Award recordCONTRACT

KIEWIT INFRASTRUCTURE WEST CO.

PIID VA101F17C2879· VA Staff Offices· OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)· Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS· FY2017· $48,091,690 net obligations· UEI YSNNL4FGAQ53· WA

Description

RIVERSIDE NATIONAL CEMETERY TWO PHASE DESIGN - BUILD CONTRACT CLOSE-OUT MODIFICATION

Base award description: IGF::OT::IGF RIVERSIDE NATIONAL CEMETERY TWO PHASE DESIGN - BUILD

First action · last action
2017-03-08 · 2022-11-17
Transactions
23
First transaction's obligation
$40,439,000
Base + all options value (sum of deltas)
$48,091,690
Extent competed
FULL AND OPEN COMPETITION
Other than full & open authority
—
Set-aside
NO SET ASIDE USED.
Offers received
5
SDVOSB flag on record
No
NAICS
237990 · OTHER HEAVY AND CIVIL ENGINEERING CONSTRUCTION

Modification chain · 23 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$48,091,690$0Base award · 2017-03-08 · this action $40,439,000 · running total $40,439,000Modification P00001 · 2017-07-18 · this action $269,707 · running total $40,708,707Modification P00003 · 2018-06-29 · this action $415,975 · running total $41,124,682Modification P00004 · 2018-06-29 · this action $26,595 · running total $41,151,277Modification P00002 · 2018-08-20 · this action $5,276,790 · running total $46,428,067Modification P00006 · 2018-11-19 · this action $258,392 · running total $46,686,459Modification P00009 · 2018-11-28 · this action $35,823 · running total $46,722,282Modification P00007 · 2019-02-11 · this action $201,406 · running total $46,923,688Modification P00011 · 2019-03-07 · this action $155,017 · running total $47,078,705Modification P00010 · 2019-03-11 · this action $255,294 · running total $47,333,999Modification P00012 · 2019-07-24 · this action $0 · running total $47,333,999Modification P00021 · 2019-08-19 · this action $28,570 · running total $47,362,569Modification P00008 · 2019-09-12 · this action $21,768 · running total $47,384,337Modification P00014 · 2020-02-15 · this action -$3,457 · running total $47,380,880Modification P00016 · 2020-04-23 · this action $5,798 · running total $47,386,678Modification P00017 · 2020-04-27 · this action $13,597 · running total $47,400,274Modification P00018 · 2020-04-27 · this action $17,600 · running total $47,417,874Modification P00013 · 2020-04-30 · this action $119,644 · running total $47,537,519Modification P00020 · 2020-06-04 · this action $365,285 · running total $47,902,804Modification P00015 · 2020-08-19 · this action $6,654 · running total $47,909,458Modification P00022 · 2020-09-28 · this action $106,106 · running total $48,015,564Modification P00023 · 2021-02-24 · this action $65,863 · running total $48,081,427Modification P00024 · 2022-11-17 · this action $10,263 · running total $48,091,690
  • Base2017-03-08+$40,439,000= $40,439,000
  • Mod P000012017-07-18+$269,707= $40,708,707
  • Mod P000032018-06-29+$415,975= $41,124,682
  • Mod P000042018-06-29+$26,595= $41,151,277
  • Mod P000022018-08-20+$5,276,790= $46,428,067
  • Mod P000062018-11-19+$258,392= $46,686,459
  • Mod P000092018-11-28+$35,823= $46,722,282
  • Mod P000072019-02-11+$201,406= $46,923,688
  • Mod P000112019-03-07+$155,017= $47,078,705
  • Mod P000102019-03-11+$255,294= $47,333,999
  • Mod P000122019-07-24+$0= $47,333,999
  • Mod P000212019-08-19+$28,570= $47,362,569
  • Mod P000082019-09-12+$21,768= $47,384,337
  • Mod P000142020-02-15-$3,457= $47,380,880
  • Mod P000162020-04-23+$5,798= $47,386,678
  • Mod P000172020-04-27+$13,597= $47,400,274
  • Mod P000182020-04-27+$17,600= $47,417,874
  • Mod P000132020-04-30+$119,644= $47,537,519
  • Mod P000202020-06-04+$365,285= $47,902,804
  • Mod P000152020-08-19+$6,654= $47,909,458
  • Mod P000222020-09-28+$106,106= $48,015,564
  • Mod P000232021-02-24+$65,863= $48,081,427
  • Mod P000242022-11-17+$10,263= $48,091,690
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2017-03-08+$40,439,000$40,439,000IGF::OT::IGF RIVERSIDE NATIONAL CEMETERY TWO PHASE DESIGN - BUILD
Mod P00001· CHANGE ORDER2017-07-18+$269,707$40,708,707IGF::OT::IGF RIVERSIDE NATIONAL CEMETERY TWO PHASE DESIGN - BUILD
Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-06-29+$415,975$41,124,682IGF::OT::IGF RIVERSIDE NATIONAL CEMETERY-MODIFICATION FOR K-RATS MITIGATION FEES
Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-06-29+$26,595$41,151,277IGF::OT::IGF RIVERSIDE NATIONAL CEMETERY. ASBESTOS REMOVAL
Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-08-20+$5,276,790$46,428,067IGF::OT::IGF RIVERSIDE NATIONAL CEMETERY TWO PHASE DESIGN - BUILD IN -SCOPE MODIFICATIONS
Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-11-19+$258,392$46,686,459IGF::OT::IGF RIVERSIDE NATIONAL CEMETERY TWO PHASE DESIGN - BUILD IN -SCOPE MODIFICATIONS
Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-11-28+$35,823$46,722,282IGF::OT::IGF RIVERSIDE NATIONAL CEMETERY TWO PHASE DESIGN - BUILD IN -SCOPE MODIFICATIONS
Mod P00007· DEFINITIZE CHANGE ORDER2019-02-11+$201,406$46,923,688IGF::OT::IGF RIVERSIDE NATIONAL CEMETERY TWO PHASE DESIGN - BUILD IN -SCOPE MODIFICATIONS
Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2019-03-07+$155,017$47,078,705IGF::OT::IGF RIVERSIDE NATIONAL CEMETERY TWO PHASE DESIGN - BUILD IN -SCOPE MODIFICATIONS
Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2019-03-11+$255,294$47,333,999IGF::OT::IGF RIVERSIDE NATIONAL CEMETERY TWO PHASE DESIGN - BUILD IN -SCOPE MODIFICATIONS
Mod P00012· OTHER ADMINISTRATIVE ACTION2019-07-24+$0$47,333,999RIVERSIDE NATIONAL CEMETERY TWO PHASE DESIGN - BUILD IN -SCOPE MODIFICATIONS-TE
Mod P00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2019-08-19+$28,570$47,362,569RIVERSIDE NATIONAL CEMETERY TWO PHASE DESIGN - BUILD IN -SCOPE MODIFICATIONS
Mod P00008· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED)2019-09-12+$21,768$47,384,337RIVERSIDE NATIONAL CEMETERY TWO PHASE DESIGN - BUILD IN -SCOPE MODIFICATIONS
Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-02-15−$3,457$47,380,880RIVERSIDE NATIONAL CEMETERY TWO PHASE DESIGN - BUILD IN -SCOPE MODIFICATIONS
Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-04-23+$5,798$47,386,678RIVERSIDE NATIONAL CEMETERY TWO PHASE DESIGN - BUILD IN -SCOPE MODIFICATIONS
Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-04-27+$13,597$47,400,274RIVERSIDE NATIONAL CEMETERY TWO PHASE DESIGN - BUILD IN -SCOPE MODIFICATIONS
Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-04-27+$17,600$47,417,874IGF RIVERSIDE NATIONAL CEMETERY TWO PHASE DESIGN - BUILD IN -SCOPE MODIFICATIONS
Mod P00013· CHANGE ORDER2020-04-30+$119,644$47,537,519RIVERSIDE NATIONAL CEMETERY TWO PHASE DESIGN - BUILD IN -SCOPE MODIFICATIONS
Mod P00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-06-04+$365,285$47,902,804RIVERSIDE NATIONAL CEMETERY TWO PHASE DESIGN - BUILD IN -SCOPE MODIFICATIONS
Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-08-19+$6,654$47,909,458RIVERSIDE NATIONAL CEMETERY TWO PHASE DESIGN - BUILD IN -SCOPE MODIFICATIONS
Mod P00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-09-28+$106,106$48,015,564RIVERSIDE NATIONAL CEMETERY TWO PHASE DESIGN - BUILD IN -SCOPE MODIFICATIONS
Mod P00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-02-24+$65,863$48,081,427RIVERSIDE NATIONAL CEMETERY TWO PHASE DESIGN - BUILD IN -SCOPE MODIFICATIONS
Mod P00024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-11-17+$10,263$48,091,690RIVERSIDE NATIONAL CEMETERY TWO PHASE DESIGN - BUILD CONTRACT CLOSE-OUT MODIFICATION

Related awards · 7

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI YSNNL4FGAQ53)

AwardOffice · PSC / listingNet obligationsFY
36C78619P0493NATIONAL CEMETERY ADMIN (36C786) · 9905 · SIGNS, ADVERTISING DISPLAYS, AND IDENTIFICATION PLATES$27,685FY2019
VA101F17C2881OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS$37,687,510FY2017

Other recipients under Y1AZ from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)

AwardRecipientOfficeNet obligationsFY
36C10F26C0002SANDOW CONSTRUCTION INCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$783,108FY2026
36C10F24C0002RICHARD GROUP LLCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$42,737,190FY2024
36C10F22C0007RANDY KINDER EXCAVATING INCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$1,663,765FY2022
36C10F21C0001SPEES-HERNANDEZ JV LLCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$19,726,379FY2021
36C10F21F0004HAMILTON PACIFIC CHAMBERLAIN LLCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$406,155FY2021