Description
THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE FUNDS IN THE AMOUNT OF $305,234.63
Base award description: ::IGF::OT::IGF THE CONTRACTOR SHALL DEVELOP A COMPLETE SOLUTION FOR THE PRE INBOUND EPRESCRIBING PROJECT TO INCLUDE IT PRODUCT ARCHITECTURAL DESIGN/ DEVELOPMENT, SOFTWARE DEVELOPMENT, PROJECT MANAGEMENT, SYSTEM ADMINISTRATION AND SUPPORT, TESTING, SYSTEM INTEGRATION, AUTHORITY TO OPERATE (ATO) APPROVAL OF THE PRODUCT, DEPLOYMENT/IMPLEMENTATION, AND TRAINING.
Modification chain · 28 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2015-09-03+$1,005,288= $1,005,288
- Mod P000012016-02-22+$0= $1,005,288
- Mod P000022016-03-18+$0= $1,005,288
- Mod P000032016-04-01+$502,644= $1,507,932
- Mod P000042016-07-01+$0= $1,507,932
- Mod P000062016-07-15+$0= $1,507,932
- Mod P000072016-07-28+$1,520,536= $3,028,468
- Mod P000092016-09-15+$0= $3,028,468
- Mod P000102016-10-06+$0= $3,028,468
- Mod P000112016-12-06+$139,984= $3,168,452
- Mod P000122017-01-19+$1,243,796= $4,412,248
- Mod P000132017-04-12+$9,370= $4,421,618
- Mod P000142017-07-17+$0= $4,421,618
- Mod P000152017-08-28+$94,282= $4,515,901
- Mod P000162017-09-14+$0= $4,515,901
- Mod P000172017-09-26+$315,288= $4,831,189
- Mod P000182017-11-15+$2,828,574= $7,659,762
- Mod P000192018-02-02+$37,954= $7,697,716
- Mod P000202018-05-11+$700,000= $8,397,716
- Mod P000212018-08-01+$12,000= $8,409,716
- Mod P000222018-10-16+$328,000= $8,737,716
- Mod P000232018-11-16+$865,129= $9,602,845
- Mod P000242018-11-20+$0= $9,602,845
- Mod P000252018-12-03-$66,042= $9,536,804
- Mod P000262019-02-26+$305,797= $9,842,601
- Mod P000272019-03-04+$0= $9,842,601
- Mod P000282019-06-06+$0= $9,842,601
- Mod P000292019-09-13-$305,241= $9,537,359
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2015-09-03 | +$1,005,288 | $1,005,288 | ::IGF::OT::IGF THE CONTRACTOR SHALL DEVELOP A COMPLETE SOLUTION FOR THE PRE INBOUND EPRESCRIBING PROJECT TO IN… |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-02-22 | +$0 | $1,005,288 | ::IGF::OT::IGF THE CONTRACTOR SHALL DEVELOP A COMPLETE SOLUTION FOR THE PRE INBOUND EPRESCRIBING PROJECT TO… |
| Mod P00002· CHANGE ORDER | 2016-03-18 | +$0 | $1,005,288 | ::IGF::OT::IGF THIS MODIFICATION IS FOR A NO COST EXTENSION AND TO CHANGE THE COR |
| Mod P00003· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES) | 2016-04-01 | +$502,644 | $1,507,932 | ::IGF::OT::IGF THE PURPOSE OF THE SUBJECT MODIFICATION IS TO EXTEND THE BASE PERIOD (PERFORMANCE WORK STATEM… |
| Mod P00004· CHANGE ORDER | 2016-07-01 | +$0 | $1,507,932 | ::IGF::OT::IGF THIS MODIFICATION IS A NO COST EXTENSION |
| Mod P00006· CHANGE ORDER | 2016-07-15 | +$0 | $1,507,932 | ::IGF::OT::IGF THIS MODIFICATION EXTENDS THE PERIOD OF PERFORMANCE FOR THE PLANNING EFFORT AT NO COST. |
| Mod P00007· EXERCISE AN OPTION | 2016-07-28 | +$1,520,536 | $3,028,468 | ::IGF::OT::IGF THIS MODIFICATION EXERCISES THE DEVELOPMENT PORTIONS OF THIS EFFORT. |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-09-15 | +$0 | $3,028,468 | ::IGF::OT::IGF THIS MODIFICATION EXERCISES THE DEVELOPMENT PORTIONS OF THIS EFFORT. |
| Mod P00010· CHANGE ORDER | 2016-10-06 | +$0 | $3,028,468 | ::IGF::OT::IGF THIS MODIFICATION EXTENDS THE DELIVERY DATE FOR ONE DELIVERABLE. |
| Mod P00011· CHANGE ORDER | 2016-12-06 | +$139,984 | $3,168,452 | ::IGF::OT::IGF THIS MODIFICATION ADDS RISK VISION SUPPORT. |
| Mod P00012· EXERCISE AN OPTION | 2017-01-19 | +$1,243,796 | $4,412,248 | ::IGF::OT::IGF THIS MODIFICATION ADDS RISK VISION SUPPORT. |
| Mod P00013· CHANGE ORDER | 2017-04-12 | +$9,370 | $4,421,618 | ::IGF::OT::IGF THIS MODIFICATION ADDS TRAVEL. |
| Mod P00014· CHANGE ORDER | 2017-07-17 | +$0 | $4,421,618 | ::IGF::OT::IGF THIS MODIFICATION EXTENDS OT2 AND 6. |
| Mod P00015· CHANGE ORDER | 2017-08-28 | +$94,282 | $4,515,901 | ::IGF::OT::IGF THIS MODIFICATION EXTENDS REQUIRED RISK VISION SUPPORT. |
| Mod P00016· CHANGE ORDER | 2017-09-14 | +$0 | $4,515,901 | ::IGF::OT::IGF THIS MODIFICATION EXTENDS OT 2 |
| Mod P00017· CHANGE ORDER | 2017-09-26 | +$315,288 | $4,831,189 | ::IGF::OT::IGF THIS MODIFICATION EXTENDS OPTIONAL TASK 2 AND INCREASES THE T+M CEILING FOR OT2. |
| Mod P00018· EXERCISE AN OPTION | 2017-11-15 | +$2,828,574 | $7,659,762 | ::IGF::OT::IGF THIS MODIFICATION EXERCISES OPTIONAL TASK THREE, FOUR, SIX AND SEVEN. |
| Mod P00019· CHANGE ORDER | 2018-02-02 | +$37,954 | $7,697,716 | ::IGF::OT::IGF THIS MODIFICATION EXTENDS RISK VISION SUPPORT. |
| Mod P00020· CHANGE ORDER | 2018-05-11 | +$700,000 | $8,397,716 | ::IGF::OT::IGF THIS MODIFICATION EXTEND DEVELOPMENT. |
| Mod P00021· CHANGE ORDER | 2018-08-01 | +$12,000 | $8,409,716 | ::IGF::OT::IGF THE PURPOSE OF THIS MODIFICATION IS TO ADD A TRAVEL LOCATION FOR OPTIONAL TASK 4. |
| Mod P00022· CHANGE ORDER | 2018-10-16 | +$328,000 | $8,737,716 | ::IGF::OT::IGF THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE POP AND ADD ADDITIONAL MONEY TO OPTIONAL TA… |
| Mod P00023· EXERCISE AN OPTION | 2018-11-16 | +$865,129 | $9,602,845 | ::IGF::OT::IGF THE PURPOSE OF THIS MODIFICATION IS TO EXERCISE OPTIONAL TASKS 5, 6 AND 8. |
| Mod P00024· OTHER ADMINISTRATIVE ACTION | 2018-11-20 | +$0 | $9,602,845 | ::IGF::OT::IGF THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE FOR OPTIONAL TASK 4. |
| Mod P00025· CHANGE ORDER | 2018-12-03 | −$66,042 | $9,536,804 | ::IGF::OT::IGF THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE FUNDS UNDER CLIN 6001 AND 6002 WHICH HAVE… |
| Mod P00026· CHANGE ORDER | 2019-02-26 | +$305,797 | $9,842,601 | ::IGF::OT::IGF THE PURPOSE OF THIS MODIFICATION IS TO TO EXTEND THE PERIOD OF PERFORMANCE FOR OPTIONAL TASK… |
| Mod P00027· CHANGE ORDER | 2019-03-04 | +$0 | $9,842,601 | ::IGF::OT::IGF THE PURPOSE OF THIS MODIFICATION IS TO TO EXTEND THE PERIOD OF PERFORMANCE FOR OPTIONAL TASK… |
| Mod P00028· CHANGE ORDER | 2019-06-06 | +$0 | $9,842,601 | ::IGF::OT::IGF THE PURPOSE OF THIS MODIFICATION IS TO TO EXTEND THE PERIOD OF PERFORMANCE FOR OPTIONAL TASK… |
| Mod P00029· FUNDING ONLY ACTION | 2019-09-13 | −$305,241 | $9,537,359 | THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE FUNDS IN THE AMOUNT OF $305,234.63 |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI TXMENY1BVR37)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C10B25N00140001 | TECHNOLOGY ACQUISITION CENTER NJ (36C10B) · DA01 · IT AND TELECOM - BUSINESS APPLICATION/APPLICATION DEVELOPMENT SUPPORT SERVICES (LABOR) | $1,000 | FY2025 |
| 36C10B25D0014 | TECHNOLOGY ACQUISITION CENTER NJ (36C10B) · DA01 · IT AND TELECOM - BUSINESS APPLICATION/APPLICATION DEVELOPMENT SUPPORT SERVICES (LABOR) | $0 | FY2025 |
| 36C10B25F0030 | TECHNOLOGY ACQUISITION CENTER NJ (36C10B) · DA01 · IT AND TELECOM - BUSINESS APPLICATION/APPLICATION DEVELOPMENT SUPPORT SERVICES (LABOR) | $8,853,718 | FY2025 |
| 36C10B24F0038 | TECHNOLOGY ACQUISITION CENTER NJ (36C10B) · DA01 · IT AND TELECOM - BUSINESS APPLICATION/APPLICATION DEVELOPMENT SUPPORT SERVICES (LABOR) | $137,232,505 | FY2024 |
| 36C10B22F0016 | TECHNOLOGY ACQUISITION CENTER NJ (36C10B) · R499 · SUPPORT- PROFESSIONAL: OTHER | $5,402,689 | FY2022 |
| 36C10B21D1030 | TECHNOLOGY ACQUISITION CENTER NJ (36C10B) · DA01 · IT AND TELECOM - BUSINESS APPLICATION/APPLICATION DEVELOPMENT SUPPORT SERVICES (LABOR) | $0 | FY2021 |
Other recipients under D308 from TECHNOLOGY ACQUISITION CENTER NJ (36C10B) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C10B20C0042 | VERTICAL DESIGN INC. | TECHNOLOGY ACQUISITION CENTER NJ (36C10B) | $4,852,418 | FY2020 |
| 36C10B20N10120005 | CACI-ISS, LLC | TECHNOLOGY ACQUISITION CENTER NJ (36C10B) | $1,162,301 | FY2020 |
| 36C10B20N10250017 | INSIGNIA TECHNOLOGY SERVICES, LLC | TECHNOLOGY ACQUISITION CENTER NJ (36C10B) | $14,437,481 | FY2020 |
| 36C10B19C0030 | READY COMPUTING INC. | TECHNOLOGY ACQUISITION CENTER NJ (36C10B) | $82,455,682 | FY2019 |
| 36C10B19N10060031 | FAVOR TECHCONSULTING, LLC | TECHNOLOGY ACQUISITION CENTER NJ (36C10B) | $1,670,904 | FY2019 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA11810050053_3600_VA11811D1005_3600 · retrieved 2026-09-26.