Award recordCONTRACT

MCGOLDRICK CONSTRUCTION SERVICES CORPORATION

PIID VA101F16C2542· VA Staff Offices· OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)· Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS· FY2016· $10,438,011 net obligations· UEI WB1KNAULH895· TX

Description

IGF::OT::IGF FT. SAM NAT. CLOSE - OUT

Base award description: IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION - CLOSE OUT

First action · last action
2016-03-31 · 2018-07-25
Transactions
54
First transaction's obligation
$9,548,000
Base + all options value (sum of deltas)
$10,438,011
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SMALL BUSINESS SET ASIDE - TOTAL
Offers received
3
SDVOSB flag on record
Yes (self-representation)
NAICS
237990 · OTHER HEAVY AND CIVIL ENGINEERING CONSTRUCTION

Modification chain · 54 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$10,438,011$0Base award · 2016-03-31 · this action $9,548,000 · running total $9,548,000Modification P00001 · 2016-06-10 · this action $0 · running total $9,548,000Modification P00002 · 2016-06-29 · this action $0 · running total $9,548,000Modification P0004 · 2016-08-03 · this action $21,512 · running total $9,569,512Modification P00007 · 2016-08-04 · this action $22,169 · running total $9,591,681Modification P00003 · 2016-08-10 · this action $0 · running total $9,591,681Modification P00009 · 2016-09-01 · this action $30,000 · running total $9,621,681Modification P00010 · 2016-09-13 · this action $0 · running total $9,621,681Modification P00006 · 2016-09-26 · this action $19,391 · running total $9,641,072Modification P00005 · 2016-10-21 · this action $4,117 · running total $9,645,189Modification P00011 · 2016-12-01 · this action $0 · running total $9,645,189Modification P00008 · 2016-12-20 · this action -$120 · running total $9,645,069Modification P00013 · 2017-01-25 · this action $9,389 · running total $9,654,458Modification P00014 · 2017-01-30 · this action $42,900 · running total $9,697,358Modification P00016 · 2017-02-02 · this action $45,566 · running total $9,742,924Modification P00017 · 2017-02-24 · this action $25,000 · running total $9,767,924Modification P00012 · 2017-03-07 · this action $8,783 · running total $9,776,707Modification P00018 · 2017-03-07 · this action $16,879 · running total $9,793,586Modification P00019 · 2017-03-09 · this action $6,339 · running total $9,799,925Modification P00015 · 2017-03-16 · this action $14,481 · running total $9,814,406Modification P00020 · 2017-03-23 · this action $3,540 · running total $9,817,946Modification P00022 · 2017-04-03 · this action $25,000 · running total $9,842,946Modification P00024 · 2017-04-19 · this action $18,000 · running total $9,860,946Modification P00021 · 2017-05-11 · this action -$230,122 · running total $9,630,824Modification P00026 · 2017-05-16 · this action $89,329 · running total $9,720,153Modification P00023 · 2017-06-29 · this action $8,557 · running total $9,728,710Modification P00025 · 2017-06-29 · this action $84,939 · running total $9,813,649Modification P00027 · 2017-07-14 · this action $72,000 · running total $9,885,649Modification P00029 · 2017-07-21 · this action $17,951 · running total $9,903,600Modification P00030 · 2017-08-02 · this action $18,949 · running total $9,922,549Modification P00031 · 2017-08-02 · this action $11,788 · running total $9,934,337Modification P00032 · 2017-08-29 · this action $81,839 · running total $10,016,176Modification P00033 · 2017-09-11 · this action $21,467 · running total $10,037,643Modification P00028 · 2017-09-14 · this action $5,000 · running total $10,042,643Modification P00034 · 2017-09-14 · this action $2,092 · running total $10,044,735Modification P00035 · 2017-10-03 · this action $14,272 · running total $10,059,007Modification P00036 · 2017-10-04 · this action $11,642 · running total $10,070,649Modification P00037 · 2017-10-13 · this action $82,418 · running total $10,153,067Modification P00038 · 2017-11-01 · this action $7,032 · running total $10,160,099Modification P00039 · 2017-11-06 · this action $145,124 · running total $10,305,223Modification P00040 · 2017-11-30 · this action $0 · running total $10,305,223Modification P00042 · 2017-12-20 · this action $0 · running total $10,305,223Modification P00041 · 2018-01-04 · this action $0 · running total $10,305,223Modification P00043 · 2018-02-02 · this action $7,237 · running total $10,312,460Modification P00044 · 2018-02-02 · this action $9,659 · running total $10,322,119Modification P00045 · 2018-02-14 · this action $14,249 · running total $10,336,368Modification P00046 · 2018-03-01 · this action $0 · running total $10,336,368Modification P00047 · 2018-03-12 · this action $19,477 · running total $10,355,845Modification P00049 · 2018-04-05 · this action $48,466 · running total $10,404,311Modification P00050 · 2018-04-11 · this action $20,495 · running total $10,424,806Modification P00048 · 2018-04-18 · this action -$20,198 · running total $10,404,608Modification P00051 · 2018-04-24 · this action $27,565 · running total $10,432,173Modification P00052 · 2018-04-26 · this action $5,838 · running total $10,438,011Modification P00053 · 2018-07-25 · this action $0 · running total $10,438,011
  • Base2016-03-31+$9,548,000= $9,548,000
  • Mod P000012016-06-10+$0= $9,548,000
  • Mod P000022016-06-29+$0= $9,548,000
  • Mod P00042016-08-03+$21,512= $9,569,512
  • Mod P000072016-08-04+$22,169= $9,591,681
  • Mod P000032016-08-10+$0= $9,591,681
  • Mod P000092016-09-01+$30,000= $9,621,681
  • Mod P000102016-09-13+$0= $9,621,681
  • Mod P000062016-09-26+$19,391= $9,641,072
  • Mod P000052016-10-21+$4,117= $9,645,189
  • Mod P000112016-12-01+$0= $9,645,189
  • Mod P000082016-12-20-$120= $9,645,069
  • Mod P000132017-01-25+$9,389= $9,654,458
  • Mod P000142017-01-30+$42,900= $9,697,358
  • Mod P000162017-02-02+$45,566= $9,742,924
  • Mod P000172017-02-24+$25,000= $9,767,924
  • Mod P000122017-03-07+$8,783= $9,776,707
  • Mod P000182017-03-07+$16,879= $9,793,586
  • Mod P000192017-03-09+$6,339= $9,799,925
  • Mod P000152017-03-16+$14,481= $9,814,406
  • Mod P000202017-03-23+$3,540= $9,817,946
  • Mod P000222017-04-03+$25,000= $9,842,946
  • Mod P000242017-04-19+$18,000= $9,860,946
  • Mod P000212017-05-11-$230,122= $9,630,824
  • Mod P000262017-05-16+$89,329= $9,720,153
  • Mod P000232017-06-29+$8,557= $9,728,710
  • Mod P000252017-06-29+$84,939= $9,813,649
  • Mod P000272017-07-14+$72,000= $9,885,649
  • Mod P000292017-07-21+$17,951= $9,903,600
  • Mod P000302017-08-02+$18,949= $9,922,549
  • Mod P000312017-08-02+$11,788= $9,934,337
  • Mod P000322017-08-29+$81,839= $10,016,176
  • Mod P000332017-09-11+$21,467= $10,037,643
  • Mod P000282017-09-14+$5,000= $10,042,643
  • Mod P000342017-09-14+$2,092= $10,044,735
  • Mod P000352017-10-03+$14,272= $10,059,007
  • Mod P000362017-10-04+$11,642= $10,070,649
  • Mod P000372017-10-13+$82,418= $10,153,067
  • Mod P000382017-11-01+$7,032= $10,160,099
  • Mod P000392017-11-06+$145,124= $10,305,223
  • Mod P000402017-11-30+$0= $10,305,223
  • Mod P000422017-12-20+$0= $10,305,223
  • Mod P000412018-01-04+$0= $10,305,223
  • Mod P000432018-02-02+$7,237= $10,312,460
  • Mod P000442018-02-02+$9,659= $10,322,119
  • Mod P000452018-02-14+$14,249= $10,336,368
  • Mod P000462018-03-01+$0= $10,336,368
  • Mod P000472018-03-12+$19,477= $10,355,845
  • Mod P000492018-04-05+$48,466= $10,404,311
  • Mod P000502018-04-11+$20,495= $10,424,806
  • Mod P000482018-04-18-$20,198= $10,404,608
  • Mod P000512018-04-24+$27,565= $10,432,173
  • Mod P000522018-04-26+$5,838= $10,438,011
  • Mod P000532018-07-25+$0= $10,438,011
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2016-03-31+$9,548,000$9,548,000IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION - CLOSE OUT
Mod P00001· CHANGE ORDER2016-06-10+$0$9,548,000IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION
Mod P00002· CHANGE ORDER2016-06-29+$0$9,548,000IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION
Mod P0004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-08-03+$21,512$9,569,512IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION REMOVE ASBESTOS BLDG 1 CRAWL SPACE
Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-08-04+$22,169$9,591,681IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION
Mod P00003· CHANGE ORDER2016-08-10+$0$9,591,681IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION
Mod P00009· CHANGE ORDER2016-09-01+$30,000$9,621,681IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION REMOVAL OF FUEL TANK
Mod P00010· CHANGE ORDER2016-09-13+$0$9,621,681IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION SUBSTITUTE PIPE
Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-09-26+$19,391$9,641,072IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION
Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-10-21+$4,117$9,645,189IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION
Mod P00011· OTHER ADMINISTRATIVE ACTION2016-12-01+$0$9,645,189IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION
Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-12-20−$120$9,645,069IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION
Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-01-25+$9,389$9,654,458IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION
Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-01-30+$42,900$9,697,358IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION WINDOW BLDG. 1
Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-02-02+$45,566$9,742,924IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION
Mod P00017· CHANGE ORDER2017-02-24+$25,000$9,767,924IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION SEWER WORK
Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-03-07+$8,783$9,776,707IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION
Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-03-07+$16,879$9,793,586IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION WEST SIDE STORM SEWER MODIFICATION
Mod P00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-03-09+$6,339$9,799,925IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION ASBESTOS TRANSITE PIPE ALONG NURSERY ROAD
Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-03-16+$14,481$9,814,406IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION PERIMETER DRAIN CHANGES BLDG 1
Mod P00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-03-23+$3,540$9,817,946IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION - METERING RACK MODIFICATION
Mod P00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-04-03+$25,000$9,842,946IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION - PHASE 1&2 CHANGES SAN ANTONIO BLVD
Mod P00024· CHANGE ORDER2017-04-19+$18,000$9,860,946IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION - URGENT WATER LEAK
Mod P00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-05-11−$230,122$9,630,824IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION - CREDIT -$230,112.00
Mod P00026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-05-16+$89,329$9,720,153IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION - IRRIGATION AT BRIDGE
Mod P00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-06-29+$8,557$9,728,710IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION -SPRAYED INTERIOR CLAY WALL INSULATION FOR B-1001
Mod P00025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-06-29+$84,939$9,813,649IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION - B-1001 ROOF REPAIRS
Mod P00027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-07-14+$72,000$9,885,649IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION - IRRIGATION AT BRIDGE
Mod P00029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-07-21+$17,951$9,903,600IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION - B-1001 STRUCTURAL REPAIRS 3 CHANGES IN ONE MOD.
Mod P00030· CHANGE ORDER2017-08-02+$18,949$9,922,549IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION - INSTALL SUMP PUMP FOR B-1001 AND ASSOCIATED PIPING, CONTRO…
Mod P00031· CHANGE ORDER2017-08-02+$11,788$9,934,337IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION - EXPLORATORY AND REMOVAL OF OLD IRRIGATION PIPING.
Mod P00032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-08-29+$81,839$10,016,176IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION - B-1001 STRUCTURAL REPAIRS 3 CHANGES IN ONE MOD.
Mod P00033· CHANGE ORDER2017-09-11+$21,467$10,037,643IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION - RELOCATE B-1001 SANITARY SEWER PIPE.
Mod P00028· CHANGE ORDER2017-09-14+$5,000$10,042,643IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION - PROVIDE GROUND CABLE ALONG OVERPASS NURSERY RD
Mod P00034· CHANGE ORDER2017-09-14+$2,092$10,044,735IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION - PROVIDE GROUND CABLE ALONG NURSERY RD OVERPASS.
Mod P00035· CHANGE ORDER2017-10-03+$14,272$10,059,007IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION - INSTALL 6-INCH WATER LINE FOR B-1001, WATERING STATIONS AN…
Mod P00036· CHANGE ORDER2017-10-04+$11,642$10,070,649IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION - CHANGES TO FOUNDATION DRAINAGE AND BOILER FLUE STACKS.
Mod P00037· CHANGE ORDER2017-10-13+$82,418$10,153,067IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION - OVERPASS CURB CORRECTIONS AND BLACK BASE OPTION.
Mod P00038· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-11-01+$7,032$10,160,099IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION -RELOCATE DOMESTIC WATER SUPPLY FOR JOINT BASE GOLF FACILITY
Mod P00039· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-11-06+$145,124$10,305,223IGF::OT::IGF FT. SAM NAT. CEMETERY - CONSTRUCTION - OVERPASS CURB CORRECTIONS AND BLACK BASE OPTION.
Mod P00040· CHANGE ORDER2017-11-30+$0$10,305,223IGF::OT::IGF FT. SAM NAT. CEMETERY - DE-SCOPE GOLF COURSE CURBING
Mod P00042· CHANGE ORDER2017-12-20+$0$10,305,223IGF::OT::IGF FT. SAM NAT. CEMETERY -59 DAY EXTENSION
Mod P00041· CHANGE ORDER2018-01-04+$0$10,305,223IGF::OT::IGF FT. SAM NAT. CEMETERY - UNILATERAL CHANGE ORDER TO START WORK ON STRIPING, SPRINKLER IRRIGATION&T…
Mod P00043· CHANGE ORDER2018-02-02+$7,237$10,312,460IGF::OT::IGF FT. SAM NAT. CEMETERY - RETAINING WALL CONFLICTS WITH EXISTING PIPING AT WEST SIDE OF UNDERPASS.
Mod P00044· CHANGE ORDER2018-02-02+$9,659$10,322,119IGF::OT::IGF FT. SAM NAT. CEMETERY - STONE WALL REINFORCING AT FRONT ENTRANCE.
Mod P00045· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-02-14+$14,249$10,336,368IGF::OT::IGF FT. SAM NAT. CEMETERY - PANEL/PUMP/FENCE
Mod P00046· CHANGE ORDER2018-03-01+$0$10,336,368IGF::OT::IGF FT. SAM NAT. CEMETERY -NON COMPENSATORY TIME EXTENSION TO COMPLETE WORK. WEATHER DELAY
Mod P00047· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-03-12+$19,477$10,355,845IGF::OT::IGF FT. SAM NAT. CEMETERY -DIFFERING SITE CONDITIONS REMOVE STRUCTURAL FOOTING
Mod P00049· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-04-05+$48,466$10,404,311IGF::OT::IGF FT. SAM NAT. CEMETERY -EXTENDED OVERHEAD
Mod P00050· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-04-11+$20,495$10,424,806IGF::OT::IGF FT. SAM NAT. CEMETERY -DEFINITIZE MOD P00040&P00040
Mod P00048· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-04-18−$20,198$10,404,608IGF::OT::IGF FT. SAM NAT. CEMETERY -CREDIT
Mod P00051· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-04-24+$27,565$10,432,173IGF::OT::IGF FT. SAM NAT. CEMETERY ADA SIDEWALK/BOLLARDS/UTILITY
Mod P00052· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-04-26+$5,838$10,438,011IGF::OT::IGF FT. SAM NAT. CEMETERY BOND PAYMENT
Mod P00053· CLOSE OUT2018-07-25+$0$10,438,011IGF::OT::IGF FT. SAM NAT. CLOSE - OUT

Related awards · 11

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI WB1KNAULH895)

AwardOffice · PSC / listingNet obligationsFY
36C25724C0018257-NETWORK CONTRACT OFFICE 17 (36C257) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES$2,170,321FY2024
36C25723C0058257-NETWORK CONTRACT OFFICE 17 (36C257) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES$3,052,249FY2023
36C25723C0017257-NETWORK CONTRACT OFFICE 17 (36C257) · Z2DZ · REPAIR OR ALTERATION OF OTHER HOSPITAL BUILDINGS$1,594,869FY2023
36C25723P0053257-NETWORK CONTRACT OFFICE 17 (36C257) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES$122,260FY2023
36C25723C0001257-NETWORK CONTRACT OFFICE 17 (36C257) · Z2PZ · REPAIR OR ALTERATION OF OTHER NON-BUILDING FACILITIES$1,341,012FY2023
36C25722P0598257-NETWORK CONTRACT OFFICE 17 (36C257) · Z2NE · REPAIR OR ALTERATION OF WATER SUPPLY FACILITIES$73,700FY2022

Other recipients under Y1AZ from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)

AwardRecipientOfficeNet obligationsFY
36C10F26C0002SANDOW CONSTRUCTION INCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$783,108FY2026
36C10F24C0002RICHARD GROUP LLCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$42,737,190FY2024
36C10F22C0007RANDY KINDER EXCAVATING INCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$1,663,765FY2022
36C10F21C0001SPEES-HERNANDEZ JV LLCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$19,726,379FY2021
36C10F21F0004HAMILTON PACIFIC CHAMBERLAIN LLCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$406,155FY2021

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA101F16C2542_3600_-NONE-_-NONE- · retrieved 2026-09-26.