Description
IGF::OT::IGF PROVIDE RULE 4 FILE PREPARATION AND ASSISTANCE FOR CBCA APPEAL CLAIMS.
Base award description: IGF::OT::IGF BASE PLUS 1 OPTION YEAR TO PROVIDE CONSTRUCTION MANAGEMENT SERVICES FOR THREE MONTH PERIOD BEGINNING 10/01/2014.
Modification chain · 12 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2014-09-30+$7,084,727= $7,084,727
- Mod P000012014-11-12+$69,691= $7,154,418
- Mod P000022014-12-05+$155,503= $7,309,921
- Mod P000032015-01-06+$0= $7,309,921
- Mod P000042015-08-05-$125,117= $7,184,803
- Mod P000052015-09-17+$1,434,786= $8,619,589
- Mod P000062015-11-04+$6,508= $8,626,097
- Mod P000072016-03-15+$0= $8,626,097
- Mod P000082016-03-22+$0= $8,626,097
- Mod P000092016-10-18-$1,611,656= $7,014,441
- Mod P000102016-10-25+$1,611,656= $8,626,097
- Mod P000112016-11-30-$1,611,656= $7,014,441
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2014-09-30 | +$7,084,727 | $7,084,727 | IGF::OT::IGF BASE PLUS 1 OPTION YEAR TO PROVIDE CONSTRUCTION MANAGEMENT SERVICES FOR THREE MONTH PERIOD BEGIN… |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-11-12 | +$69,691 | $7,154,418 | IGF::OT::IGF IMPLEMENT PROLOG PHASE 5A. |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-12-05 | +$155,503 | $7,309,921 | IGF::OT::IGF PROVIDE RULE 4 FILE PREPARATION AND ASSISTANCE FOR CBCA APPEAL CLAIMS. |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-01-06 | +$0 | $7,309,921 | IGF::OT::IGF NO COST MODIFICATION (SA) TO INCLUDE VA IT SECURITY/PRIVACY LANGUAGE INTO THE ORDER. |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-08-05 | −$125,117 | $7,184,803 | IGF::OT::IGF PROVIDE RULE 4 FILE PREPARATION AND ASSISTANCE FOR CBCA APPEAL CLAIMS. |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-17 | +$1,434,786 | $8,619,589 | IGF::OT::IGF PROVIDE RULE 4 FILE PREPARATION AND ASSISTANCE FOR CBCA APPEAL CLAIMS. |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-11-04 | +$6,508 | $8,626,097 | IGF::OT::IGF PROVIDE RULE 4 FILE PREPARATION AND ASSISTANCE FOR CBCA APPEAL CLAIMS. |
| Mod P00007· OTHER ADMINISTRATIVE ACTION | 2016-03-15 | +$0 | $8,626,097 | IGF::OT::IGF PROVIDE RULE 4 FILE PREPARATION AND ASSISTANCE FOR CBCA APPEAL CLAIMS. |
| Mod P00008· OTHER ADMINISTRATIVE ACTION | 2016-03-22 | +$0 | $8,626,097 | IGF::OT::IGF PROVIDE RULE 4 FILE PREPARATION AND ASSISTANCE FOR CBCA APPEAL CLAIMS. |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-10-18 | −$1,611,656 | $7,014,441 | IGF::OT::IGF PROVIDE RULE 4 FILE PREPARATION AND ASSISTANCE FOR CBCA APPEAL CLAIMS. |
| Mod P00010· OTHER ADMINISTRATIVE ACTION | 2016-10-25 | +$1,611,656 | $8,626,097 | IGF::OT::IGF PROVIDE RULE 4 FILE PREPARATION AND ASSISTANCE FOR CBCA APPEAL CLAIMS. |
| Mod P00011· CLOSE OUT | 2016-11-30 | −$1,611,656 | $7,014,441 | IGF::OT::IGF PROVIDE RULE 4 FILE PREPARATION AND ASSISTANCE FOR CBCA APPEAL CLAIMS. |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI H2RGSKWXKHQ5)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C10F20N0010 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · C214 · ARCHITECT AND ENGINEERING- GENERAL: MANAGEMENT ENGINEERING | $36,243 | FY2020 |
| VA101F16J2721 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · C214 · ARCHITECT AND ENGINEERING- GENERAL: MANAGEMENT ENGINEERING | $94,845 | FY2016 |
| VA101F15J0360 | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT · R425 · SUPPORT- PROFESSIONAL: ENGINEERING/TECHNICAL | $16,292 | FY2015 |
| VA101F15J0361 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · C214 · ARCHITECT AND ENGINEERING- GENERAL: MANAGEMENT ENGINEERING | $28,079 | FY2015 |
| VA101F15F0169 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · R425 · SUPPORT- PROFESSIONAL: ENGINEERING/TECHNICAL | $423,939 | FY2015 |
| VA101F14A0006A | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · C214 · ARCHITECT AND ENGINEERING- GENERAL: MANAGEMENT ENGINEERING | $0 | FY2015 |
Other recipients under R425 from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C10F26F0009 | VALI COOPER INTERNATIONAL LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $658,396 | FY2026 |
| 36C10F26N0018 | SA3 CONSTRUCTION MANAGEMENT LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $473,328 | FY2026 |
| 36C10F26N0017 | SSPC LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $1,915,692 | FY2026 |
| 36C10F25C0009 | GOLDEN WOLF, LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $5,332,064 | FY2025 |
| 36C10F25C0010 | GUIDON DESIGN INC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $5,964,155 | FY2025 |