Award recordCONTRACT

SWINERTON ABSHER JV

PIID VA101F13C0071· VA Staff Offices· OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)· Y1LZ · CONSTRUCTION OF PARKING FACILITIES· FY2013· $47,449,027 net obligations· UEI GH1KEBS4H9P9· CO

Description

BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN WAY, SEATTLE, WA DE-SCOPE CONTRACT FOR CREDIT FOR FIRE ALARM SPARE PARTS AND MANUFACTURER SEISMIC CERTIFICATION, AND FOR MISCELLANEOUS ROUNDING DISCREPANCIES. IGF::OT::IGF

Base award description: BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN WAY, SEATTLE, WA IGF::OT::IGF

First action · last action
2013-09-30 · 2018-12-19
Transactions
138
First transaction's obligation
$44,374,390
Base + all options value (sum of deltas)
$47,450,103
Extent competed
FULL AND OPEN COMPETITION
Other than full & open authority
—
Set-aside
NO SET ASIDE USED.
Offers received
4
SDVOSB flag on record
No
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION

Modification chain · 138 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$47,453,686$0Base award · 2013-09-30 · this action $44,374,390 · running total $44,374,390Modification P00001 · 2014-04-02 · this action $3,000 · running total $44,377,390Modification P00002 · 2014-04-07 · this action $48,000 · running total $44,425,390Modification P00004 · 2014-06-16 · this action $65,000 · running total $44,490,390Modification P00005 · 2014-06-23 · this action $17,969 · running total $44,508,359Modification P00006 · 2014-06-23 · this action $10,000 · running total $44,518,359Modification P00007 · 2014-07-17 · this action $0 · running total $44,518,359Modification P00003 · 2014-08-18 · this action $0 · running total $44,518,359Modification P00009 · 2014-09-15 · this action $4,609 · running total $44,522,968Modification P00010 · 2014-09-29 · this action $15,000 · running total $44,537,968Modification P00011 · 2014-10-02 · this action -$99,000 · running total $44,438,968Modification P00013 · 2014-10-14 · this action $17,297 · running total $44,456,265Modification P00014 · 2014-10-17 · this action $25,000 · running total $44,481,265Modification P00016 · 2014-10-24 · this action $23,399 · running total $44,504,664Modification P00019 · 2014-11-03 · this action $6,500 · running total $44,511,164Modification P00018 · 2014-11-06 · this action $11,300 · running total $44,522,464Modification P00020 · 2014-11-13 · this action $26,500 · running total $44,548,964Modification P00024 · 2014-12-30 · this action $98,400 · running total $44,647,364Modification P00021 · 2015-01-15 · this action $8,878 · running total $44,656,242Modification P00025 · 2015-01-15 · this action $0 · running total $44,656,242Modification P00022 · 2015-01-20 · this action -$1,705 · running total $44,654,537Modification P00032 · 2015-01-20 · this action $25,000 · running total $44,679,537Modification P00023 · 2015-01-27 · this action $3,158 · running total $44,682,695Modification P00026 · 2015-01-27 · this action $2,273 · running total $44,684,968Modification P00027 · 2015-01-27 · this action $16,259 · running total $44,701,227Modification P00028 · 2015-01-27 · this action $7,020 · running total $44,708,247Modification P00031 · 2015-01-27 · this action $850 · running total $44,709,096Modification P00033 · 2015-01-27 · this action $17,372 · running total $44,726,468Modification P00034 · 2015-01-27 · this action -$50,000 · running total $44,676,468Modification P00038 · 2015-01-27 · this action $67,643 · running total $44,744,111Modification P00030 · 2015-01-28 · this action $16,385 · running total $44,760,496Modification P00040 · 2015-01-28 · this action $0 · running total $44,760,496Modification P00041 · 2015-02-11 · this action $12,601 · running total $44,773,097Modification P00035 · 2015-02-17 · this action $2,923 · running total $44,776,020Modification P00046 · 2015-02-17 · this action $5,908 · running total $44,781,928Modification P00052 · 2015-02-19 · this action $5,000 · running total $44,786,928Modification P00054 · 2015-03-04 · this action $10,000 · running total $44,796,928Modification P00049 · 2015-03-11 · this action $2,867 · running total $44,799,795Modification P00039 · 2015-03-16 · this action $9,680 · running total $44,809,475Modification P00050 · 2015-03-16 · this action -$6,508 · running total $44,802,967Modification P00053 · 2015-03-16 · this action $36,987 · running total $44,839,954Modification P00055 · 2015-03-18 · this action $1,500 · running total $44,841,454Modification P00060 · 2015-03-20 · this action $5,000 · running total $44,846,454Modification P00056 · 2015-03-27 · this action $8,154 · running total $44,854,608Modification P00062 · 2015-03-31 · this action $75,000 · running total $44,929,608Modification P00045 · 2015-04-17 · this action $2,381 · running total $44,931,989Modification P00042 · 2015-04-22 · this action $3,600 · running total $44,935,589Modification P00048 · 2015-04-22 · this action $12,199 · running total $44,947,787Modification P00074 · 2015-04-29 · this action $11,979 · running total $44,959,766Modification P00071 · 2015-05-01 · this action $18,000 · running total $44,977,766Modification P00063 · 2015-05-05 · this action $84,500 · running total $45,062,266Modification P00069 · 2015-05-05 · this action $95,000 · running total $45,157,266Modification P00058 · 2015-05-08 · this action $7,500 · running total $45,164,766Modification P00065 · 2015-05-08 · this action $1,200 · running total $45,165,966Modification P00066 · 2015-05-08 · this action $4,000 · running total $45,169,966Modification P00076 · 2015-05-13 · this action $12,000 · running total $45,181,966Modification P00068 · 2015-06-01 · this action $4,144 · running total $45,186,110Modification P00070 · 2015-06-01 · this action $2,843 · running total $45,188,953Modification P00083 · 2015-06-10 · this action $915 · running total $45,189,868Modification P00084 · 2015-06-15 · this action $34,200 · running total $45,224,068Modification P00085 · 2015-06-15 · this action $24,000 · running total $45,248,068Modification P00082 · 2015-06-19 · this action $887 · running total $45,248,955Modification P00086 · 2015-06-19 · this action $11,300 · running total $45,260,255Modification P00077 · 2015-06-29 · this action $7,923 · running total $45,268,178Modification P00091 · 2015-07-16 · this action $0 · running total $45,268,178Modification P00017 · 2015-08-05 · this action -$23,311 · running total $45,244,867Modification P00087 · 2015-08-06 · this action $2,185 · running total $45,247,052Modification P00092 · 2015-08-24 · this action $2,050 · running total $45,249,102Modification P00093 · 2015-08-24 · this action $3,280 · running total $45,252,382Modification P00096 · 2015-09-21 · this action $5,800 · running total $45,258,182Modification P00103 · 2015-09-28 · this action $1,648 · running total $45,259,830Modification P00108 · 2015-10-22 · this action $2,500 · running total $45,262,330Modification P00110 · 2015-11-03 · this action $0 · running total $45,262,330Modification P00080 · 2015-11-06 · this action $7,000 · running total $45,269,330Modification P00081 · 2015-11-06 · this action $174,650 · running total $45,443,980Modification P00090 · 2015-11-06 · this action $7,481 · running total $45,451,461Modification P00097 · 2015-11-06 · this action $3,407 · running total $45,454,868Modification P00102 · 2015-11-06 · this action $826 · running total $45,455,694Modification P00104 · 2015-11-06 · this action $26,512 · running total $45,482,206Modification P00106 · 2015-11-06 · this action $218 · running total $45,482,424Modification P00112 · 2015-11-06 · this action $2,800 · running total $45,485,224Modification P00107 · 2015-11-09 · this action $1,795 · running total $45,487,019Modification P00113 · 2015-11-17 · this action -$12,333 · running total $45,474,686Modification P00029 · 2015-11-18 · this action $0 · running total $45,474,686Modification P00059 · 2015-11-20 · this action $13,836 · running total $45,488,522Modification P00088 · 2015-12-08 · this action $7,261 · running total $45,495,783Modification P00089 · 2015-12-08 · this action $9,467 · running total $45,505,250Modification P00057 · 2015-12-15 · this action $3,364 · running total $45,508,614Modification P00101 · 2015-12-15 · this action $652 · running total $45,509,266Modification P00114 · 2015-12-15 · this action $1,860 · running total $45,511,126Modification P00115 · 2015-12-15 · this action $2,864 · running total $45,513,990Modification P00073 · 2015-12-16 · this action $6,350 · running total $45,520,340Modification P00098 · 2016-01-13 · this action -$6,883 · running total $45,513,457Modification P00100 · 2016-01-13 · this action -$2,231 · running total $45,511,226Modification P00116 · 2016-01-13 · this action $3,790 · running total $45,515,016Modification P00111 · 2016-01-14 · this action $3,598 · running total $45,518,614Modification P00120 · 2016-01-28 · this action $1,943 · running total $45,520,557Modification P00121 · 2016-01-29 · this action $3,150 · running total $45,523,707Modification P00122 · 2016-02-05 · this action $7,000 · running total $45,530,707Modification P00123 · 2016-02-10 · this action $958 · running total $45,531,665Modification P00125 · 2016-02-10 · this action $7,150 · running total $45,538,815Modification P00131 · 2016-02-10 · this action $7,285 · running total $45,546,100Modification P00126 · 2016-02-12 · this action $650 · running total $45,546,750Modification P00119 · 2016-02-15 · this action $7,949 · running total $45,554,699Modification P00128 · 2016-02-18 · this action $1,810 · running total $45,556,509Modification P00127 · 2016-02-22 · this action $2,536 · running total $45,559,045Modification P00132 · 2016-02-29 · this action $7,608 · running total $45,566,653Modification P00124 · 2016-03-02 · this action $14,940 · running total $45,581,593Modification P00137 · 2016-03-04 · this action $2,969 · running total $45,584,562Modification P00138 · 2016-03-08 · this action $26,019 · running total $45,610,581Modification P00134 · 2016-03-09 · this action $4,537 · running total $45,615,118Modification P00141 · 2016-03-09 · this action $5,170 · running total $45,620,288Modification P00129 · 2016-03-14 · this action $5,446 · running total $45,625,734Modification P00130 · 2016-03-15 · this action $7,357 · running total $45,633,091Modification P00136 · 2016-03-15 · this action $4,369 · running total $45,637,460Modification P00139 · 2016-03-15 · this action $2,625 · running total $45,640,085Modification P00142 · 2016-03-15 · this action $3,380 · running total $45,643,465Modification P00144 · 2016-03-18 · this action $2,500 · running total $45,645,965Modification P00133 · 2016-03-23 · this action -$383 · running total $45,645,582Modification P00146 · 2016-03-23 · this action $0 · running total $45,645,582Modification P00148 · 2016-03-23 · this action $3,075 · running total $45,648,657Modification P00064 · 2016-03-30 · this action $5,267 · running total $45,653,924Modification P00135 · 2016-03-31 · this action $3,461 · running total $45,657,385Modification P00143 · 2016-04-05 · this action $14,183 · running total $45,671,568Modification P00149 · 2016-04-05 · this action $19,514 · running total $45,691,082Modification P00150 · 2016-04-05 · this action $1,050 · running total $45,692,132Modification P00151 · 2016-04-05 · this action $24,259 · running total $45,716,391Modification P00152 · 2016-04-05 · this action $1,217 · running total $45,717,608Modification P00153 · 2016-04-05 · this action $6,806 · running total $45,724,414Modification P00154 · 2016-04-05 · this action $2,632 · running total $45,727,046Modification P00155 · 2016-04-11 · this action $3,192 · running total $45,730,238Modification P00156 · 2016-04-11 · this action $12,978 · running total $45,743,216Modification P00159 · 2016-04-11 · this action $1,737 · running total $45,744,953Modification P00160 · 2016-04-18 · this action $1,047 · running total $45,746,000Modification P00161 · 2016-04-18 · this action $8,686 · running total $45,754,686Modification P00169 · 2016-07-06 · this action $531,150 · running total $46,285,836Modification P00170 · 2017-07-21 · this action $1,167,850 · running total $47,453,686Modification P00171 · 2018-12-19 · this action -$4,659 · running total $47,449,027
  • Base2013-09-30+$44,374,390= $44,374,390
  • Mod P000012014-04-02+$3,000= $44,377,390
  • Mod P000022014-04-07+$48,000= $44,425,390
  • Mod P000042014-06-16+$65,000= $44,490,390
  • Mod P000052014-06-23+$17,969= $44,508,359
  • Mod P000062014-06-23+$10,000= $44,518,359
  • Mod P000072014-07-17+$0= $44,518,359
  • Mod P000032014-08-18+$0= $44,518,359
  • Mod P000092014-09-15+$4,609= $44,522,968
  • Mod P000102014-09-29+$15,000= $44,537,968
  • Mod P000112014-10-02-$99,000= $44,438,968
  • Mod P000132014-10-14+$17,297= $44,456,265
  • Mod P000142014-10-17+$25,000= $44,481,265
  • Mod P000162014-10-24+$23,399= $44,504,664
  • Mod P000192014-11-03+$6,500= $44,511,164
  • Mod P000182014-11-06+$11,300= $44,522,464
  • Mod P000202014-11-13+$26,500= $44,548,964
  • Mod P000242014-12-30+$98,400= $44,647,364
  • Mod P000212015-01-15+$8,878= $44,656,242
  • Mod P000252015-01-15+$0= $44,656,242
  • Mod P000222015-01-20-$1,705= $44,654,537
  • Mod P000322015-01-20+$25,000= $44,679,537
  • Mod P000232015-01-27+$3,158= $44,682,695
  • Mod P000262015-01-27+$2,273= $44,684,968
  • Mod P000272015-01-27+$16,259= $44,701,227
  • Mod P000282015-01-27+$7,020= $44,708,247
  • Mod P000312015-01-27+$850= $44,709,096
  • Mod P000332015-01-27+$17,372= $44,726,468
  • Mod P000342015-01-27-$50,000= $44,676,468
  • Mod P000382015-01-27+$67,643= $44,744,111
  • Mod P000302015-01-28+$16,385= $44,760,496
  • Mod P000402015-01-28+$0= $44,760,496
  • Mod P000412015-02-11+$12,601= $44,773,097
  • Mod P000352015-02-17+$2,923= $44,776,020
  • Mod P000462015-02-17+$5,908= $44,781,928
  • Mod P000522015-02-19+$5,000= $44,786,928
  • Mod P000542015-03-04+$10,000= $44,796,928
  • Mod P000492015-03-11+$2,867= $44,799,795
  • Mod P000392015-03-16+$9,680= $44,809,475
  • Mod P000502015-03-16-$6,508= $44,802,967
  • Mod P000532015-03-16+$36,987= $44,839,954
  • Mod P000552015-03-18+$1,500= $44,841,454
  • Mod P000602015-03-20+$5,000= $44,846,454
  • Mod P000562015-03-27+$8,154= $44,854,608
  • Mod P000622015-03-31+$75,000= $44,929,608
  • Mod P000452015-04-17+$2,381= $44,931,989
  • Mod P000422015-04-22+$3,600= $44,935,589
  • Mod P000482015-04-22+$12,199= $44,947,787
  • Mod P000742015-04-29+$11,979= $44,959,766
  • Mod P000712015-05-01+$18,000= $44,977,766
  • Mod P000632015-05-05+$84,500= $45,062,266
  • Mod P000692015-05-05+$95,000= $45,157,266
  • Mod P000582015-05-08+$7,500= $45,164,766
  • Mod P000652015-05-08+$1,200= $45,165,966
  • Mod P000662015-05-08+$4,000= $45,169,966
  • Mod P000762015-05-13+$12,000= $45,181,966
  • Mod P000682015-06-01+$4,144= $45,186,110
  • Mod P000702015-06-01+$2,843= $45,188,953
  • Mod P000832015-06-10+$915= $45,189,868
  • Mod P000842015-06-15+$34,200= $45,224,068
  • Mod P000852015-06-15+$24,000= $45,248,068
  • Mod P000822015-06-19+$887= $45,248,955
  • Mod P000862015-06-19+$11,300= $45,260,255
  • Mod P000772015-06-29+$7,923= $45,268,178
  • Mod P000912015-07-16+$0= $45,268,178
  • Mod P000172015-08-05-$23,311= $45,244,867
  • Mod P000872015-08-06+$2,185= $45,247,052
  • Mod P000922015-08-24+$2,050= $45,249,102
  • Mod P000932015-08-24+$3,280= $45,252,382
  • Mod P000962015-09-21+$5,800= $45,258,182
  • Mod P001032015-09-28+$1,648= $45,259,830
  • Mod P001082015-10-22+$2,500= $45,262,330
  • Mod P001102015-11-03+$0= $45,262,330
  • Mod P000802015-11-06+$7,000= $45,269,330
  • Mod P000812015-11-06+$174,650= $45,443,980
  • Mod P000902015-11-06+$7,481= $45,451,461
  • Mod P000972015-11-06+$3,407= $45,454,868
  • Mod P001022015-11-06+$826= $45,455,694
  • Mod P001042015-11-06+$26,512= $45,482,206
  • Mod P001062015-11-06+$218= $45,482,424
  • Mod P001122015-11-06+$2,800= $45,485,224
  • Mod P001072015-11-09+$1,795= $45,487,019
  • Mod P001132015-11-17-$12,333= $45,474,686
  • Mod P000292015-11-18+$0= $45,474,686
  • Mod P000592015-11-20+$13,836= $45,488,522
  • Mod P000882015-12-08+$7,261= $45,495,783
  • Mod P000892015-12-08+$9,467= $45,505,250
  • Mod P000572015-12-15+$3,364= $45,508,614
  • Mod P001012015-12-15+$652= $45,509,266
  • Mod P001142015-12-15+$1,860= $45,511,126
  • Mod P001152015-12-15+$2,864= $45,513,990
  • Mod P000732015-12-16+$6,350= $45,520,340
  • Mod P000982016-01-13-$6,883= $45,513,457
  • Mod P001002016-01-13-$2,231= $45,511,226
  • Mod P001162016-01-13+$3,790= $45,515,016
  • Mod P001112016-01-14+$3,598= $45,518,614
  • Mod P001202016-01-28+$1,943= $45,520,557
  • Mod P001212016-01-29+$3,150= $45,523,707
  • Mod P001222016-02-05+$7,000= $45,530,707
  • Mod P001232016-02-10+$958= $45,531,665
  • Mod P001252016-02-10+$7,150= $45,538,815
  • Mod P001312016-02-10+$7,285= $45,546,100
  • Mod P001262016-02-12+$650= $45,546,750
  • Mod P001192016-02-15+$7,949= $45,554,699
  • Mod P001282016-02-18+$1,810= $45,556,509
  • Mod P001272016-02-22+$2,536= $45,559,045
  • Mod P001322016-02-29+$7,608= $45,566,653
  • Mod P001242016-03-02+$14,940= $45,581,593
  • Mod P001372016-03-04+$2,969= $45,584,562
  • Mod P001382016-03-08+$26,019= $45,610,581
  • Mod P001342016-03-09+$4,537= $45,615,118
  • Mod P001412016-03-09+$5,170= $45,620,288
  • Mod P001292016-03-14+$5,446= $45,625,734
  • Mod P001302016-03-15+$7,357= $45,633,091
  • Mod P001362016-03-15+$4,369= $45,637,460
  • Mod P001392016-03-15+$2,625= $45,640,085
  • Mod P001422016-03-15+$3,380= $45,643,465
  • Mod P001442016-03-18+$2,500= $45,645,965
  • Mod P001332016-03-23-$383= $45,645,582
  • Mod P001462016-03-23+$0= $45,645,582
  • Mod P001482016-03-23+$3,075= $45,648,657
  • Mod P000642016-03-30+$5,267= $45,653,924
  • Mod P001352016-03-31+$3,461= $45,657,385
  • Mod P001432016-04-05+$14,183= $45,671,568
  • Mod P001492016-04-05+$19,514= $45,691,082
  • Mod P001502016-04-05+$1,050= $45,692,132
  • Mod P001512016-04-05+$24,259= $45,716,391
  • Mod P001522016-04-05+$1,217= $45,717,608
  • Mod P001532016-04-05+$6,806= $45,724,414
  • Mod P001542016-04-05+$2,632= $45,727,046
  • Mod P001552016-04-11+$3,192= $45,730,238
  • Mod P001562016-04-11+$12,978= $45,743,216
  • Mod P001592016-04-11+$1,737= $45,744,953
  • Mod P001602016-04-18+$1,047= $45,746,000
  • Mod P001612016-04-18+$8,686= $45,754,686
  • Mod P001692016-07-06+$531,150= $46,285,836
  • Mod P001702017-07-21+$1,167,850= $47,453,686
  • Mod P001712018-12-19-$4,659= $47,449,027
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2013-09-30+$44,374,390$44,374,390BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00001· CHANGE ORDER2014-04-02+$3,000$44,377,390BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00002· CHANGE ORDER2014-04-07+$48,000$44,425,390BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00004· CHANGE ORDER2014-06-16+$65,000$44,490,390BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00005· CHANGE ORDER2014-06-23+$17,969$44,508,359BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00006· CHANGE ORDER2014-06-23+$10,000$44,518,359BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00007· CHANGE ORDER2014-07-17+$0$44,518,359BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-08-18+$0$44,518,359BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00009· CHANGE ORDER2014-09-15+$4,609$44,522,968BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00010· CHANGE ORDER2014-09-29+$15,000$44,537,968BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00011· CHANGE ORDER2014-10-02−$99,000$44,438,968BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-10-14+$17,297$44,456,265BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00014· CHANGE ORDER2014-10-17+$25,000$44,481,265BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00016· CHANGE ORDER2014-10-24+$23,399$44,504,664BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00019· CHANGE ORDER2014-11-03+$6,500$44,511,164BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00018· CHANGE ORDER2014-11-06+$11,300$44,522,464BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00020· CHANGE ORDER2014-11-13+$26,500$44,548,964BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00024· CHANGE ORDER2014-12-30+$98,400$44,647,364BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-01-15+$8,878$44,656,242BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-01-15+$0$44,656,242BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-01-20−$1,705$44,654,537BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00032· CHANGE ORDER2015-01-20+$25,000$44,679,537BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-01-27+$3,158$44,682,695BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-01-27+$2,273$44,684,968BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-01-27+$16,259$44,701,227BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00028· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-01-27+$7,020$44,708,247BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-01-27+$850$44,709,096BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00033· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-01-27+$17,372$44,726,468BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00034· CHANGE ORDER2015-01-27−$50,000$44,676,468BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00038· CHANGE ORDER2015-01-27+$67,643$44,744,111BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00030· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-01-28+$16,385$44,760,496BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00040· CHANGE ORDER2015-01-28+$0$44,760,496BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00041· DEFINITIZE CHANGE ORDER2015-02-11+$12,601$44,773,097BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00035· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-02-17+$2,923$44,776,020BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00046· DEFINITIZE CHANGE ORDER2015-02-17+$5,908$44,781,928BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00052· CHANGE ORDER2015-02-19+$5,000$44,786,928BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00054· CHANGE ORDER2015-03-04+$10,000$44,796,928BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00049· DEFINITIZE CHANGE ORDER2015-03-11+$2,867$44,799,795BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00039· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-03-16+$9,680$44,809,475BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00050· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-03-16−$6,508$44,802,967BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00053· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-03-16+$36,987$44,839,954BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00055· CHANGE ORDER2015-03-18+$1,500$44,841,454BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00060· CHANGE ORDER2015-03-20+$5,000$44,846,454BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00056· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-03-27+$8,154$44,854,608BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00062· CHANGE ORDER2015-03-31+$75,000$44,929,608BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00045· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-04-17+$2,381$44,931,989BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00042· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-04-22+$3,600$44,935,589BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00048· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-04-22+$12,199$44,947,787BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00074· CHANGE ORDER2015-04-29+$11,979$44,959,766BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00071· CHANGE ORDER2015-05-01+$18,000$44,977,766BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00063· CHANGE ORDER2015-05-05+$84,500$45,062,266BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00069· CHANGE ORDER2015-05-05+$95,000$45,157,266BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00058· CHANGE ORDER2015-05-08+$7,500$45,164,766BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00065· CHANGE ORDER2015-05-08+$1,200$45,165,966BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00066· CHANGE ORDER2015-05-08+$4,000$45,169,966BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00076· CHANGE ORDER2015-05-13+$12,000$45,181,966BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00068· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-06-01+$4,144$45,186,110BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00070· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-06-01+$2,843$45,188,953BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00083· CHANGE ORDER2015-06-10+$915$45,189,868BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00084· CHANGE ORDER2015-06-15+$34,200$45,224,068BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00085· CHANGE ORDER2015-06-15+$24,000$45,248,068BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00082· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-06-19+$887$45,248,955BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00086· CHANGE ORDER2015-06-19+$11,300$45,260,255BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00077· DEFINITIZE CHANGE ORDER2015-06-29+$7,923$45,268,178BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00091· CHANGE ORDER2015-07-16+$0$45,268,178BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00017· DEFINITIZE CHANGE ORDER2015-08-05−$23,311$45,244,867BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00087· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-08-06+$2,185$45,247,052BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00092· CHANGE ORDER2015-08-24+$2,050$45,249,102BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00093· CHANGE ORDER2015-08-24+$3,280$45,252,382BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00096· CHANGE ORDER2015-09-21+$5,800$45,258,182BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00103· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-09-28+$1,648$45,259,830BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00108· CHANGE ORDER2015-10-22+$2,500$45,262,330BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00110· OTHER ADMINISTRATIVE ACTION2015-11-03+$0$45,262,330BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00080· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-11-06+$7,000$45,269,330BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00081· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-11-06+$174,650$45,443,980BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00090· DEFINITIZE CHANGE ORDER2015-11-06+$7,481$45,451,461BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00097· CHANGE ORDER2015-11-06+$3,407$45,454,868BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00102· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-11-06+$826$45,455,694BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00104· DEFINITIZE CHANGE ORDER2015-11-06+$26,512$45,482,206BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00106· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-11-06+$218$45,482,424BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00112· CHANGE ORDER2015-11-06+$2,800$45,485,224BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00107· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-11-09+$1,795$45,487,019BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00113· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-11-17−$12,333$45,474,686BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00029· CHANGE ORDER2015-11-18+$0$45,474,686BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00059· CHANGE ORDER2015-11-20+$13,836$45,488,522BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00088· DEFINITIZE CHANGE ORDER2015-12-08+$7,261$45,495,783BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00089· DEFINITIZE CHANGE ORDER2015-12-08+$9,467$45,505,250BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00057· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-12-15+$3,364$45,508,614BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00101· DEFINITIZE CHANGE ORDER2015-12-15+$652$45,509,266BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00114· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-12-15+$1,860$45,511,126BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00115· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-12-15+$2,864$45,513,990BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00073· CHANGE ORDER2015-12-16+$6,350$45,520,340BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00098· DEFINITIZE CHANGE ORDER2016-01-13−$6,883$45,513,457BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00100· DEFINITIZE CHANGE ORDER2016-01-13−$2,231$45,511,226BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00116· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-01-13+$3,790$45,515,016BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00111· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-01-14+$3,598$45,518,614BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00120· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-01-28+$1,943$45,520,557BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00121· CHANGE ORDER2016-01-29+$3,150$45,523,707BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00122· CHANGE ORDER2016-02-05+$7,000$45,530,707BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00123· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-02-10+$958$45,531,665BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00125· CHANGE ORDER2016-02-10+$7,150$45,538,815BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00131· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-02-10+$7,285$45,546,100BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00126· CHANGE ORDER2016-02-12+$650$45,546,750BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00119· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-02-15+$7,949$45,554,699BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00128· CHANGE ORDER2016-02-18+$1,810$45,556,509BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00127· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-02-22+$2,536$45,559,045BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00132· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-02-29+$7,608$45,566,653BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00124· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-03-02+$14,940$45,581,593BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00137· CHANGE ORDER2016-03-04+$2,969$45,584,562BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00138· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-03-08+$26,019$45,610,581BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00134· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-03-09+$4,537$45,615,118BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00141· CHANGE ORDER2016-03-09+$5,170$45,620,288BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00129· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-03-14+$5,446$45,625,734BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00130· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-03-15+$7,357$45,633,091BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00136· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-03-15+$4,369$45,637,460BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00139· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-03-15+$2,625$45,640,085BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00142· CHANGE ORDER2016-03-15+$3,380$45,643,465BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00144· CHANGE ORDER2016-03-18+$2,500$45,645,965BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00133· DEFINITIZE CHANGE ORDER2016-03-23−$383$45,645,582BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00146· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-03-23+$0$45,645,582BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00148· CHANGE ORDER2016-03-23+$3,075$45,648,657BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00064· DEFINITIZE CHANGE ORDER2016-03-30+$5,267$45,653,924BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00135· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-03-31+$3,461$45,657,385BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00143· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-04-05+$14,183$45,671,568BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00149· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-04-05+$19,514$45,691,082BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00150· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-04-05+$1,050$45,692,132BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00151· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-04-05+$24,259$45,716,391BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00152· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-04-05+$1,217$45,717,608BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00153· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-04-05+$6,806$45,724,414BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00154· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-04-05+$2,632$45,727,046BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00155· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-04-11+$3,192$45,730,238BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00156· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-04-11+$12,978$45,743,216BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00159· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-04-11+$1,737$45,744,953BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00160· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-04-18+$1,047$45,746,000BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00161· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-04-18+$8,686$45,754,686BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00169· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-07-06+$531,150$46,285,836BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00170· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-07-21+$1,167,850$47,453,686BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…
Mod P00171· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-12-19−$4,659$47,449,027BUILDING 101 MENTAL HEALTH SERVICES - PHASE 1, PARKING STRUCTURE AND MAIN ENTRY DRIVE AT 1660 SOUTH COLUMBIAN…

Related awards · 1

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other recipients under Y1LZ from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)

AwardRecipientOfficeNet obligationsFY
VA101F17C3132BILLY W. JARRETT CONSTRUCTION COMPANY, INC.OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$6,952,617FY2017

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA101F13C0071_3600_-NONE-_-NONE- · retrieved 2026-09-26.