Description
DESIGN-BUILD OF NEW NATIONAL CEMETERY SETTLEMENT BY DETERMINATION
Base award description: DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF
Modification chain · 78 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2014-09-30+$28,907,000= $28,907,000
- Mod P000032016-01-28+$6,292= $28,913,292
- Mod P000012016-03-17+$34,684= $28,947,976
- Mod P000022016-03-21+$23,450= $28,971,426
- Mod P000042016-03-25+$45,076= $29,016,502
- Mod P000052016-03-25+$2,500= $29,019,002
- Mod P000062016-04-04+$2,382= $29,021,384
- Mod P000072016-04-05+$2,151= $29,023,535
- Mod P000082016-04-08+$10,002= $29,033,537
- Mod P000092016-05-25+$98,000= $29,131,537
- Mod P000102016-05-31+$96,740= $29,228,277
- Mod P000112016-06-09+$44,320= $29,272,597
- Mod P000122016-06-09+$30,118= $29,302,715
- Mod P000132016-06-13+$12,878= $29,315,593
- Mod P000142016-07-13+$12,963= $29,328,556
- Mod P000152016-07-14+$30,000= $29,358,556
- Mod P000162016-07-21+$9,675= $29,368,231
- Mod P000172016-07-22+$25,000= $29,393,231
- Mod P000182016-07-25+$3,543= $29,396,774
- Mod P000192016-08-10+$16,432= $29,413,206
- Mod P000202016-08-11+$51,881= $29,465,087
- Mod P000212016-08-11+$8,121= $29,473,208
- Mod P000222016-08-29+$4,389= $29,477,597
- Mod P000232016-09-16+$11,553= $29,489,150
- Mod P000242016-09-16+$21,978= $29,511,128
- Mod P000252016-09-19+$3,934= $29,515,062
- Mod P000262016-09-20+$10,235= $29,525,297
- Mod P000272016-09-20+$11,941= $29,537,238
- Mod P000282016-09-20+$8,629= $29,545,867
- Mod P000292016-09-20+$3,547= $29,549,414
- Mod P000302016-09-21+$2,571= $29,551,985
- Mod P000322016-09-22+$6,611= $29,558,596
- Mod P000312016-09-26+$5,416= $29,564,012
- Mod P000332016-09-29+$6,698= $29,570,710
- Mod P000342016-10-04+$7,257= $29,577,967
- Mod P000352016-11-04+$54,708= $29,632,675
- Mod P000362016-11-30+$14,723= $29,647,398
- Mod P000382016-12-15+$24,139= $29,671,537
- Mod P000392016-12-15+$46,299= $29,717,836
- Mod P000402016-12-15+$18,208= $29,736,044
- Mod P000412016-12-21+$13,037= $29,749,081
- Mod P000422016-12-21+$7,619= $29,756,700
- Mod P000372016-12-22+$51,345= $29,808,045
- Mod P000432016-12-22+$44= $29,808,089
- Mod P000442016-12-22+$11,977= $29,820,066
- Mod P000452016-12-22+$12,713= $29,832,779
- Mod P000462016-12-22+$8,932= $29,841,711
- Mod P000472016-12-22+$2,840= $29,844,551
- Mod P000482016-12-23+$23,606= $29,868,157
- Mod P000492016-12-23+$15,758= $29,883,915
- Mod P000502017-01-20+$10,951= $29,894,866
- Mod P000512017-01-20+$18,225= $29,913,091
- Mod P000522017-02-01+$5,757= $29,918,848
- Mod P000532017-02-23+$12,135= $29,930,983
- Mod P000542017-03-08+$1,374= $29,932,357
- Mod P000552017-03-08+$15,327= $29,947,684
- Mod P000562017-03-08+$74,825= $30,022,509
- Mod P000572017-04-11+$23,567= $30,046,076
- Mod P000582017-04-27+$4,769= $30,050,845
- Mod P000592017-04-27+$22,215= $30,073,060
- Mod P000602017-05-16-$648= $30,072,412
- Mod P000612017-06-08+$37,428= $30,109,840
- Mod P000622017-06-09+$66,824= $30,176,664
- Mod P000632017-07-11+$0= $30,176,664
- Mod P000642017-07-21+$21,284= $30,197,948
- Mod P000652017-07-25+$32,820= $30,230,768
- Mod P000662017-07-25+$0= $30,230,768
- Mod P000672017-08-29+$80,135= $30,310,903
- Mod P000682017-08-29+$5,085= $30,315,988
- Mod P000692017-08-29+$16,124= $30,332,112
- Mod P000702017-09-20+$4,000= $30,336,112
- Mod P000712018-02-06+$285,975= $30,622,087
- Mod P000722018-12-11+$0= $30,622,087
- Mod P000742018-12-11+$952= $30,623,039
- Mod P000752018-12-11+$6,656= $30,629,695
- Mod P000772020-07-27+$123,274= $30,752,969
- Mod P000782020-07-27+$20,676= $30,773,645
- Mod P000762020-09-30-$25,616= $30,748,029
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2014-09-30 | +$28,907,000 | $28,907,000 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-01-28 | +$6,292 | $28,913,292 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF ABANDON EXISTING WELL NOT SHOWN ON DRAWINGS, PER RFI #50. |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-03-17 | +$34,684 | $28,947,976 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-03-21 | +$23,450 | $28,971,426 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-03-25 | +$45,076 | $29,016,502 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00005· CHANGE ORDER | 2016-03-25 | +$2,500 | $29,019,002 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-04-04 | +$2,382 | $29,021,384 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-04-05 | +$2,151 | $29,023,535 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-04-08 | +$10,002 | $29,033,537 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00009· CHANGE ORDER | 2016-05-25 | +$98,000 | $29,131,537 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-05-31 | +$96,740 | $29,228,277 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-06-09 | +$44,320 | $29,272,597 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-06-09 | +$30,118 | $29,302,715 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-06-13 | +$12,878 | $29,315,593 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-07-13 | +$12,963 | $29,328,556 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00015· CHANGE ORDER | 2016-07-14 | +$30,000 | $29,358,556 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-07-21 | +$9,675 | $29,368,231 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00017· CHANGE ORDER | 2016-07-22 | +$25,000 | $29,393,231 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-07-25 | +$3,543 | $29,396,774 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-08-10 | +$16,432 | $29,413,206 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-08-11 | +$51,881 | $29,465,087 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-08-11 | +$8,121 | $29,473,208 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-08-29 | +$4,389 | $29,477,597 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-09-16 | +$11,553 | $29,489,150 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-09-16 | +$21,978 | $29,511,128 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-09-19 | +$3,934 | $29,515,062 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-09-20 | +$10,235 | $29,525,297 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-09-20 | +$11,941 | $29,537,238 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00028· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-09-20 | +$8,629 | $29,545,867 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-09-20 | +$3,547 | $29,549,414 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00030· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-09-21 | +$2,571 | $29,551,985 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00032· CHANGE ORDER | 2016-09-22 | +$6,611 | $29,558,596 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-09-26 | +$5,416 | $29,564,012 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00033· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-09-29 | +$6,698 | $29,570,710 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00034· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-10-04 | +$7,257 | $29,577,967 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00035· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-11-04 | +$54,708 | $29,632,675 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00036· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-11-30 | +$14,723 | $29,647,398 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00038· DEFINITIZE CHANGE ORDER | 2016-12-15 | +$24,139 | $29,671,537 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00039· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-12-15 | +$46,299 | $29,717,836 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00040· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-12-15 | +$18,208 | $29,736,044 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00041· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-12-21 | +$13,037 | $29,749,081 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00042· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-12-21 | +$7,619 | $29,756,700 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00037· DEFINITIZE CHANGE ORDER | 2016-12-22 | +$51,345 | $29,808,045 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00043· DEFINITIZE CHANGE ORDER | 2016-12-22 | +$44 | $29,808,089 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00044· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-12-22 | +$11,977 | $29,820,066 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00045· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-12-22 | +$12,713 | $29,832,779 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00046· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-12-22 | +$8,932 | $29,841,711 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00047· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-12-22 | +$2,840 | $29,844,551 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00048· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-12-23 | +$23,606 | $29,868,157 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00049· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-12-23 | +$15,758 | $29,883,915 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00050· DEFINITIZE CHANGE ORDER | 2017-01-20 | +$10,951 | $29,894,866 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00051· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-01-20 | +$18,225 | $29,913,091 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00052· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-02-01 | +$5,757 | $29,918,848 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00053· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-02-23 | +$12,135 | $29,930,983 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00054· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-03-08 | +$1,374 | $29,932,357 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00055· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-03-08 | +$15,327 | $29,947,684 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00056· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-03-08 | +$74,825 | $30,022,509 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00057· CHANGE ORDER | 2017-04-11 | +$23,567 | $30,046,076 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00058· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-04-27 | +$4,769 | $30,050,845 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00059· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-04-27 | +$22,215 | $30,073,060 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF |
| Mod P00060· DEFINITIZE CHANGE ORDER | 2017-05-16 | −$648 | $30,072,412 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF THIS SUPPLEMENTAL AGREEMENT DEFINITIZES CHANGE ORDER P00005… |
| Mod P00061· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-06-08 | +$37,428 | $30,109,840 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF SUPPLEMENTAL AGREEMENT P00061 TO INSTALL CONCRETE PAVING AN… |
| Mod P00062· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-06-09 | +$66,824 | $30,176,664 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF SUPPLEMENTAL AGREEMENT P00062 IS TO ASPHALT THE GRAVEL SERV… |
| Mod P00063· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-07-11 | +$0 | $30,176,664 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF SUPPLEMENTAL AGREEMENT P00063 IS TO SUBSTITUTE FIVE (5) SUG… |
| Mod P00064· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-07-21 | +$21,284 | $30,197,948 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF SUPPLEMENTAL AGREEMENT P00064 IS TO REMOVE AND DISPOSE OF L… |
| Mod P00065· DEFINITIZE CHANGE ORDER | 2017-07-25 | +$32,820 | $30,230,768 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF SUPPLEMENTAL AGREEMENT P00065 IS TO DEFINITIZE CHANGE ORDER… |
| Mod P00066· CHANGE ORDER | 2017-07-25 | +$0 | $30,230,768 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF CHANGE ORDER P00066 DELETES THE REQUIREMENT FOR A SYNTHETIC… |
| Mod P00067· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-08-29 | +$80,135 | $30,310,903 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF SUPPLEMENTAL AGREEMENT P00067 - ADDED SOD (3 AREAS) AND STO… |
| Mod P00068· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-08-29 | +$5,085 | $30,315,988 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF SUPPLEMENTAL AGREEMENT P00068 - DEDICATION PLAQUE AND CHAIR… |
| Mod P00069· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-08-29 | +$16,124 | $30,332,112 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF SUPPLEMENTAL AGREEMENT P00069 - MOW 65 ACRES |
| Mod P00070· CHANGE ORDER | 2017-09-20 | +$4,000 | $30,336,112 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF CHANGE ORDER P00070 RELOCATE FWS IN CRYPT FIELD 4 AND ASSOC… |
| Mod P00071· DEFINITIZE CHANGE ORDER | 2018-02-06 | +$285,975 | $30,622,087 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF SETTLEMENT BY DETERMINATION |
| Mod P00072· DEFINITIZE CHANGE ORDER | 2018-12-11 | +$0 | $30,622,087 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF SETTLEMENT BY DETERMINATION |
| Mod P00074· DEFINITIZE CHANGE ORDER | 2018-12-11 | +$952 | $30,623,039 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF SETTLEMENT BY DETERMINATION |
| Mod P00075· DEFINITIZE CHANGE ORDER | 2018-12-11 | +$6,656 | $30,629,695 | DESIGN-BUILD OF NEW NATIONAL CEMETERY IGF::OT::IGF SETTLEMENT BY DETERMINATION |
| Mod P00077· OTHER ADMINISTRATIVE ACTION | 2020-07-27 | +$123,274 | $30,752,969 | DESIGN-BUILD OF NEW NATIONAL CEMETERY SETTLEMENT BY DETERMINATION |
| Mod P00078· OTHER ADMINISTRATIVE ACTION | 2020-07-27 | +$20,676 | $30,773,645 | DESIGN-BUILD OF NEW NATIONAL CEMETERY SETTLEMENT BY DETERMINATION |
| Mod P00076· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-09-30 | −$25,616 | $30,748,029 | DESIGN-BUILD OF NEW NATIONAL CEMETERY SETTLEMENT BY DETERMINATION |
Related awards · 5
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other recipients under Y1PC from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C10F26C0005 | GC & V CONSTRUCTION LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $59,890,000 | FY2026 |
| 36C10F25C0007 | HAMILTON PACIFIC CHAMBERLAIN LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $637,437 | FY2025 |
| 36C10F24C0007 | SEABEE CONSTRUCTION, INC. | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $79,106,191 | FY2024 |
| 36C10F24C0001 | RBVETCO, LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $38,940,668 | FY2024 |
| 36C10F23C0008 | SGC SERVICES 2, LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $42,010,850 | FY2023 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA101F14C0038_3600_-NONE-_-NONE- · retrieved 2026-09-26.