Award recordCONTRACT

C & C CONTRACTORS LLC

PIID VA101F14C0035· VA Staff Offices· OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)· Y1PC · CONSTRUCTION OF UNIMPROVED REAL PROPERTY (LAND)· FY2014· $31,132,413 net obligations· UEI Z6ZVR3MXC9L4· AL

Description

IGF::OT::IGF CONTRACT CLOSE OUT

Base award description: CONSTRUCTION OF NEW NATIONAL CEMETERY IGF::OT::IGF

First action · last action
2014-09-30 · 2019-04-16
Transactions
165
First transaction's obligation
$26,800,443
Base + all options value (sum of deltas)
$31,143,507
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
5
SDVOSB flag on record
Yes (self-representation)
NAICS
237990 · OTHER HEAVY AND CIVIL ENGINEERING CONSTRUCTION

Modification chain · 165 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$31,132,413$0Base award · 2014-09-30 · this action $26,800,443 · running total $26,800,443Modification P00001 · 2015-01-26 · this action $17,531 · running total $26,817,974Modification P00002 · 2015-05-14 · this action $29,309 · running total $26,847,283Modification P00003 · 2015-05-14 · this action $39,310 · running total $26,886,593Modification P00004 · 2015-05-28 · this action $0 · running total $26,886,593Modification P00005 · 2015-05-28 · this action $81,065 · running total $26,967,658Modification P00006 · 2015-05-28 · this action $3,266 · running total $26,970,924Modification P00007 · 2015-07-06 · this action $78,437 · running total $27,049,361Modification P00008 · 2015-07-08 · this action $39,632 · running total $27,088,993Modification P00009 · 2015-07-14 · this action $28,122 · running total $27,117,115Modification P00010 · 2015-08-03 · this action $11,772 · running total $27,128,887Modification P00011 · 2015-08-03 · this action $38,528 · running total $27,167,415Modification P00012 · 2015-08-05 · this action $80,500 · running total $27,247,915Modification P00013 · 2015-08-05 · this action $11,536 · running total $27,259,451Modification P00014 · 2015-08-25 · this action $6,644 · running total $27,266,095Modification P00015 · 2015-08-25 · this action $70,000 · running total $27,336,095Modification P00016 · 2015-09-02 · this action $11,364 · running total $27,347,459Modification P00017 · 2015-11-18 · this action $197,917 · running total $27,545,376Modification P00018 · 2015-12-16 · this action $3,500 · running total $27,548,876Modification P00019 · 2016-01-25 · this action $0 · running total $27,548,876Modification P00020 · 2016-02-08 · this action $6,257 · running total $27,555,133Modification P00021 · 2016-02-16 · this action $18,933 · running total $27,574,066Modification P00022 · 2016-02-22 · this action $96,565 · running total $27,670,631Modification P00023 · 2016-02-22 · this action $4,302 · running total $27,674,933Modification P00024 · 2016-02-22 · this action $5,500 · running total $27,680,433Modification P00025 · 2016-03-04 · this action $15,500 · running total $27,695,933Modification P00026 · 2016-03-04 · this action $21,661 · running total $27,717,594Modification P00027 · 2016-03-09 · this action $22,700 · running total $27,740,294Modification P00028 · 2016-03-28 · this action $99,231 · running total $27,839,525Modification P00029 · 2016-03-30 · this action $61,099 · running total $27,900,624Modification P00030 · 2016-04-21 · this action $98,488 · running total $27,999,112Modification P00031 · 2016-04-28 · this action $16,535 · running total $28,015,647Modification P00032 · 2016-04-28 · this action $8,044 · running total $28,023,691Modification P00033 · 2016-04-29 · this action -$66,496 · running total $27,957,195Modification P00034 · 2016-05-12 · this action $39,339 · running total $27,996,534Modification P00035 · 2016-06-10 · this action $88,251 · running total $28,084,785Modification P00036 · 2016-06-21 · this action $88,214 · running total $28,172,999Modification P00037 · 2016-06-23 · this action $1,612 · running total $28,174,611Modification P00038 · 2016-06-28 · this action $1,695 · running total $28,176,306Modification P00039 · 2016-06-30 · this action $36,120 · running total $28,212,426Modification P00040 · 2016-07-11 · this action $15,293 · running total $28,227,719Modification P00041 · 2016-07-25 · this action $17,584 · running total $28,245,303Modification P00042 · 2016-07-26 · this action $76,752 · running total $28,322,055Modification P00043 · 2016-07-26 · this action $43,960 · running total $28,366,015Modification P00044 · 2016-08-04 · this action $2,562 · running total $28,368,577Modification P00045 · 2016-08-04 · this action $4,240 · running total $28,372,817Modification P00046 · 2016-09-19 · this action $7,614 · running total $28,380,431Modification P00047 · 2016-09-19 · this action $9,259 · running total $28,389,690Modification P00048 · 2016-09-20 · this action $73,210 · running total $28,462,900Modification P00049 · 2016-10-05 · this action $12,505 · running total $28,475,405Modification P00050 · 2016-10-06 · this action $7,044 · running total $28,482,449Modification P00051 · 2016-10-19 · this action $15,701 · running total $28,498,150Modification P00052 · 2016-10-20 · this action $0 · running total $28,498,150Modification P00053 · 2016-10-20 · this action $8,181 · running total $28,506,331Modification P00054 · 2016-11-02 · this action $40,981 · running total $28,547,312Modification P00055 · 2016-11-09 · this action -$48,000 · running total $28,499,312Modification P00056 · 2016-11-29 · this action $10,172 · running total $28,509,484Modification P00057 · 2016-12-07 · this action $13,184 · running total $28,522,668Modification P00058 · 2016-12-08 · this action $90,000 · running total $28,612,668Modification P00059 · 2016-12-15 · this action $54,883 · running total $28,667,551Modification P00060 · 2017-01-03 · this action $33,200 · running total $28,700,751Modification P00061 · 2017-01-05 · this action $13,696 · running total $28,714,447Modification P00062 · 2017-01-05 · this action $3,179 · running total $28,717,626Modification P00063 · 2017-01-05 · this action $1,171 · running total $28,718,797Modification P00064 · 2017-01-10 · this action $8,392 · running total $28,727,189Modification P00065 · 2017-01-11 · this action $2,287 · running total $28,729,476Modification P00066 · 2017-01-17 · this action $2,953 · running total $28,732,429Modification P00067 · 2017-01-19 · this action $33,668 · running total $28,766,097Modification P00069 · 2017-01-24 · this action $18,346 · running total $28,784,443Modification P00070 · 2017-01-26 · this action $13,699 · running total $28,798,142Modification P00071 · 2017-02-06 · this action $3,798 · running total $28,801,940Modification P00072 · 2017-02-10 · this action $21,843 · running total $28,823,783Modification P00068 · 2017-02-14 · this action -$118,724 · running total $28,705,059Modification P00074 · 2017-02-17 · this action $14,095 · running total $28,719,154Modification P00075 · 2017-02-21 · this action $8,410 · running total $28,727,564Modification P00073 · 2017-02-22 · this action $24,895 · running total $28,752,459Modification P00076 · 2017-02-22 · this action $4,003 · running total $28,756,462Modification P00077 · 2017-02-23 · this action $2,001 · running total $28,758,463Modification P00078 · 2017-02-24 · this action $1,450 · running total $28,759,913Modification P00079 · 2017-03-02 · this action $9,480 · running total $28,769,393Modification P00080 · 2017-03-02 · this action $24,964 · running total $28,794,357Modification P00081 · 2017-03-06 · this action $14,036 · running total $28,808,393Modification P00082 · 2017-03-07 · this action $21,188 · running total $28,829,581Modification P00083 · 2017-03-07 · this action $21,050 · running total $28,850,631Modification P00084 · 2017-03-09 · this action $28,781 · running total $28,879,412Modification P00085 · 2017-03-09 · this action $68,613 · running total $28,948,025Modification P00086 · 2017-03-15 · this action -$31,365 · running total $28,916,660Modification P00087 · 2017-03-15 · this action $15,086 · running total $28,931,746Modification P00088 · 2017-03-16 · this action $14,907 · running total $28,946,653Modification P00090 · 2017-03-31 · this action $13,977 · running total $28,960,630Modification P00089 · 2017-04-05 · this action $0 · running total $28,960,630Modification P00091 · 2017-04-06 · this action $19,172 · running total $28,979,802Modification P00092 · 2017-04-07 · this action $31,880 · running total $29,011,682Modification P00094 · 2017-04-24 · this action $4,417 · running total $29,016,099Modification P00095 · 2017-04-27 · this action $26,869 · running total $29,042,968Modification P00096 · 2017-05-01 · this action $22,122 · running total $29,065,090Modification P00097 · 2017-05-02 · this action $5,392 · running total $29,070,482Modification P00098 · 2017-05-03 · this action $11,607 · running total $29,082,089Modification P00099 · 2017-05-04 · this action $1,960 · running total $29,084,049Modification P00093 · 2017-05-10 · this action $140,000 · running total $29,224,049Modification P00100 · 2017-05-10 · this action $829 · running total $29,224,878Modification P00101 · 2017-05-10 · this action $6,080 · running total $29,230,958Modification P00102 · 2017-05-10 · this action $18,649 · running total $29,249,607Modification P00103 · 2017-05-10 · this action $2,677 · running total $29,252,284Modification P00104 · 2017-05-11 · this action $5,262 · running total $29,257,546Modification P00105 · 2017-05-19 · this action $11,202 · running total $29,268,748Modification P00106 · 2017-06-06 · this action $62,007 · running total $29,330,755Modification P00107 · 2017-06-07 · this action $24,469 · running total $29,355,224Modification P00108 · 2017-06-08 · this action $39,137 · running total $29,394,361Modification P00109 · 2017-06-12 · this action $0 · running total $29,394,361Modification P00110 · 2017-06-13 · this action $8,899 · running total $29,403,260Modification P00111 · 2017-06-13 · this action $59,181 · running total $29,462,441Modification P00112 · 2017-06-13 · this action $2,151 · running total $29,464,592Modification P00113 · 2017-06-13 · this action $12,240 · running total $29,476,832Modification P00114 · 2017-06-15 · this action -$37,492 · running total $29,439,340Modification P00115 · 2017-06-15 · this action -$40,378 · running total $29,398,962Modification P00116 · 2017-06-21 · this action $1,395 · running total $29,400,357Modification P00117 · 2017-06-21 · this action $10,194 · running total $29,410,551Modification P00118 · 2017-06-22 · this action $24,596 · running total $29,435,147Modification P00119 · 2017-06-22 · this action $9,181 · running total $29,444,328Modification P00120 · 2017-06-22 · this action $4,574 · running total $29,448,902Modification P00121 · 2017-06-23 · this action $5,252 · running total $29,454,154Modification P00122 · 2017-06-27 · this action $28,760 · running total $29,482,914Modification P00123 · 2017-06-27 · this action $18,315 · running total $29,501,229Modification P00124 · 2017-06-28 · this action $3,648 · running total $29,504,877Modification P00125 · 2017-08-01 · this action $10,282 · running total $29,515,159Modification P00126 · 2017-08-02 · this action $18,619 · running total $29,533,778Modification P00127 · 2017-08-03 · this action $3,335 · running total $29,537,113Modification P00128 · 2017-08-03 · this action $6,685 · running total $29,543,798Modification P00129 · 2017-08-09 · this action $5,700 · running total $29,549,498Modification P00130 · 2017-08-14 · this action $3,771 · running total $29,553,269Modification P00131 · 2017-08-15 · this action -$508 · running total $29,552,761Modification P00132 · 2017-08-17 · this action $18,108 · running total $29,570,869Modification P00133 · 2017-08-17 · this action $99,516 · running total $29,670,385Modification P00134 · 2017-08-18 · this action $74,777 · running total $29,745,162Modification P00135 · 2017-08-21 · this action $5,559 · running total $29,750,721Modification P00136 · 2017-08-21 · this action $12,772 · running total $29,763,493Modification P00137 · 2017-08-22 · this action $10,736 · running total $29,774,229Modification P00138 · 2017-08-23 · this action $3,910 · running total $29,778,139Modification P00139 · 2017-08-23 · this action $3,435 · running total $29,781,574Modification P00140 · 2017-08-24 · this action $20,861 · running total $29,802,435Modification P00141 · 2017-08-29 · this action $14,805 · running total $29,817,240Modification P00142 · 2017-08-30 · this action $12,959 · running total $29,830,199Modification P00143 · 2017-09-05 · this action $6,495 · running total $29,836,694Modification P00144 · 2017-09-15 · this action -$15,966 · running total $29,820,728Modification P00145 · 2017-10-04 · this action $4,075 · running total $29,824,803Modification P00146 · 2017-10-04 · this action $20,743 · running total $29,845,546Modification P00147 · 2017-10-17 · this action $13,069 · running total $29,858,615Modification P00149 · 2017-10-24 · this action $3,106 · running total $29,861,721Modification P00151 · 2017-10-26 · this action $2,537 · running total $29,864,258Modification P00152 · 2017-10-30 · this action $655 · running total $29,864,913Modification P00153 · 2017-10-31 · this action $11,993 · running total $29,876,906Modification P00154 · 2017-11-02 · this action $10,276 · running total $29,887,182Modification P00155 · 2017-11-02 · this action $4,962 · running total $29,892,144Modification P00148 · 2017-12-13 · this action $252,730 · running total $30,144,874Modification P00150 · 2018-02-20 · this action $517,970 · running total $30,662,844Modification P00156 · 2018-02-20 · this action $0 · running total $30,662,844Modification P00157 · 2018-06-21 · this action $131,005 · running total $30,793,849Modification P00158 · 2018-06-21 · this action $68,870 · running total $30,862,719Modification P00159 · 2018-06-21 · this action $13,839 · running total $30,876,558Modification P00160 · 2018-06-21 · this action $152,529 · running total $31,029,087Modification P00161 · 2018-06-21 · this action $53,836 · running total $31,082,923Modification P00162 · 2018-12-18 · this action $23,857 · running total $31,106,780Modification P00163 · 2019-03-08 · this action $25,633 · running total $31,132,413Modification P00164 · 2019-04-16 · this action $0 · running total $31,132,413
  • Base2014-09-30+$26,800,443= $26,800,443
  • Mod P000012015-01-26+$17,531= $26,817,974
  • Mod P000022015-05-14+$29,309= $26,847,283
  • Mod P000032015-05-14+$39,310= $26,886,593
  • Mod P000042015-05-28+$0= $26,886,593
  • Mod P000052015-05-28+$81,065= $26,967,658
  • Mod P000062015-05-28+$3,266= $26,970,924
  • Mod P000072015-07-06+$78,437= $27,049,361
  • Mod P000082015-07-08+$39,632= $27,088,993
  • Mod P000092015-07-14+$28,122= $27,117,115
  • Mod P000102015-08-03+$11,772= $27,128,887
  • Mod P000112015-08-03+$38,528= $27,167,415
  • Mod P000122015-08-05+$80,500= $27,247,915
  • Mod P000132015-08-05+$11,536= $27,259,451
  • Mod P000142015-08-25+$6,644= $27,266,095
  • Mod P000152015-08-25+$70,000= $27,336,095
  • Mod P000162015-09-02+$11,364= $27,347,459
  • Mod P000172015-11-18+$197,917= $27,545,376
  • Mod P000182015-12-16+$3,500= $27,548,876
  • Mod P000192016-01-25+$0= $27,548,876
  • Mod P000202016-02-08+$6,257= $27,555,133
  • Mod P000212016-02-16+$18,933= $27,574,066
  • Mod P000222016-02-22+$96,565= $27,670,631
  • Mod P000232016-02-22+$4,302= $27,674,933
  • Mod P000242016-02-22+$5,500= $27,680,433
  • Mod P000252016-03-04+$15,500= $27,695,933
  • Mod P000262016-03-04+$21,661= $27,717,594
  • Mod P000272016-03-09+$22,700= $27,740,294
  • Mod P000282016-03-28+$99,231= $27,839,525
  • Mod P000292016-03-30+$61,099= $27,900,624
  • Mod P000302016-04-21+$98,488= $27,999,112
  • Mod P000312016-04-28+$16,535= $28,015,647
  • Mod P000322016-04-28+$8,044= $28,023,691
  • Mod P000332016-04-29-$66,496= $27,957,195
  • Mod P000342016-05-12+$39,339= $27,996,534
  • Mod P000352016-06-10+$88,251= $28,084,785
  • Mod P000362016-06-21+$88,214= $28,172,999
  • Mod P000372016-06-23+$1,612= $28,174,611
  • Mod P000382016-06-28+$1,695= $28,176,306
  • Mod P000392016-06-30+$36,120= $28,212,426
  • Mod P000402016-07-11+$15,293= $28,227,719
  • Mod P000412016-07-25+$17,584= $28,245,303
  • Mod P000422016-07-26+$76,752= $28,322,055
  • Mod P000432016-07-26+$43,960= $28,366,015
  • Mod P000442016-08-04+$2,562= $28,368,577
  • Mod P000452016-08-04+$4,240= $28,372,817
  • Mod P000462016-09-19+$7,614= $28,380,431
  • Mod P000472016-09-19+$9,259= $28,389,690
  • Mod P000482016-09-20+$73,210= $28,462,900
  • Mod P000492016-10-05+$12,505= $28,475,405
  • Mod P000502016-10-06+$7,044= $28,482,449
  • Mod P000512016-10-19+$15,701= $28,498,150
  • Mod P000522016-10-20+$0= $28,498,150
  • Mod P000532016-10-20+$8,181= $28,506,331
  • Mod P000542016-11-02+$40,981= $28,547,312
  • Mod P000552016-11-09-$48,000= $28,499,312
  • Mod P000562016-11-29+$10,172= $28,509,484
  • Mod P000572016-12-07+$13,184= $28,522,668
  • Mod P000582016-12-08+$90,000= $28,612,668
  • Mod P000592016-12-15+$54,883= $28,667,551
  • Mod P000602017-01-03+$33,200= $28,700,751
  • Mod P000612017-01-05+$13,696= $28,714,447
  • Mod P000622017-01-05+$3,179= $28,717,626
  • Mod P000632017-01-05+$1,171= $28,718,797
  • Mod P000642017-01-10+$8,392= $28,727,189
  • Mod P000652017-01-11+$2,287= $28,729,476
  • Mod P000662017-01-17+$2,953= $28,732,429
  • Mod P000672017-01-19+$33,668= $28,766,097
  • Mod P000692017-01-24+$18,346= $28,784,443
  • Mod P000702017-01-26+$13,699= $28,798,142
  • Mod P000712017-02-06+$3,798= $28,801,940
  • Mod P000722017-02-10+$21,843= $28,823,783
  • Mod P000682017-02-14-$118,724= $28,705,059
  • Mod P000742017-02-17+$14,095= $28,719,154
  • Mod P000752017-02-21+$8,410= $28,727,564
  • Mod P000732017-02-22+$24,895= $28,752,459
  • Mod P000762017-02-22+$4,003= $28,756,462
  • Mod P000772017-02-23+$2,001= $28,758,463
  • Mod P000782017-02-24+$1,450= $28,759,913
  • Mod P000792017-03-02+$9,480= $28,769,393
  • Mod P000802017-03-02+$24,964= $28,794,357
  • Mod P000812017-03-06+$14,036= $28,808,393
  • Mod P000822017-03-07+$21,188= $28,829,581
  • Mod P000832017-03-07+$21,050= $28,850,631
  • Mod P000842017-03-09+$28,781= $28,879,412
  • Mod P000852017-03-09+$68,613= $28,948,025
  • Mod P000862017-03-15-$31,365= $28,916,660
  • Mod P000872017-03-15+$15,086= $28,931,746
  • Mod P000882017-03-16+$14,907= $28,946,653
  • Mod P000902017-03-31+$13,977= $28,960,630
  • Mod P000892017-04-05+$0= $28,960,630
  • Mod P000912017-04-06+$19,172= $28,979,802
  • Mod P000922017-04-07+$31,880= $29,011,682
  • Mod P000942017-04-24+$4,417= $29,016,099
  • Mod P000952017-04-27+$26,869= $29,042,968
  • Mod P000962017-05-01+$22,122= $29,065,090
  • Mod P000972017-05-02+$5,392= $29,070,482
  • Mod P000982017-05-03+$11,607= $29,082,089
  • Mod P000992017-05-04+$1,960= $29,084,049
  • Mod P000932017-05-10+$140,000= $29,224,049
  • Mod P001002017-05-10+$829= $29,224,878
  • Mod P001012017-05-10+$6,080= $29,230,958
  • Mod P001022017-05-10+$18,649= $29,249,607
  • Mod P001032017-05-10+$2,677= $29,252,284
  • Mod P001042017-05-11+$5,262= $29,257,546
  • Mod P001052017-05-19+$11,202= $29,268,748
  • Mod P001062017-06-06+$62,007= $29,330,755
  • Mod P001072017-06-07+$24,469= $29,355,224
  • Mod P001082017-06-08+$39,137= $29,394,361
  • Mod P001092017-06-12+$0= $29,394,361
  • Mod P001102017-06-13+$8,899= $29,403,260
  • Mod P001112017-06-13+$59,181= $29,462,441
  • Mod P001122017-06-13+$2,151= $29,464,592
  • Mod P001132017-06-13+$12,240= $29,476,832
  • Mod P001142017-06-15-$37,492= $29,439,340
  • Mod P001152017-06-15-$40,378= $29,398,962
  • Mod P001162017-06-21+$1,395= $29,400,357
  • Mod P001172017-06-21+$10,194= $29,410,551
  • Mod P001182017-06-22+$24,596= $29,435,147
  • Mod P001192017-06-22+$9,181= $29,444,328
  • Mod P001202017-06-22+$4,574= $29,448,902
  • Mod P001212017-06-23+$5,252= $29,454,154
  • Mod P001222017-06-27+$28,760= $29,482,914
  • Mod P001232017-06-27+$18,315= $29,501,229
  • Mod P001242017-06-28+$3,648= $29,504,877
  • Mod P001252017-08-01+$10,282= $29,515,159
  • Mod P001262017-08-02+$18,619= $29,533,778
  • Mod P001272017-08-03+$3,335= $29,537,113
  • Mod P001282017-08-03+$6,685= $29,543,798
  • Mod P001292017-08-09+$5,700= $29,549,498
  • Mod P001302017-08-14+$3,771= $29,553,269
  • Mod P001312017-08-15-$508= $29,552,761
  • Mod P001322017-08-17+$18,108= $29,570,869
  • Mod P001332017-08-17+$99,516= $29,670,385
  • Mod P001342017-08-18+$74,777= $29,745,162
  • Mod P001352017-08-21+$5,559= $29,750,721
  • Mod P001362017-08-21+$12,772= $29,763,493
  • Mod P001372017-08-22+$10,736= $29,774,229
  • Mod P001382017-08-23+$3,910= $29,778,139
  • Mod P001392017-08-23+$3,435= $29,781,574
  • Mod P001402017-08-24+$20,861= $29,802,435
  • Mod P001412017-08-29+$14,805= $29,817,240
  • Mod P001422017-08-30+$12,959= $29,830,199
  • Mod P001432017-09-05+$6,495= $29,836,694
  • Mod P001442017-09-15-$15,966= $29,820,728
  • Mod P001452017-10-04+$4,075= $29,824,803
  • Mod P001462017-10-04+$20,743= $29,845,546
  • Mod P001472017-10-17+$13,069= $29,858,615
  • Mod P001492017-10-24+$3,106= $29,861,721
  • Mod P001512017-10-26+$2,537= $29,864,258
  • Mod P001522017-10-30+$655= $29,864,913
  • Mod P001532017-10-31+$11,993= $29,876,906
  • Mod P001542017-11-02+$10,276= $29,887,182
  • Mod P001552017-11-02+$4,962= $29,892,144
  • Mod P001482017-12-13+$252,730= $30,144,874
  • Mod P001502018-02-20+$517,970= $30,662,844
  • Mod P001562018-02-20+$0= $30,662,844
  • Mod P001572018-06-21+$131,005= $30,793,849
  • Mod P001582018-06-21+$68,870= $30,862,719
  • Mod P001592018-06-21+$13,839= $30,876,558
  • Mod P001602018-06-21+$152,529= $31,029,087
  • Mod P001612018-06-21+$53,836= $31,082,923
  • Mod P001622018-12-18+$23,857= $31,106,780
  • Mod P001632019-03-08+$25,633= $31,132,413
  • Mod P001642019-04-16+$0= $31,132,413
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2014-09-30+$26,800,443$26,800,443CONSTRUCTION OF NEW NATIONAL CEMETERY IGF::OT::IGF
Mod P00001· CHANGE ORDER2015-01-26+$17,531$26,817,974CONSTRUCTION OF NEW NATIONAL CEMETERY IGF::OT::IGF
Mod P00002· CHANGE ORDER2015-05-14+$29,309$26,847,283CONSTRUCTION OF NEW NATIONAL CEMETERY IGF::OT::IGF
Mod P00003· CHANGE ORDER2015-05-14+$39,310$26,886,593CONSTRUCTION OF NEW NATIONAL CEMETERY IGF::OT::IGF
Mod P00004· CHANGE ORDER2015-05-28+$0$26,886,593CONSTRUCTION OF NEW NATIONAL CEMETERY IGF::OT::IGF
Mod P00005· CHANGE ORDER2015-05-28+$81,065$26,967,658CONSTRUCTION OF NEW NATIONAL CEMETERY IGF::OT::IGF
Mod P00006· CHANGE ORDER2015-05-28+$3,266$26,970,924CONSTRUCTION OF NEW NATIONAL CEMETERY IGF::OT::IGF
Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-07-06+$78,437$27,049,361CONSTRUCTION OF NEW NATIONAL CEMETERY-MODIFICATION IGF::OT::IGF
Mod P00008· CHANGE ORDER2015-07-08+$39,632$27,088,993CONSTRUCTION OF NEW NATIONAL CEMETERY IGF::OT::IGF
Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-07-14+$28,122$27,117,115CONSTRUCTION OF NEW NATIONAL CEMETERY-MODIFICATION IGF::OT::IGF
Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-08-03+$11,772$27,128,887CONSTRUCTION OF NEW NATIONAL CEMETERY-MODIFICATION IGF::OT::IGF
Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-08-03+$38,528$27,167,415CONSTRUCTION OF NEW NATIONAL CEMETERY-MODIFICATION IGF::OT::IGF
Mod P00012· CHANGE ORDER2015-08-05+$80,500$27,247,915CONSTRUCTION OF NEW NATIONAL CEMETERY IGF::OT::IGF
Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-08-05+$11,536$27,259,451CONSTRUCTION OF NEW NATIONAL CEMETERY-MODIFICATION IGF::OT::IGF
Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-08-25+$6,644$27,266,095CONSTRUCTION OF NEW NATIONAL CEMETERY-MODIFICATION IGF::OT::IGF
Mod P00015· CHANGE ORDER2015-08-25+$70,000$27,336,095CONSTRUCTION OF NEW NATIONAL CEMETERY IGF::OT::IGF
Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-09-02+$11,364$27,347,459CONSTRUCTION OF NEW NATIONAL CEMETERY-MODIFICATION IGF::OT::IGF
Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-11-18+$197,917$27,545,376CONSTRUCTION OF NEW NATIONAL CEMETERY-MODIFICATION FOR STORM INLETS IGF::OT::IGF
Mod P00018· CHANGE ORDER2015-12-16+$3,500$27,548,876CONSTRUCTION OF NEW NATIONAL CEMETERY IGF::OT::IGF
Mod P00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-01-25+$0$27,548,876CONSTRUCTION OF NEW NATIONAL CEMETERY-MODIFICATION FOR PRIOR MODIFICATION ADJUSTMENTS IGF::OT::IGF
Mod P00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-02-08+$6,257$27,555,133CONSTRUCTION OF NEW NATIONAL CEMETERY-MODIFICATION FOR STORM INLETS IGF::OT::IGF
Mod P00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-02-16+$18,933$27,574,066CONSTRUCTION OF NEW NATIONAL CEMETERY-MODIFICATION FOR STORM INLETS IGF::OT::IGF
Mod P00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-02-22+$96,565$27,670,631CONSTRUCTION OF NEW NATIONAL CEMETERY-MODIFICATION FOR STORM INLETS IGF::OT::IGF
Mod P00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-02-22+$4,302$27,674,933CONSTRUCTION OF NEW NATIONAL CEMETERY-MODIFICATION FOR STORM INLETS IGF::OT::IGF
Mod P00024· CHANGE ORDER2016-02-22+$5,500$27,680,433CONSTRUCTION OF NEW NATIONAL CEMETERY IGF::OT::IGF
Mod P00025· CHANGE ORDER2016-03-04+$15,500$27,695,933CONSTRUCTION OF NEW NATIONAL CEMETERY IGF::OT::IGF
Mod P00026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-03-04+$21,661$27,717,594CONSTRUCTION OF NEW NATIONAL CEMETERY-MODIFICATION FOR CURB INLETS IGF::OT::IGF
Mod P00027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-03-09+$22,700$27,740,294CONSTRUCTION OF NEW NATIONAL CEMETERY-MODIFICATION FOR CURB INLETS IGF::OT::IGF
Mod P00028· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-03-28+$99,231$27,839,525CONSTRUCTION OF NEW NATIONAL CEMETERY-MODIFICATION FOR CURB INLETS IGF::OT::IGF
Mod P00029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-03-30+$61,099$27,900,624RETAINING WALL 1 STORMWATER DRAINAGE IGF::OT::IGF
Mod P00030· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-04-21+$98,488$27,999,112BULLETIN 35 FDOT ROW REVISIONS IGF::OT::IGF
Mod P00031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-04-28+$16,535$28,015,647RFI 033 GRADING BETWEEN ENTRANCES IGF::OT::IGF
Mod P00032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-04-28+$8,044$28,023,691RFI 080 ROAD H / MAINTENANCE PARKING LOT REVISIONS IGF::OT::IGF
Mod P00033· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-04-29−$66,496$27,957,195REPLACE SYNTHETIC TURF WITH SOD IGF::OT::IGF
Mod P00034· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-05-12+$39,339$27,996,534PHASE 1A SITE WORK REVISIONS IGF::OT::IGF
Mod P00035· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-06-10+$88,251$28,084,785PHASE 1A MISCELLANEOUS REVISIONS IGF::OT::IGF
Mod P00036· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-06-21+$88,214$28,172,999NORTH WELL CONTROLS AND POWER IGF::OT::IGF
Mod P00037· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-06-23+$1,612$28,174,611RFI 089 ABOVE CEILING TYPE C WALL IGF::OT::IGF
Mod P00038· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-06-28+$1,695$28,176,306ADD IRRIGATION VALVE AND ZONE IGF::OT::IGF
Mod P00039· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-06-30+$36,120$28,212,426BULLETIN 38 COLUMBARIUM ELEVATION CHANGES IGF::OT::IGF
Mod P00040· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-07-11+$15,293$28,227,719PHASE 1A IRRIGATION WELL IGF::OT::IGF
Mod P00041· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-07-25+$17,584$28,245,303HIGHWAY 27 TURN LANE WIDENING IGF::OT::IGF
Mod P00042· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-07-26+$76,752$28,322,055RETAINING WALL 1 WASHOUT REPAIRS IGF::OT::IGF
Mod P00043· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-07-26+$43,960$28,366,015RFI 92 ROAD F CENTERLINE PROFILE CHANGES IGF::OT::IGF
Mod P00044· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-08-04+$2,562$28,368,577MISCELLANEOUS TREE REMOVAL IGF::OT::IGF
Mod P00045· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-08-04+$4,240$28,372,817RFI 107 TYPE P LIGHT FIXTURES IGF::OT::IGF
Mod P00046· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-09-19+$7,614$28,380,431MAINTENANCE BUILDING EAST PORCH INSULATION ENVELOPE IGF::OT::IGF
Mod P00047· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-09-19+$9,259$28,389,690MAINTENANCE BUILDING DOORS AND FRAMES IGF::OT::IGF
Mod P00048· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-09-20+$73,210$28,462,900SOUTH WELL REVISIONS IGF::OT::IGF
Mod P00049· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-10-05+$12,505$28,475,405RFI 67 MAINTENANCE BUILDING SITE LIGHTING IGF::OT::IGF
Mod P00050· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-10-06+$7,044$28,482,449BULLETIN 29 STORM DRAINAGE REVISIONS IGF::OT::IGF
Mod P00051· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-10-19+$15,701$28,498,150REVISED DETAILS AT OSSUARY/MEMORIAL WALL PLAZA IGF::OT::IGF
Mod P00052· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-10-20+$0$28,498,150CCTV CHANGES IGF::OT::IGF
Mod P00053· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-10-20+$8,181$28,506,331BULLETIN 23 SWALE NORTH OF CONTRACTOR'S YARD IGF::OT::IGF
Mod P00054· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-11-02+$40,981$28,547,312BULLETIN 41 POND 100 INLET IGF::OT::IGF
Mod P00055· CHANGE ORDER2016-11-09−$48,000$28,499,312SECURITY SYSTEM CHANGES IGF::OT::IGF
Mod P00056· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-11-29+$10,172$28,509,484ADD STREET IDENTIFICATION SIGNS IGF::OT::IGF
Mod P00057· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-12-07+$13,184$28,522,668WETLAND MITIGATION EXOTIC REMOVAL AND PLANTING IGF::OT::IGF
Mod P00058· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-12-08+$90,000$28,612,668ADD BMPS AND EROSION CONTROL IGF::OT::IGF
Mod P00059· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-12-15+$54,883$28,667,551CONCRETE REINFORCEMENT REVISIONS IGF::OT::IGF
Mod P00060· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-01-03+$33,200$28,700,751RFI 97 SCREEN WALL IGF::OT::IGF
Mod P00061· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-01-05+$13,696$28,714,447RFI 90 ADD DOWNSPOUT CONNECTORS IGF::OT::IGF
Mod P00062· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-01-05+$3,179$28,717,626ADD FILTER FABRIC AT SAND FILTERS IGF::OT::IGF
Mod P00063· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-01-05+$1,171$28,718,797RFI 122 ADD DOWNSPOUTS AT ADMIN BUILDING IGF::OT::IGF
Mod P00064· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-01-10+$8,392$28,727,189MAIN ENTRANCE SOD REVISIONS IGF::OT::IGF
Mod P00065· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-01-11+$2,287$28,729,476DEDICATED POWER FOR CLEAN AGENT FIRE SUPPRESSION SYSTEM IGF::OT::IGF
Mod P00066· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-01-17+$2,953$28,732,429BULLETIN 24 TEMP COMMITTAL SHELTER REGRADING IGF::OT::IGF
Mod P00067· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-01-19+$33,668$28,766,097HONOR GUARD LANDSCAPING CHANGES IGF::OT::IGF
Mod P00069· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-01-24+$18,346$28,784,443ADD FLOWER WATERING STATION AT COLUMBARIUM IGF::OT::IGF
Mod P00070· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-01-26+$13,699$28,798,142ADDED SOD AT POND 300 IGF::OT::IGF
Mod P00071· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-02-06+$3,798$28,801,940RFI 94 REVISED POWER FOR KITCHEN EQUIPMENT IGF::OT::IGF
Mod P00072· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-02-10+$21,843$28,823,783ADDED SOD PER RFI 73 RESPONSE IGF::OT::IGF
Mod P00068· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-02-14−$118,724$28,705,059HONOR GUARD LANDSCAPING CHANGES IGF::OT::IGF
Mod P00074· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-02-17+$14,095$28,719,154ADDED SOD AT ROAD A NEAR STA 41+00 IGF::OT::IGF
Mod P00075· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-02-21+$8,410$28,727,564ADDED SOD AT BASE OF POND 100 RETAINING WALL IGF::OT::IGF
Mod P00073· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-02-22+$24,895$28,752,459ADDED SOD PER RFI 73 RESPONSE IGF::OT::IGF
Mod P00076· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-02-22+$4,003$28,756,462ADDED SOD AT INTERSECTION OF MAINT. CONNECTOR AND MAIN LOOP IGF::OT::IGF
Mod P00077· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-02-23+$2,001$28,758,463REMOVE TREES AT POND 100 AND MAIN ENTRANCE IGF::OT::IGF
Mod P00078· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-02-24+$1,450$28,759,913RFI 30 RELOCATE PEMB EXHAUST FAN IGF::OT::IGF
Mod P00079· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-03-02+$9,480$28,769,393RFQ D-017 MAINTENANCE BUILDING REVISIONS IGF::OT::IGF
Mod P00080· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-03-02+$24,964$28,794,357ADD DRAINS AT FLAG ASSEMBLY AREA IGF::OT::IGF
Mod P00081· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-03-06+$14,036$28,808,393RFQ D-011 PHASE 1A LOOP ROAD CHANGES IGF::OT::IGF
Mod P00082· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-03-07+$21,188$28,829,581BULLETIN 42 REPLACE CONCRETE PAVING WITH ASPHALT IGF::OT::IGF
Mod P00083· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-03-07+$21,050$28,850,631RFI 154 REGRADING AT ADMIN AREA IGF::OT::IGF
Mod P00084· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-03-09+$28,781$28,879,412BULLETIN 44 REVISE CURB AND INLETS NORTH OF COMMITTAL SHELTER 1 IGF::OT::IGF
Mod P00085· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-03-09+$68,613$28,948,025RFI 181 ADD BAHIA SOD IGF::OT::IGF
Mod P00086· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-03-15−$31,365$28,916,660CONTRACTOR YARD SURFACE REVISIONS IGF::OT::IGF
Mod P00087· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-03-15+$15,086$28,931,746POND 300 SINKHOLE INVESTIGATION IGF::OT::IGF
Mod P00088· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-03-16+$14,907$28,946,653RFI 56 ADD BLOCKING FOR SIPS TO ICF ATTACHMENT IGF::OT::IGF
Mod P00090· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-03-31+$13,977$28,960,630MISCELLANEOUS ELECTRICAL RFIS IGF::OT::IGF
Mod P00089· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-04-05+$0$28,960,630WEATHER DELAY IGF::OT::IGF
Mod P00091· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-04-06+$19,172$28,979,802RFI 152 REVISE CURBS AND INLET AT ROAD H IGF::OT::IGF
Mod P00092· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-04-07+$31,880$29,011,682RFI 167 ADMIN CONCRETE PAVING GRADES IGF::OT::IGF
Mod P00094· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-04-24+$4,417$29,016,099COMMITTAL SHELTER AREA LANDSCAPING IGF::OT::IGF
Mod P00095· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-04-27+$26,869$29,042,968RFI 173 MAINTENANCE BUILDING DRAINAGE REVISIONS IGF::OT::IGF
Mod P00096· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-05-01+$22,122$29,065,090RFI 180 ADDED SOD EAST OF FLAG ASSEMBLY IGF::OT::IGF
Mod P00097· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-05-02+$5,392$29,070,482PRUNE AND FERTILIZE OAK TREE WEST OF MAIN ENTRANCE IGF::OT::IGF
Mod P00098· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-05-03+$11,607$29,082,089ADDITIONAL TREE REMOVAL IGF::OT::IGF
Mod P00099· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-05-04+$1,960$29,084,049ADDED PARKING BUMPERS AT PIC/ADMIN BUILDING IGF::OT::IGF
Mod P00093· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-05-10+$140,000$29,224,049SECURITY CHANGE IGF::OT::IGF
Mod P00100· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-05-10+$829$29,224,878RFI 184 ADD WALL BASE AT MAINTENANCE GARAGE IGF::OT::IGF
Mod P00101· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-05-10+$6,080$29,230,958RFI 174 RAISE INLET 504 AT HIGHWAY 27 IGF::OT::IGF
Mod P00102· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-05-10+$18,649$29,249,607GRADE BEHIND CURB AT BURIAL SECTIONS 1-3 IGF::OT::IGF
Mod P00103· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-05-10+$2,677$29,252,284RAISE INLET SD 343 IGF::OT::IGF
Mod P00104· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-05-11+$5,262$29,257,546RFI 165 REVISE GRADES AT MAINTENANCE YARD IGF::OT::IGF
Mod P00105· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-05-19+$11,202$29,268,748REMOVE AND REPLACE CURB IGF::OT::IGF
Mod P00106· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-06-06+$62,007$29,330,7551B WELL RELOCATION AND ADDED ELECTRICAL METER IGF::OT::IGF
Mod P00107· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-06-07+$24,469$29,355,224ADD PINE STRAW IGF::OT::IGF
Mod P00108· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-06-08+$39,137$29,394,361SPOT COOLERS AND DEHUMIDIFIERS FOR DRY OUT IGF::OT::IGF
Mod P00109· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-06-12+$0$29,394,3611B WELL RELOCATION AND ADDED ELECTRICAL METER IGF::OT::IGF
Mod P00110· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-06-13+$8,899$29,403,260ADD RIP RAP ARMORING TO OLD ST. AUGUSTINE SWALES IGF::OT::IGF
Mod P00111· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-06-13+$59,181$29,462,441BULLETIN 45 ADD PRIVACY FENCES IGF::OT::IGF
Mod P00112· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-06-13+$2,151$29,464,592VEEDER ROOT FINAL LOCATION AND CIRCUITING IGF::OT::IGF
Mod P00113· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-06-13+$12,240$29,476,832ADD BENCHES IGF::OT::IGF
Mod P00114· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-06-15−$37,492$29,439,340RETAINING WALL HANDRAIL REVISIONS IGF::OT::IGF
Mod P00115· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-06-15−$40,378$29,398,962DELETE ENTRY GATE OPERATORS IGF::OT::IGF
Mod P00116· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-06-21+$1,395$29,400,357RFI 125 ADD ANGLE AT MAINTENANCE MEZZANINE IGF::OT::IGF
Mod P00117· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-06-21+$10,194$29,410,551REROUTE NATURAL GAS LINE FOR GENERATOR IGF::OT::IGF
Mod P00118· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-06-22+$24,596$29,435,147RFI 150 ADD PRESSURE REGULATORS IGF::OT::IGF
Mod P00119· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-06-22+$9,181$29,444,328ADD HAT CHANNEL FOR COMMITTAL SHELTER CEILINGS IGF::OT::IGF
Mod P00120· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-06-22+$4,574$29,448,902REPLACEMENT STREET SIGN IGF::OT::IGF
Mod P00121· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-06-23+$5,252$29,454,154RFI 186 ADD HOLES AND STONE AT SWALES IGF::OT::IGF
Mod P00122· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-06-27+$28,760$29,482,914RFI 146 ADD AERATION TO PONDS 100 AND 200 IGF::OT::IGF
Mod P00123· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-06-27+$18,315$29,501,229HWY 27 ROW SOD AND IRRIGATION REVISIONS IGF::OT::IGF
Mod P00124· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-06-28+$3,648$29,504,877RFI 87 RELOCATE PIC/ADMIN BUILDING SHUTOFF VALVES IGF::OT::IGF
Mod P00125· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-08-01+$10,282$29,515,159RFI 147 DELETE 1A CS AND ADD POLIGON STRUCTURE IGF::OT::IGF
Mod P00126· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-08-02+$18,619$29,533,778RFI 183 REPLACE CONCRETE AT CS 2 AND MAINTENANCE BUILDING PORCH IGF::OT::IGF
Mod P00127· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-08-03+$3,335$29,537,113RAISE IRRIGATION VALVE BOXES IGF::OT::IGF
Mod P00128· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-08-03+$6,685$29,543,798ADD BAHIA SOD AT WEST MOW STRIP IGF::OT::IGF
Mod P00129· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-08-09+$5,700$29,549,498RFI 132 ADMIN BUILDING LANDSCAPE REVISIONS IGF::OT::IGF
Mod P00130· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-08-14+$3,771$29,553,269RFI 169 RELOCATE FIRE ALARM DEVICES IGF::OT::IGF
Mod P00131· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-08-15−$508$29,552,761RFQ D-016 COLUMBARIUM AND MEMORIAL WALL REVISIONS IGF::OT::IGF
Mod P00132· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-08-17+$18,108$29,570,869RFI 158 SIPS ATTACHMENT TO STEEL IGF::OT::IGF
Mod P00133· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-08-17+$99,516$29,670,385DEMO AND REPLACE ADMIN AND HONOR GUARD PORCHES IGF::OT::IGF
Mod P00134· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-08-18+$74,777$29,745,162ADD IRRIGATION PER BAHIA SOD ADDED IN RFI 181 IGF::OT::IGF
Mod P00135· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-08-21+$5,559$29,750,721ADD LANDSCAPING AT PVC ENCLOSURES IGF::OT::IGF
Mod P00136· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-08-21+$12,772$29,763,493RFI 195 ADDITIONAL BRUSH HOGGING IGF::OT::IGF
Mod P00137· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-08-22+$10,736$29,774,229HONOR GUARD IT CLOSET REVISIONS IGF::OT::IGF
Mod P00138· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-08-23+$3,910$29,778,139ADD MOTION SENSORS AT MAINTENANCE YARD IGF::OT::IGF
Mod P00139· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-08-23+$3,435$29,781,574GETTYSBURG ADDRESS PLAQUE IGF::OT::IGF
Mod P00140· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-08-24+$20,861$29,802,435ADD POWER ASSIST AUTO OPERATORS AND SECURITY IGF::OT::IGF
Mod P00141· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-08-29+$14,805$29,817,240RFI 191 RELOCATE RE TRAILER IGF::OT::IGF
Mod P00142· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-08-30+$12,959$29,830,199RFI 143 REVISED JOINTS AT COLUMBARIUM AND OSSUARY PLAZA IGF::OT::IGF
Mod P00143· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-09-05+$6,495$29,836,694RFI 190 CONCRETE TRANSITION AT ADMIN BUILDING PORCH IGF::OT::IGF
Mod P00144· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-09-15−$15,966$29,820,728POND 300 SINKHOLE REMEDIATION IGF::OT::IGF
Mod P00145· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-10-04+$4,075$29,824,803ADD SOAP AND PAPER TOWEL DISPENSERS IGF::OT::IGF
Mod P00146· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-10-04+$20,743$29,845,546ADD AERATION FOUNTAIN FOR POND 200 IGF::OT::IGF
Mod P00147· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-10-17+$13,069$29,858,615REVISED MAIN ENTRANCE LANDSCAPING IGF::OT::IGF
Mod P00149· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-10-24+$3,106$29,861,721RFI 182 MOTOR STARTER AND DISCONNECT FOR EF 2-1 AND 2-2 IGF::OT::IGF
Mod P00151· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-10-26+$2,537$29,864,258TREE REMOVAL AT EAST ROAD IGF::OT::IGF
Mod P00152· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-10-30+$655$29,864,913TEMPORARY COVER AT GRAVE LOCATOR IGF::OT::IGF
Mod P00153· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-10-31+$11,993$29,876,906REPAIR ASPHALT NEAR COMMITTAL SHELTER 1 IGF::OT::IGF
Mod P00154· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-11-02+$10,276$29,887,182ADD LIGHTNING PROTECTION AT WELLS IGF::OT::IGF
Mod P00155· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2017-11-02+$4,962$29,892,144ADD TAPS PLAYER AT CS 1 AND 2 IGF::OT::IGF
Mod P00148· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-12-13+$252,730$30,144,874REVISED MAIN ENTRANCE LANDSCAPING IGF::OT::IGF
Mod P00150· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2018-02-20+$517,970$30,662,844OVERHEAD COST IGF::OT::IGF
Mod P00156· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-02-20+$0$30,662,844HURRICANE IRMA TIME EXTENSION FOR CLEAN-UP IGF::OT::IGF
Mod P00157· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-06-21+$131,005$30,793,849HURRICANE IRMA TIME EXTENSION FOR CLEAN-UP IGF::OT::IGF
Mod P00158· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-06-21+$68,870$30,862,719HURRICANE IRMA TIME EXTENSION FOR CLEAN-UP IGF::OT::IGF
Mod P00159· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-06-21+$13,839$30,876,558HURRICANE IRMA TIME EXTENSION FOR CLEAN-UP IGF::OT::IGF
Mod P00160· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-06-21+$152,529$31,029,087HURRICANE IRMA CLEAN UP IGF::OT::IGF
Mod P00161· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-06-21+$53,836$31,082,923HURRICANE IRMA TIME EXTENSION FOR CLEAN-UP IGF::OT::IGF
Mod P00162· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-12-18+$23,857$31,106,780POND 300 REPAIR IGF::OT::IGF
Mod P00163· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2019-03-08+$25,633$31,132,413IGF::OT::IGF BONDING ADJUSTMENT
Mod P00164· CLOSE OUT2019-04-16+$0$31,132,413IGF::OT::IGF CONTRACT CLOSE OUT

Related awards · 11

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI Z6ZVR3MXC9L4)

AwardOffice · PSC / listingNet obligationsFY
36C78626C0020NATIONAL CEMETERY ADMIN (36C786) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS$31,145,450FY2026
36C24726C0055247-NETWORK CONTRACT OFFICE 7 (36C247) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$9,079,864FY2026
36C78626N0338NATIONAL CEMETERY ADMIN (36C786) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS$122,570FY2026
36C78626N0342NATIONAL CEMETERY ADMIN (36C786) · Z2JZ · REPAIR OR ALTERATION OF MISCELLANEOUS BUILDINGS$361,151FY2026
36C78625C0042NATIONAL CEMETERY ADMIN (36C786) · Y1JZ · CONSTRUCTION OF MISCELLANEOUS BUILDINGS$24,203,981FY2025
36C78625N0565NATIONAL CEMETERY ADMIN (36C786) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS$281,750FY2025

Other recipients under Y1PC from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)

AwardRecipientOfficeNet obligationsFY
36C10F26C0005GC & V CONSTRUCTION LLCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$59,890,000FY2026
36C10F25C0007HAMILTON PACIFIC CHAMBERLAIN LLCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$637,437FY2025
36C10F24C0007SEABEE CONSTRUCTION, INC.OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$79,106,191FY2024
36C10F24C0001RBVETCO, LLCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$38,940,668FY2024
36C10F23C0008SGC SERVICES 2, LLCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$42,010,850FY2023

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA101F14C0035_3600_-NONE-_-NONE- · retrieved 2026-09-26.