTING DOMAIN CONTROLLERS MUST BE UPGRADED. HOWEVER, THE DOMAIN CONTROLLER UPGRADE CANNOT TAKE PLACE UNTIL EXCHANGE 2003 HAS BEEN COMPLETELY REMOVED FROM THE VA ACTIVE DIRECTORY FOREST. THE EXCHANGE 2003 APPLICATION IS TECHNICALLY PREVENTING THE MATERIAL WEAKNESS FROM BEING REMEDIATED. HARDWARE IS REQUIRED FOR 572 SERVERS OF VARIOUS TYPES TO COMPLETE AN ON PREMISE REPLACEMENT OF VA S MICROSOFT EXCHANGE 2003 AND 2007 ENVIRONMENT.

First action · last action
2014-09-23 · 2015-12-15
Transactions
12
First transaction's obligation
$16,819,056
Base + all options value (sum of deltas)
$16,843,056
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
10
SDVOSB flag on record
Yes (self-representation)
Parent IDV
NNG07DA45B
NAICS
541519 · OTHER COMPUTER RELATED SERVICES

Modification chain · 12 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$16,843,056$0Base award · 2014-09-23 · this action $16,819,056 · running total $16,819,056Modification P00001 · 2015-05-22 · this action $0 · running total $16,819,056Modification P00002 · 2015-06-22 · this action $0 · running total $16,819,056Modification P00003 · 2015-07-23 · this action $0 · running total $16,819,056Modification P00004 · 2015-08-21 · this action $0 · running total $16,819,056Modification P00005 · 2015-09-01 · this action $0 · running total $16,819,056Modification P00006 · 2015-09-23 · this action $0 · running total $16,819,056Modification P00007 · 2015-10-23 · this action $0 · running total $16,819,056Modification P00008 · 2015-11-04 · this action $0 · running total $16,819,056Modification P00009 · 2015-11-20 · this action $0 · running total $16,819,056Modification P00010 · 2015-12-02 · this action $0 · running total $16,819,056Modification P00011 · 2015-12-15 · this action $24,000 · running total $16,843,056
  • Base2014-09-23+$16,819,056= $16,819,056
  • Mod P000012015-05-22+$0= $16,819,056
  • Mod P000022015-06-22+$0= $16,819,056
  • Mod P000032015-07-23+$0= $16,819,056
  • Mod P000042015-08-21+$0= $16,819,056
  • Mod P000052015-09-01+$0= $16,819,056
  • Mod P000062015-09-23+$0= $16,819,056
  • Mod P000072015-10-23+$0= $16,819,056
  • Mod P000082015-11-04+$0= $16,819,056
  • Mod P000092015-11-20+$0= $16,819,056
  • Mod P000102015-12-02+$0= $16,819,056
  • Mod P000112015-12-15+$24,000= $16,843,056
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2014-09-23+$16,819,056$16,819,056IGF::OT::IGF EXCHANGE HARDWARE REPLACEMENT TO INCLUDE HARDWARE, ASSOCIATED WARRANTIES AND INSTALLATION AND TES…
Mod P00001· OTHER ADMINISTRATIVE ACTION2015-05-22+$0$16,819,056IGF::OT::IGF NO COST PERIOD OF PERFORMANCE EXTENSION.
Mod P00002· OTHER ADMINISTRATIVE ACTION2015-06-22+$0$16,819,056IGF::OT::IGF NO COST PERIOD OF PERFORMANCE EXTENSION.
Mod P00003· OTHER ADMINISTRATIVE ACTION2015-07-23+$0$16,819,056IGF::OT::IGF NO COST PERIOD OF PERFORMANCE EXTENSION FROM JULY 23, 2015 THROUGH AUGUST 22,2015.
Mod P00004· CHANGE ORDER2015-08-21+$0$16,819,056IGF::OT::IGF NO COST PERIOD OF PERFORMANCE EXTENSION.
Mod P00005· OTHER ADMINISTRATIVE ACTION2015-09-01+$0$16,819,056IGF::OT::IGF NO COST PERIOD OF PERFORMANCE EXTENSION FROM SEPTEMBER 2, 2015 THROUGH SEPTEMBER 23,2015.
Mod P00006· CHANGE ORDER2015-09-23+$0$16,819,056IGF::OT::IGF NO COST PERIOD OF PERFORMANCE EXTENSION.
Mod P00007· CHANGE ORDER2015-10-23+$0$16,819,056IGF::OT::IGF NO COST PERIOD OF PERFORMANCE EXTENSION.
Mod P00008· CHANGE ORDER2015-11-04+$0$16,819,056IGF::OT::IGF NO COST PERIOD OF PERFORMANCE EXTENSION THROUGH TO NOVEMBER 20, 2015.
Mod P00009· CHANGE ORDER2015-11-20+$0$16,819,056IGF::OT::IGF NO COST PERIOD OF PERFORMANCE EXTENSION THROUGH TO DECEMBER 4, 2015.
Mod P00010· CHANGE ORDER2015-12-02+$0$16,819,056IGF::OT::IGF NO COST PERIOD OF PERFORMANCE EXTENSION THROUGH DECEMBER 22, 2015.
Mod P00011· CHANGE ORDER2015-12-15+$24,000$16,843,056IGF::OT::IGF THE PURPOSE OF THIS MODIFICATION IS TO CONSOLIDATE AND CHANGE SERVER DEPLOYMENT LOCATIONS, UPDAT…

Related awards · 11

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI UER4AJLUB8D5)

AwardOffice · PSC / listingNet obligationsFY
36C10B26F0353TECHNOLOGY ACQUISITION CENTER NJ (36C10B) · DA10 · IT AND TELECOM - BUSINESS APPLICATION/APPLICATION DEVELOPMENT SOFTWARE AS A SERVICE$6,699,160FY2026
36C10B26F0294TECHNOLOGY ACQUISITION CENTER NJ (36C10B) · DK10 · IT AND TELECOM - STORAGE AS A SERVICE$399,990FY2026
36C10B26F0331TECHNOLOGY ACQUISITION CENTER NJ (36C10B) · DA10 · IT AND TELECOM - BUSINESS APPLICATION/APPLICATION DEVELOPMENT SOFTWARE AS A SERVICE$302,255FY2026
36C10B26F0361TECHNOLOGY ACQUISITION CENTER NJ (36C10B) · DA01 · IT AND TELECOM - BUSINESS APPLICATION/APPLICATION DEVELOPMENT SUPPORT SERVICES (LABOR)$249,500FY2026
36C10B26F0330TECHNOLOGY ACQUISITION CENTER NJ (36C10B) · DA10 · IT AND TELECOM - BUSINESS APPLICATION/APPLICATION DEVELOPMENT SOFTWARE AS A SERVICE$197,230FY2026
36C10B26F0314TECHNOLOGY ACQUISITION CENTER NJ (36C10B) · 7K20 · IT AND TELECOM - STORAGE PRODUCTS (HARDWARE AND PERPETUAL LICENSE SOFTWARE)$16,825,634FY2026

Other recipients under 7050 from TECHNOLOGY ACQUISITION CENTER - NJ (most recent first)

AwardRecipientOfficeNet obligationsFY
VA11816F0869I3 FEDERAL LLCTECHNOLOGY ACQUISITION CENTER - NJ$17,000FY2016
VA11816J0828INTELLIGENT WAVES LLCTECHNOLOGY ACQUISITION CENTER - NJ$22,552FY2016
VA11816J0827RED RIVER TECHNOLOGY LLCTECHNOLOGY ACQUISITION CENTER - NJ$12,593FY2016
VA11815F0688MERLIN INTERNATIONAL, INC.TECHNOLOGY ACQUISITION CENTER - NJ$1,796,558FY2015
VA11815F0684ABBA TECHNOLOGIES, INC.TECHNOLOGY ACQUISITION CENTER - NJ$3,803,573FY2015

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA11814F0567_3600_NNG07DA45B_8000 · retrieved 2026-09-26.