TL SERVICES, INC.

PIID VA101F17J3111· VA Staff Offices· OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)· Y1AA · CONSTRUCTION OF OFFICE BUILDINGS· FY2017· $1,570,244 net obligations· UEI PKY8AMMMHL38· AR

Description

THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE EXCESS FUNDS IN THE AMOUNT OF $16,077.75. THE EXCESS FUNDS REMAIN AS A RESULT OF TASKS ASSOCIATED WITH INSTALLING FENCING AROUND THE MODULAR BUILDING. CONTRACTOR AND CUSTOMER ACKNOWLEDGE THE WORK WAS NOT PERFORMED. FINAL INVOICE PAID ON 1/31/2020 . THE RELEASE OF CLAIMS WAS RECEIVED ON 2/5/2020. CONTRACT PRICE CHANGED FROM $1,586,321.87 BY -$16,077.75 TO $1,570,244.12

Base award description: SEED PROJECT TASK ORDER AWARD FROM DESIGN BUILD MACC SOLICITATION.

First action · last action
2017-09-29 · 2020-04-30
Transactions
8
First transaction's obligation
$1,346,300
Base + all options value (sum of deltas)
$1,586,322
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
—
Offers received
1
SDVOSB flag on record
Yes (self-representation)
Parent IDV
VA101F17D3103
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION

Modification chain · 8 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$1,586,322$0Base award · 2017-09-29 · this action $1,346,300 · running total $1,346,300Modification P00002 · 2018-11-15 · this action $100,000 · running total $1,446,300Modification P00003 · 2019-02-11 · this action $66,938 · running total $1,513,238Modification P00004 · 2019-03-05 · this action $0 · running total $1,513,238Modification P00005 · 2019-08-22 · this action $0 · running total $1,513,238Modification P00006 · 2019-10-09 · this action $0 · running total $1,513,238Modification P00007 · 2019-11-18 · this action $73,084 · running total $1,586,322Modification P00008 · 2020-04-30 · this action -$16,078 · running total $1,570,244
  • Base2017-09-29+$1,346,300= $1,346,300
  • Mod P000022018-11-15+$100,000= $1,446,300
  • Mod P000032019-02-11+$66,938= $1,513,238
  • Mod P000042019-03-05+$0= $1,513,238
  • Mod P000052019-08-22+$0= $1,513,238
  • Mod P000062019-10-09+$0= $1,513,238
  • Mod P000072019-11-18+$73,084= $1,586,322
  • Mod P000082020-04-30-$16,078= $1,570,244
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2017-09-29+$1,346,300$1,346,300SEED PROJECT TASK ORDER AWARD FROM DESIGN BUILD MACC SOLICITATION.
Mod P00002· CHANGE ORDER2018-11-15+$100,000$1,446,300THIS CONTRACT MODIFICATION SUBJECT TO DEFINITIZATION THE PURPOSE OF THIS MODIFICATION IS TO PROVIDE WATER TIEI…
Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2019-02-11+$66,938$1,513,238THIS CONTRACT MODIFICATION DEFINITIZES CHANGE ORDER P00002. CONTRACT PRICE INCREASED CHANGED FROM $1,446,300 B…
Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2019-03-05+$0$1,513,238THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE BY FIFTY-NINE (59) CALENDAR DAYS. THE…
Mod P00005· OTHER ADMINISTRATIVE ACTION2019-08-22+$0$1,513,238THE PURPOSE OF THIS MODIFICATION IS TO UNILATERALLY ISSUE A SETTLEMENT BY DETERMINATION TO EXTEND THE PERIOD O…
Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2019-10-09+$0$1,513,238THE PURPOSE OF THIS MODIFICATION IS TO ISSUE A BILATERAL AGREEMENT TO EXTEND THE PERIOD OF PERFORMANCE AT NO A…
Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2019-11-18+$73,084$1,586,322THE PURPOSE OF THIS MODIFICATION IS TO ADJUST THE CONTRACT PRICE PURSUANT A REQUEST FOR EQUITABLE ADJUSTMENT F…
Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-04-30−$16,078$1,570,244THE PURPOSE OF THIS MODIFICATION IS TO DE-OBLIGATE EXCESS FUNDS IN THE AMOUNT OF $16,077.75. THE EXCESS FUNDS…

Related awards · 11

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI PKY8AMMMHL38)

AwardOffice · PSC / listingNet obligationsFY
36C10X26P0030SAC FREDERICK (36C10X) · 4120 · AIR CONDITIONING EQUIPMENT$62,364FY2026
36C24826F0113248-NETWORK CONTRACT OFFICE 8 (36C248) · 4130 · REFRIGERATION AND AIR CONDITIONING COMPONENTS$50,705FY2026
36C25226P0158252-NETWORK CONTRACT OFFICE 12 (36C252) · J041 · MAINT/REPAIR/REBUILD OF EQUIPMENT- REFRIGERATION, AIR CONDITIONING, AND AIR CIRCULATING EQUIPMENT$943,415FY2026
36C77625C0146252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$4,498,691FY2025
36C25225P0793252-NETWORK CONTRACT OFFICE 12 (36C252) · J047 · MAINT/REPAIR/REBUILD OF EQUIPMENT- PIPE, TUBING, HOSE, AND FITTINGS$9,175FY2025
36C77625C0067PCAC (36C776) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES$21,130,821FY2025

Other recipients under Y1AA from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)

AwardRecipientOfficeNet obligationsFY
VA101F17D3105GREENLAND ENTERPRISES, INC.OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$0FY2017
VA101F17D31093T BUSINESS GROUP LLCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$0FY2017
VA101F17D3108CMP COMMERCIAL CONSTRUCTION INCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$0FY2017
VA101F17D3107SEED JOINT VENTURE LPOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$0FY2017
VA101F17P3038G&C FAB-CON, LLCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$25,000FY2017